BRIDGE AND APPROACHES - DIVISION IV COUNTY ROAD (EW-28): OVER BIRD'S NEST CREEK , AT US-77 NEAR TONKAWA . PROJECT LENGTH = 0.245 MILE
- Let date
- Thursday, May 21, 2015
- Contract
- 150164
- J/P numbers
- 25549(05)
- District
- Division 4
- County
- Kay
- Highway
- Limits
- BRIDGE AND APPROACHES - DIVISION IV COUNTY ROAD (EW-28): OVER BIRD'S NEST CREEK , AT US-77 NEAR TONKAWA . PROJECT LENGTH = 0.245 MILE
- Project number
- STP-136D(179)CI
Bidders 10
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $601,273 | | |
| 1 |
H & H BRIDGE COMPANY Low bidder |
$475,506 |
-20.9% |
|
| 2 |
K & R BUILDERS, INC. |
$509,109 |
-15.3% |
+7.1% |
| 3 |
L & M Contractors, Inc. |
$549,318 |
-8.6% |
+15.5% |
| 4 |
Reece Construction Co, Inc. |
$559,426 |
-7.0% |
+17.6% |
| 5 |
B & B BRIDGE COMPANY, LLC |
$580,379 |
-3.5% |
+22.1% |
| 6 |
Bridges, Inc. DBA Scudder Bridge Co. |
$609,521 |
+1.4% |
+28.2% |
| 7 |
RRY SERVICES LLC |
$620,938 |
+3.3% |
+30.6% |
| 8 |
King Construction CO., INC. |
$633,084 |
+5.3% |
+33.1% |
| 9 |
Dondlinger & Sons Construction Co., Inc. |
$647,366 |
+7.7% |
+36.1% |
| 10 |
WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES |
$649,744 |
+8.1% |
+36.6% |
Bid tab: unit prices 36 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 H & H BRIDGE CO… | #2 K & R BUILDERS,… | #3 L & M Contracto… | #4 Reece Construct… | #5 B & B BRIDGE CO… | #6 Bridges, Inc. D… | #7 RRY SERVICES LLC | #8 King Constructi… |
| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$8,000.00 |
$5,000.00 |
$5,000.00 |
$5,000.00 |
$4,718.07 |
$4,718.07 |
$5,000.00 |
$11,000.00 |
$4,718.07 |
| 2 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$60,000.00 |
$66,000.00 |
$58,400.00 |
$70,000.00 |
$68,131.13 |
$68,131.13 |
$68,500.00 |
$100,000.00 |
$68,131.13 |
| 3 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$20,000.00 |
$3,000.00 |
$6,500.00 |
$5,500.00 |
$5,032.60 |
$5,032.60 |
$5,000.00 |
$5,000.00 |
$5,032.60 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 500 | LF |
$1.90 |
$1.50 |
$2.20 |
$1.95 |
$1.33 |
$1.95 |
$3.00 |
$2.00 |
$1.33 |
| 5 | 221(F) 0100 |
TEMPORARY SILT DIKE | 360 | LF |
$8.20 |
$4.00 |
$7.75 |
$6.95 |
$6.22 |
$6.95 |
$8.00 |
$7.00 |
$6.22 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 9,100 | SY |
$2.00 |
$1.10 |
$1.31 |
$1.10 |
$1.14 |
$1.10 |
$1.10 |
$1.10 |
$1.14 |
| 7 | 233(A) 2817 |
VEGETATIVE MULCHING | 1.88 | AC |
$500.00 |
$449.00 |
$200.00 |
$449.00 |
$388.00 |
$449.00 |
$449.00 |
$449.00 |
$388.00 |
| 8 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 723 | TON |
$35.00 |
$32.00 |
$35.67 |
$31.00 |
$31.00 |
$27.45 |
$45.00 |
$36.00 |
$27.11 |
| 9 | 509(D) 0325 |
CLASS C CONCRETE | 20 | CY |
$310.00 |
$150.00 |
$290.00 |
$200.00 |
$289.00 |
$200.00 |
$375.00 |
$250.00 |
$600.00 |
| 10 | 613(B) 0690 |
24" CORR. GALV. STEEL PIPE | 56 | LF |
$35.00 |
$40.00 |
$32.00 |
$25.00 |
$28.00 |
$28.20 |
$35.00 |
$35.00 |
$30.35 |
| 11 | 613(M) 7187 |
TYPE B4 CULVERT END TREATMENT | 2 | EA |
$1,200.00 |
$1,000.00 |
$885.00 |
$1,300.00 |
$1,734.00 |
$1,100.00 |
$1,250.00 |
$2,000.00 |
$200.00 |
| 12 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$2,500.00 |
$2,000.00 |
$4,750.00 |
$2,000.00 |
$1,572.69 |
$1,572.69 |
$1,600.00 |
$4,000.00 |
$1,572.69 |
| 13 | 623(F) 4446 |
GUARDRAIL ANCHOR UNIT (TYPE A) | 4 | EA |
$1,800.00 |
$1,650.00 |
$1,350.00 |
$1,300.00 |
$1,175.00 |
$1,175.00 |
$1,175.00 |
$1,300.00 |
$1,175.00 |
| 14 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$1,800.00 |
