| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$10,000.00 |
$5,000.00 |
$19,200.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 10,953 | CY |
$5.00 |
$9.00 |
$8.00 |
| 3 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$10,000.00 |
$5,000.00 |
$14,681.00 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 7,207 | LF |
$2.00 |
$1.75 |
$1.23 |
| 5 | 221(F) 0100 |
TEMPORARY SILT DIKE | 165 | LF |
$8.00 |
$7.00 |
$11.50 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 13,629 | SY |
$1.75 |
$2.00 |
$1.98 |
| 7 | 233(A) 2817 |
VEGETATIVE MULCHING | 10 | AC |
$350.00 |
$750.00 |
$324.00 |
| 8 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 2,696 | CY |
$35.00 |
$50.00 |
$44.00 |
| 9 | 325 5271 |
SEPARATOR FABRIC | 19,184 | SY |
$1.25 |
$1.20 |
$1.35 |
| 10 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 1,160 | TON |
$20.00 |
$26.50 |
$24.75 |
| 11 | 408 5774 |
PRIME COAT | 2,528 | GAL |
$3.00 |
$5.00 |
$0.5000 |
| 12 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 2,369 | TON |
$69.00 |
$70.00 |
$64.50 |
| 13 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 2,012 | TON |
$75.00 |
$75.00 |
$74.00 |
| 14 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$300.00 |
$150.00 |
$450.00 |
| 15 | 610(B) 0604 |
6" CONCRETE DRIVEWAY | 72 | SY |
$60.00 |
$50.00 |
$85.00 |
| 16 | 613(A) 0491 |
18" R.C.PIPE CLASS III | 30 | LF |
$75.00 |
$50.00 |
$123.32 |
| 17 | 613(B) 0689 |
18" CORR. GALV. STEEL PIPE | 90 | LF |
$25.00 |
$34.00 |
$40.00 |
| 18 | 613(L) 5726 |
18" PREFAB. CULVERT END SECTION, ROUND | 2 | EA |
$350.00 |
$760.00 |
$726.00 |
| 19 | 613(M) 7186 |
TYPE A4 CULVERT END TREATMENT | 4 | EA |
$800.00 |
$850.00 |
$1,850.00 |
| 20 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 10,567 | SY |
$2.00 |
$0.1000 |
$1.90 |
| 21 | 619(B) 4766 |
REMOVAL OF CONCRETE DRIVEWAY | 103 | SY |
$10.00 |
$5.00 |
$24.37 |
| 22 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 4,853 | LF |
$3.50 |
$1.00 |
$0.7500 |
| 23 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 5,714 | LF |
$17.00 |
$17.00 |
$17.00 |
| 24 | 623(F) 4446 |
GUARDRAIL ANCHOR UNIT (TYPE A) | 2 | EA |
$1,500.00 |
$1,600.00 |
$1,650.00 |
| 25 | 623(F) 4447 |
GUARDRAIL ANCHOR UNIT (TYPE B) | 2 | EA |
$1,000.00 |
$500.00 |
$497.00 |
| 26 | 623(F) 6263 |
GUARDRAIL ANCHOR UNIT (TYPE X) | 4 | EA |
$2,500.00 |
$1,800.00 |
$1,825.00 |
| 27 | 629(A) 4958 |
MAILBOX INSTALLATION-SINGLE | 2 | EA |
$100.00 |
$93.00 |
$50.00 |
| 28 | 629(B) 4959 |
MAILBOX INSTALLATION-MULTIPLE | 2 | EA |
$200.00 |
$180.00 |
$93.50 |
| 29 | 629(C) 4960 |
MAILBOX | 6 | EA |
$40.00 |
$38.00 |
$27.50 |
| 30 | 629(D) 4961 |
REMOVAL OF MAILBOX INSTALLATION | 6 | EA |
$10.00 |
$27.00 |
$78.00 |
| 31 | 805(A) 8722 |
(PL)REMOVAL OF EXISTING SIGNS | 1 | LSUM |
$300.00 |
$55.00 |
$255.35 |
| 32 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 25.72 | SF |
$20.00 |
$16.00 |
$17.66 |
| 33 | 851(C) 8324 |
2" SQUARE TUBE POST | 65 | LF |
$15.00 |
$11.00 |
$13.25 |
| 34 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$5,000.00 |
$6,000.00 |
$2,422.00 |
| 35 | 504(A) 1304 |
APPROACH SLAB | 120 | SY |
$170.00 |
$200.00 |
$274.00 |
| 36 | 504(C) 6250 |
SEALED EXPANSION JOINT | 50 | LF |
$250.00 |
$280.00 |
$385.22 |
| 37 | 509 6386 |
SILICONE CONSTRUCTION JOINT | 432 | LF |
$10.00 |
$10.00 |
$11.00 |
| 38 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$60,000.00 |
$15,000.00 |
$32,976.00 |
| 39 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 18 | SY |
$450.00 |
$200.00 |
$661.00 |
| 40 | 523(C) 6570 |
DECK AREA SEALED (FLOODCOATS) | 1,044 | SY |
$15.00 |
$10.00 |
$16.50 |
| 41 | 619(B) 2505 |
REMOVAL OF BRIDGE ITEMS | 2 | EA |
$5,000.00 |
$6,500.00 |
$2,198.00 |
| 42 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$10,000.00 |
$19,000.00 |
$18,500.00 |
| 43 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$5,000.00 |
$1,000.00 |
| 44 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$75,000.00 |
$27,000.00 |
$45,000.00 |