Bid tab 140153

Let Apr 17, 2014 · Division 3 · Mcclain Sign up free

‹ Apr 2014 results

GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROAD (NS-305/EW-131/EW-133): AT MULTIPLE LOCATIONS IN DIVISION III. PROJECT LENGTH = 1.245 MILES

Let date
Thursday, April 17, 2014
Contract
140153
J/P numbers
25449(04)
District
Division 3
County
Mcclain
Highway
Limits
GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROAD (NS-305/EW-131/EW-133): AT MULTIPLE LOCATIONS IN DIVISION III. PROJECT LENGTH = 1.245 MILES
Project number
CIRB-144D(131)RB

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,903,563
1 HASKELL LEMON CONSTRUCTION CO. Low bidder $2,044,642 +7.4%
2 MANHATTAN ROAD & BRIDGE COMPANY, LLC $2,063,420 +8.4% +0.9%
3 KLAVER CONSTRUCTION COMPANY, INC. $2,271,298 +19.3% +11.1%
4 Cimarron Construction Company, LLC $2,334,466 +22.6% +14.2%
5 T.J. CAMPBELL CONSTRUCTION CO. $2,618,752 +37.6% +28.1%

Bid tab: unit prices 44 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 HASKELL LEMON C…#2 MANHATTAN ROAD …#3 KLAVER CONSTRUC…#4 Cimarron Constr…#5 T.J. CAMPBELL C…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $5,000.00 $35,000.00 $60,000.00 $125,000.00 $22,000.00 $80,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION33,293CY $5.00 $8.00 $6.60 $6.00 $7.10 $13.00
3202(D) 0184 UNCLASSIFIED BORROW5,782CY $8.00 $9.00 $6.60 $1.00 $1.30 $13.50
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $5,500.00 $25,000.00 $31,000.00 $12,000.00 $16,000.00 $50,000.00
5221(C) 2801 TEMPORARY SILT FENCE808LF $2.00 $2.00 $1.50 $1.44 $1.50 $2.00
6221(F) 0100 TEMPORARY SILT DIKE407LF $8.00 $8.00 $7.25 $7.12 $7.50 $7.00
7230(A) 2806 SOLID SLAB SODDING58,159SY $2.00 $1.50 $1.20 $1.17 $1.35 $2.65
8233(A) 2817 VEGETATIVE MULCHING12.1AC $540.00 $200.00 $355.00 $344.00 $350.00 $1,450.00
9307(A) 4200 FLY ASH968TON $65.00 $80.00 $80.25 $80.00 $90.00 $72.00
10307(E) 4240 CEMENTITIOUS STABILIZED SUBGRADE22,535SY $3.00 $2.50 $2.55 $2.50 $2.80 $4.00
11402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E172.5TON $25.00 $30.00 $26.00 $31.00 $35.00 $35.00
12407(B) 0250 TACK COAT3,350GAL $2.75 $2.50 $2.60 $2.50 $2.75 $3.50
13408 5774 PRIME COAT7,695GAL $4.00 $7.20 $2.60 $7.20 $7.50 $7.50
14411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)4,165TON $70.00 $67.80 $70.00 $67.80 $82.00 $70.00
15411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)2,395TON $80.00 $81.50 $84.00 $81.50 $96.00 $83.00
16412 5267 COLD MILLING PAVEMENT2,220SY $2.00 $4.00 $4.50 $7.50 $7.50 $3.25
17501(A) 0313 STRUCTURAL EXCAVATION UNCLASSIFIED1,125CY $14.50 $15.00 $30.00 $5.00 $17.00 $34.00
18509(A) 0319 CLASS AA CONCRETE97.6CY $450.00 $450.00 $615.00 $406.91 $670.00 $650.00
19509(A) 1326 CLASS AA CONCRETE603.9CY $450.00 $400.00 $495.00 $394.68 $605.00 $650.00
20509(D) 0325 CLASS C CONCRETE20CY $260.00 $200.00 $290.00 $450.00 $250.00 $1,200.00
21511(A) 0332 REINFORCING STEEL13,924LB $0.9000 $1.00 $0.9500 $0.9000 $1.00 $0.5000
22511(A) 1332 REINFORCING STEEL104,845LB $0.9000 $1.00 $0.9500 $0.9000 $1.00 $0.5000
23601(A) 0297 TYPE I PLAIN RIPRAP3,220TON $20.00 $40.00 $37.00 $40.00 $49.00 $65.00
24610(B) 0604 6" CONCRETE DRIVEWAY35SY $50.00 $40.00 $80.00 $75.00 $96.00 $60.00
25613(A) 0494 36" R.C.PIPE CLASS III112LF $90.00 $90.00 $84.00 $86.00 $105.00 $135.00
26613(A) 4500 58" X 36" R.C.PIPE ARCH CLASS A-III58LF $200.00 $200.00 $160.00 $248.00 $295.00 $245.00
27613(A) 4502 73" X 45" R.C.PIPE ARCH CLASS A-III144LF $230.00 $300.00 $215.00 $374.00 $425.00 $360.00
28613(B) 0690 24" CORR. GALV. STEEL PIPE290LF $35.00 $30.00 $33.00 $38.00 $48.00 $30.00
29613(L) 4546 58" X 36" PREFAB. CULVERT END SECTION, ARCH2EA $2,500.00 $3,000.00 $2,350.00 $5,000.00 $2,700.00 $3,500.00
30613(L) 4559 73" X 45" PREFAB. CULVERT END SECTION, ARCH6EA $3,000.00 $5,000.00 $1,100.00 $8,000.00 $3,200.00 $4,000.00
31613(L) 5734 36" PREFAB. CULVERT END SECTION, ROUND4EA $1,265.00 $1,500.00 $1,035.00 $1,500.00 $1,800.00 $1,500.00
32613(M) 7187 TYPE B4 CULVERT END TREATMENT12EA $1,100.00 $1,000.00 $675.00 $1,200.00 $1,400.00 $1,500.00
33619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $15,000.00 $18,000.00 $15,250.00 $35,000.00 $17,000.00 $6,500.00
34619(B) 4728 REMOVAL OF ASPHALT PAVEMENT21,850SY $4.00 $2.00 $3.15 $6.25 $5.95 $1.90
35619(C) 0924 SAWING PAVEMENT200LF $3.00 $10.00 $8.00 $10.00 $5.00 $3.50
36624(A) 4281 FENCE-STYLE WWF270LF $6.50 $10.00 $7.25 $20.00 $12.00 $9.50
37850(A) 8110 SHEET ALUMINUM SIGNS36.26SF $16.00 $25.00 $24.00 $22.00 $27.00 $30.00
38851(C) 8327 2 1/4" SQUARE TUBE POST105LF $9.00 $7.50 $7.25 $8.00 $8.00 $11.00
39855(A) 8812 TRAFFIC STRIPE(PLASTIC)(4" WIDE)26,720LF $0.4800 $0.7000 $0.6500 $0.5400 $0.7500 $0.6500
40855(A) 8814 TRAFFIC STRIPE(PLASTIC)(8" WIDE)112LF $1.36 $3.00 $4.00 $0.9000 $3.50 $1.10
41880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $15,000.00 $5,000.00 $4,250.00 $5,400.00 $4,900.00 $15,000.00
42642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $15,000.00 $30,000.00 $6,000.00 $65,000.00 $28,000.00 $22,000.00
43220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $10,000.00 $2,500.00 $1,842.16 $7,000.00 $16,000.00 $2,000.00
44641 1552 MOBILIZATION1LSUM $114,500.00 $75,000.00 $130,000.00 $184,529.21 $44,500.00 $25,000.00