$1,650.00 |
$1,900.00 |
$1,800.00 |
$1,650.00 |
$1,650.00 |
$1,650.00 |
$1,800.00 |
$1,650.00 |
| 15 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 84 | CY |
$23.00 |
$20.00 |
$9.50 |
$30.00 |
$21.00 |
$30.00 |
$20.00 |
$25.00 |
$70.00 |
| 16 | 501(D) 6353 |
UNCLASSIFIED BACKFILL | 82 | CY |
$25.00 |
$25.00 |
$10.50 |
$40.00 |
$32.00 |
$40.00 |
$22.00 |
$25.00 |
$80.00 |
| 17 | 503(A) 1313 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 416.67 | LF |
$250.00 |
$190.00 |
$190.00 |
$215.00 |
$232.00 |
$300.00 |
$285.00 |
$250.00 |
$244.00 |
| 18 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 275 | LF |
$80.00 |
$90.00 |
$73.00 |
$70.00 |
$119.00 |
$70.00 |
$70.00 |
$80.00 |
$65.00 |
| 19 | 506(A) 1322 |
STRUCTURAL STEEL | 346 | LB |
$3.80 |
$4.00 |
$3.00 |
$5.00 |
$4.00 |
$3.00 |
$4.50 |
$3.00 |
$5.00 |
| 20 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 4 | EA |
$900.00 |
$1,000.00 |
$785.00 |
$800.00 |
$902.00 |
$1,200.00 |
$1,200.00 |
$1,000.00 |
$4,500.00 |
| 21 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 4 | EA |
$1,000.00 |
$1,000.00 |
$785.00 |
$800.00 |
$902.00 |
$1,200.00 |
$1,200.00 |
$1,000.00 |
$4,500.00 |
| 22 | 509(A) 1326 |
CLASS AA CONCRETE | 80.6 | CY |
$620.00 |
$500.00 |
$620.00 |
$775.00 |
$835.00 |
$789.25 |
$675.00 |
$650.00 |
$850.00 |
| 23 | 509(B) 1328 |
CLASS A CONCRETE | 53.8 | CY |
$650.00 |
$500.00 |
$642.50 |
$775.00 |
$666.00 |
$789.25 |
$875.00 |
$650.00 |
$850.00 |
| 24 | 511(A) 1332 |
REINFORCING STEEL | 26,410 | LB |
$1.00 |
$1.50 |
$0.9200 |
$1.00 |
$0.8000 |
$0.9000 |
$1.00 |
$1.00 |
$1.20 |
| 25 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 210 | LF |
$35.00 |
$21.00 |
$30.10 |
$46.00 |
$36.00 |
$30.00 |
$45.00 |
$40.00 |
$30.00 |
| 26 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 680 | LF |
$40.00 |
$24.00 |
$34.30 |
$51.00 |
$44.00 |
$37.00 |
$55.00 |
$50.00 |
$34.00 |
| 27 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 210 | LF |
$16.00 |
$7.00 |
$12.90 |
$7.00 |
$10.00 |
$22.00 |
$9.00 |
$10.00 |
$10.00 |
| 28 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 680 | LF |
$18.00 |
$8.00 |
$14.70 |
$6.00 |
$10.00 |
$22.00 |
$9.00 |
$10.00 |
$12.00 |
| 29 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 30 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 1,050 | TON |
$40.00 |
$37.00 |
$40.62 |
$37.00 |
$43.00 |
$37.92 |
$56.00 |
$40.00 |
$35.00 |
| 31 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 250 | TON |
$36.00 |
$32.00 |
$36.46 |
$30.00 |
$31.00 |
$27.07 |
$47.00 |
$37.00 |
$45.00 |
| 32 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$7,000.00 |
$7,000.00 |
$6,000.00 |
$5,000.00 |
$4,914.65 |
$4,914.65 |
$5,000.00 |
$12,000.00 |
$21,000.00 |
| 33 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$3,000.00 |
$3,750.00 |
$4,000.00 |
$3,200.00 |
$2,650.00 |
$2,650.00 |
$2,650.00 |
$3,600.00 |
$2,650.00 |
| 34 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$20,000.00 |
$5,000.00 |
$9,000.00 |
$8,600.00 |
$6,350.00 |
$7,200.00 |
$7,900.00 |
$8,000.00 |
$7,200.00 |
| 35 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,500.00 |
$2,400.00 |
$3,800.00 |
$2,400.00 |
$2,000.00 |
$3,000.00 |
$4,500.00 |
$2,500.00 |
$6,000.00 |
| 36 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$50,000.00 |
$26,000.00 |
$35,750.00 |
$40,500.00 |
$39,200.00 |
$41,346.88 |
$32,000.00 |
$55,000.00 |
$54,046.80 |
Showing the first 8 bidders. The Excel and CSV downloads include all 10.