| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$5,000.00 |
$7,000.00 |
$3,600.00 |
$5,000.00 |
$5,000.00 |
$5,796.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 705 | CY |
$4.50 |
$10.38 |
$7.15 |
$6.00 |
$13.00 |
$7.06 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 1,163 | CY |
$6.00 |
$12.00 |
$13.50 |
$10.00 |
$13.00 |
$11.00 |
| 4 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$4,500.00 |
$6,000.00 |
$2,500.00 |
$5,000.00 |
$6,000.00 |
$4,830.00 |
| 5 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,360 | LF |
$2.00 |
$1.80 |
$1.99 |
$1.99 |
$2.00 |
$1.34 |
| 6 | 221(F) 0100 |
TEMPORARY SILT DIKE | 140 | LF |
$8.00 |
$9.00 |
$9.95 |
$9.95 |
$10.00 |
$7.89 |
| 7 | 230(A) 2806 |
SOLID SLAB SODDING | 2,900 | SY |
$2.00 |
$2.34 |
$1.95 |
$1.95 |
$2.00 |
$2.19 |
| 8 | 233(A) 2817 |
VEGETATIVE MULCHING | 0.6 | AC |
$500.00 |
$200.00 |
$199.00 |
$199.00 |
$215.00 |
$1,200.00 |
| 9 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 459 | TON |
$20.00 |
$38.57 |
$46.50 |
$35.00 |
$37.00 |
$38.00 |
| 10 | 509(D) 0325 |
CLASS C CONCRETE | 20 | CY |
$270.00 |
$300.00 |
$180.00 |
$350.00 |
$200.00 |
$333.00 |
| 11 | 601(A) 0297 |
TYPE I PLAIN RIPRAP | 150 | TON |
$21.50 |
$52.18 |
$50.00 |
$50.00 |
$50.00 |
$48.00 |
| 12 | 623(F) 4446 |
GUARDRAIL ANCHOR UNIT (TYPE A) | 4 | EA |
$1,300.00 |
$1,560.00 |
$1,300.00 |
$1,300.00 |
$1,800.00 |
$1,300.00 |
| 13 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$1,500.00 |
$1,717.50 |
$1,421.25 |
$1,431.25 |
$1,800.00 |
$1,431.25 |
| 14 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$7,400.00 |
$3,500.00 |
$2,176.25 |
$2,176.12 |
$2,100.00 |
$1,950.00 |
| 15 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 168 | CY |
$17.00 |
$11.00 |
$35.00 |
$35.00 |
$25.00 |
$23.00 |
| 16 | 501(F) 6352 |
GRANULAR BACKFILL | 64 | CY |
$54.00 |
$77.00 |
$75.00 |
$125.00 |
$65.00 |
$70.00 |
| 17 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 238.4 | LF |
$71.00 |
$81.50 |
$100.00 |
$85.00 |
$75.00 |
$134.00 |
| 18 | 506(A) 1322 |
STRUCTURAL STEEL | 73,960 | LB |
$2.00 |
$1.88 |
$1.80 |
$2.20 |
$2.36 |
$2.00 |
| 19 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 3 | EA |
$860.00 |
$1,100.00 |
$930.00 |
$1,800.00 |
$1,300.00 |
$1,152.00 |
| 20 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 3 | EA |
$1,075.00 |
$1,100.00 |
$1,200.00 |
$1,800.00 |
$1,300.00 |
$1,152.00 |
| 21 | 509(A) 1326 |
CLASS AA CONCRETE | 67.7 | CY |
$500.00 |
$735.00 |
$870.00 |
$620.00 |
$625.00 |
$1,028.00 |
| 22 | 509(B) 1328 |
CLASS A CONCRETE | 62.8 | CY |
$500.00 |
$685.00 |
$735.00 |
$620.00 |
$675.00 |
$865.00 |
| 23 | 511(A) 1332 |
REINFORCING STEEL | 24,940 | LB |
$1.00 |
$0.9800 |
$1.00 |
$1.00 |
$1.00 |
$0.8000 |
| 24 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 104 | LF |
$30.00 |
$37.10 |
$45.00 |
$37.00 |
$47.00 |
$53.00 |
| 25 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 230 | LF |
$34.50 |
$44.10 |
$58.00 |
$46.00 |
$58.00 |
$68.00 |
| 26 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 104 | LF |
$16.00 |
$15.90 |
$30.00 |
$25.00 |
$10.00 |
$21.00 |
| 27 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 230 | LF |
$17.00 |
$18.90 |
$30.00 |
$23.00 |
$10.00 |
$19.00 |
| 28 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 29 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 570 | TON |
$37.50 |
$45.68 |
$48.00 |
$40.00 |
$51.00 |
$45.00 |
| 30 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 280 | TON |
$33.00 |
$37.57 |
$43.50 |
$35.00 |
$42.00 |
$36.00 |
| 31 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 52 | LF |
$28.00 |
$35.00 |
$25.00 |
$35.00 |
$25.00 |
$15.00 |
| 32 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 22 | LF |
$21.00 |
$65.00 |
$25.00 |
$35.00 |
$25.00 |
$15.00 |
| 33 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$8,000.00 |
$5,000.00 |
$3,000.00 |
$7,500.00 |
$12,500.00 |
$8,630.75 |
| 34 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$6,500.00 |
$6,500.00 |
$5,400.00 |
$5,700.00 |
$5,500.00 |
$5,470.00 |
| 35 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$3,500.00 |
$1,500.00 |
$3,000.00 |
$2,700.00 |
$2,500.00 |
| 36 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$50,000.00 |
$34,000.00 |
$34,000.00 |
$50,900.00 |
$51,000.00 |
$56,700.00 |