Bid tab 130236

Let Jul 25, 2013 · Division 3 · Garvin Sign up free

‹ Jul 2013 results

BRIDGE AND APPROACHES SH -74: OVER UNNAMED CREEK, 6.6 MI NORTH OF THE CARTER COUNTY C /L. PROJECT LENGTH = 0.132 MILES

Let date
Thursday, July 25, 2013
Contract
130236
J/P numbers
23263(04)
District
Division 3
County
Garvin
Highway
Limits
BRIDGE AND APPROACHES SH -74: OVER UNNAMED CREEK, 6.6 MI NORTH OF THE CARTER COUNTY C /L. PROJECT LENGTH = 0.132 MILES
Project number
SSP-125C(134)SS

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$759,846
1 MANHATTAN ROAD & BRIDGE COMPANY, LLC Low bidder $746,245 -1.8%
2 CP3 ENTERPRISES, INC. $817,322 +7.6% +9.5%
3 KLAVER CONSTRUCTION COMPANY, INC. $970,117 +27.7% +30.0%

Bid tab: unit prices 47 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 MANHATTAN ROAD …#2 CP3 ENTERPRISES…#3 KLAVER CONSTRUC…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $10,000.00 $10,000.00 $9,744.00 $12,150.00
2202(A) 0183 UNCLASSIFIED EXCAVATION19,082CY $6.00 $5.25 $5.70 $7.41
3202(D) 0184 UNCLASSIFIED BORROW500CY $6.00 $15.00 $9.74 $8.41
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $16,000.00 $7,000.00 $14,616.00 $7,907.00
5221(C) 2801 TEMPORARY SILT FENCE600LF $2.00 $2.00 $2.29 $1.88
6221(G) 0150 TEMPORARY ROCK FILTER DAM TYPE 112CY $90.00 $80.00 $95.00 $78.00
7230(A) 2806 SOLID SLAB SODDING16,746SY $1.25 $1.45 $1.80 $1.39
8232(B) 2814 SEEDING METHOD B3.46AC $353.00 $990.00 $1,153.24 $988.00
9233(A) 2817 VEGETATIVE MULCHING3.46AC $351.00 $890.00 $1,036.52 $888.00
10234(A) 2824 FERTILIZING (10-20-10)1.68TON $642.00 $825.00 $1,013.73 $799.00
11241 2832 MOWING3.46AC $70.00 $125.00 $140.96 $124.00
12303(B) 2110 AGGREGATE BASE TYPE B645CY $35.00 $40.00 $44.62 $51.00
13307(A) 4200 FLY ASH175TON $70.00 $85.00 $96.27 $82.00
14307(E) 4240 CEMENTITIOUS STABILIZED SUBGRADE3,236SY $2.00 $3.00 $4.87 $4.00
15325 5271 SEPARATOR FABRIC3,301SY $1.50 $2.00 $3.97 $1.25
16402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E270TON $22.00 $22.00 $23.07 $32.00
17407(B) 0250 TACK COAT374GAL $2.40 $2.60 $2.97 $4.00
18408 5774 PRIME COAT1,867GAL $4.00 $7.25 $7.96 $4.00
19411(B) 5940 SUPERPAVE, TYPE S3(PG 70-28 OK)349TON $90.00 $92.00 $100.49 $104.00
20411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)353TON $82.00 $87.00 $94.90 $97.00
21411(C) 5955 SUPERPAVE, TYPE S4(PG 70-28 OK)289TON $85.00 $103.00 $111.65 $113.50
22501(A) 0313 STRUCTURAL EXCAVATION UNCLASSIFIED59CY $20.00 $40.00 $24.36 $5.00
23509(A) 0319 CLASS AA CONCRETE376CY $465.00 $475.00 $393.41 $313.00
24509(D) 0325 CLASS C CONCRETE206CY $260.00 $225.00 $242.99 $300.00
25511(A) 0332 REINFORCING STEEL49,511LB $1.10 $1.00 $0.8700 $0.8500
26601(A) 0297 TYPE I PLAIN RIPRAP882TON $45.00 $38.00 $45.38 $48.00
27613(H) 0500 8" PERFORATED PIPE UNDERDRAIN ROUND500LF $12.00 $8.00 $18.10 $25.00
28613(I) 1097 8" NON-PERF.PIPE UNDERDRAIN RND.125LF $11.00 $8.50 $15.67 $25.00
29613(Q) 5946 OUTLET LATERAL HEADWALL2EA $500.00 $295.00 $14,174.48 $2,500.00
30613(T) 1187 STANDARD BEDDING MATERIAL, CLASS C25CY $34.00 $31.00 $62.99 $45.00
31613(U) 1100 PIPE UNDERDRAIN COVER MAT'L.13CY $34.00 $40.00 $87.21 $45.00
32613(V) 1180 TRENCH EXCAVATION150CY $12.00 $7.50 $16.34 $12.00
33619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $2,500.00 $2,500.00 $3,775.80 $8,050.00
34619(B) 4728 REMOVAL OF ASPHALT PAVEMENT1,789SY $3.30 $3.75 $4.87 $5.00
35619(C) 0924 SAWING PAVEMENT100LF $5.00 $4.00 $12.18 $15.00
36624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)1,101LF $6.50 $4.50 $10.13 $10.00
37619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $10,000.00 $8,000.00 $23,385.60 $29,534.00
38856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)4,500LF $0.4400 $1.25 $1.49 $1.22
39880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF10,200SD $0.2300 $0.0500 $0.0500 $0.0400
40880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF600SD $0.5600 $0.1100 $0.1200 $0.1000
41880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF420SD $1.01 $1.05 $1.22 $1.00
42880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)660SD $0.4200 $0.1100 $0.1200 $0.1000
43880(E) 8860 WARNING LIGHTS(TYPE A)1,320SD $0.1100 $1.05 $1.22 $1.00
44882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN420SD $10.48 $4.15 $4.87 $4.00
45642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $8,935.00 $7,000.00 $3,675.92 $6,500.00
46220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $4,000.00 $1,964.00 $2,557.80 $4,500.00
47641 1552 MOBILIZATION1LSUM $59,805.00 $57,000.00 $46,324.60 $217,775.00