BRIDGE AND APPROACHES COUNTY ROAD (NS-310)/BROADWAY BLVD .): OVER COTTONWOOD CREEK 0.5 MILES SOUTH AND 3.5 MILES WEST OF THE I -35/US-77 JCT. PROJECT LENGTH = 0.302 MILES

Let date
Thursday, March 15, 2012
Contract
120134
J/P numbers
23018(04)
District
Division 4
County
Logan
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (NS-310)/BROADWAY BLVD .): OVER COTTONWOOD CREEK 0.5 MILES SOUTH AND 3.5 MILES WEST OF THE I -35/US-77 JCT. PROJECT LENGTH = 0.302 MILES
Project number
STP-142C(119)AG

Bidders 7

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,079,425
1 BRIDGECO CONTRACTORS, INC. Low bidder $1,115,637 +3.4%
2 K & R BUILDERS, INC. $1,130,201 +4.7% +1.3%
3 SEWELL BROS., INC. $1,162,760 +7.7% +4.2%
4 Reece Construction Co, Inc. $1,251,884 +16.0% +12.2%
5 Allen Contracting, Inc. $1,322,731 +22.5% +18.6%
6 Cimarron Construction Company, LLC $1,405,727 +30.2% +26.0%
7 C-P INTEGRATED SERVICES, INC. $1,447,868 +34.1% +29.8%

Bid tab: unit prices 50 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 BRIDGECO CONTRA…#2 K & R BUILDERS,…#3 SEWELL BROS., I…#4 Reece Construct…#5 Allen Contracti…#6 Cimarron Constr…#7 C-P INTEGRATED …
1201(A) 0102 CLEARING AND GRUBBING1LSUM $5,000.00 $6,000.00 $5,000.00 $5,000.00 $6,000.00 $20,000.00 $19,500.00 $9,216.04
2202(H) 0185 EARTHWORK1LSUM $45,000.00 $88,000.00 $91,000.00 $94,000.00 $62,000.00 $125,000.00 $124,000.00 $342,200.98
3205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $7,000.00 $7,400.00 $5,500.00 $6,000.00 $7,000.00 $14,000.00 $9,000.00 $3,072.01
4221(C) 2801 TEMPORARY SILT FENCE600LF $1.80 $2.00 $1.80 $2.20 $1.30 $2.20 $3.00 $2.46
5221(F) 0100 TEMPORARY SILT DIKE600LF $7.00 $6.00 $6.50 $11.00 $6.30 $11.00 $8.00 $12.15
6230(A) 2806 SOLID SLAB SODDING14,774SY $2.00 $1.80 $1.53 $1.52 $1.50 $1.60 $1.65 $1.71
7233(A) 2817 VEGETATIVE MULCHING2.27AC $800.00 $750.00 $400.00 $750.00 $260.00 $770.00 $500.00 $858.93
8307(E) 4240 CEMENTITIOUS STABILIZED SUBGRADE6,050SY $3.50 $5.00 $6.44 $5.00 $4.35 $5.00 $7.00 $8.80
9402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E325TON $35.00 $35.00 $36.77 $30.00 $53.00 $40.00 $40.75 $16.51
10407(B) 0250 TACK COAT290GAL $4.00 $4.00 $2.48 $2.50 $3.00 $6.60 $2.70 $10.44
11408 5774 PRIME COAT1,300GAL $7.00 $7.50 $7.43 $7.40 $6.50 $4.00 $8.10 $12.29
12411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)1,170TON $80.00 $69.85 $70.03 $68.00 $66.55 $70.00 $74.00 $73.20
13411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)570TON $90.00 $84.85 $86.63 $84.00 $80.80 $88.00 $92.00 $91.75
14509(D) 0325 CLASS C CONCRETE20CY $300.00 $250.00 $278.00 $350.00 $334.00 $300.00 $300.00 $192.92
15601(A) 0297 TYPE I PLAIN RIPRAP310TON $30.00 $39.00 $43.94 $42.00 $57.00 $55.00 $55.00 $26.75
16613(B) 0692 36" CORR. GALV. STEEL PIPE86LF $65.00 $38.00 $34.50 $40.00 $40.31 $58.00 $55.00 $57.99
17613(B) 4528 28" X 20" CORR. GALV. STEEL PIPE ARCH92LF $50.00 $27.00 $25.00 $30.00 $53.86 $39.00 $37.00 $63.56
18613(M) 7187 TYPE B4 CULVERT END TREATMENT4EA $900.00 $850.00 $1,005.00 $1,300.00 $1,740.00 $750.00 $950.00 $474.24
19613(M) 7189 TYPE D4 CULVERT END TREATMENT2EA $1,300.00 $600.00 $1,545.00 $1,500.00 $2,590.00 $850.00 $1,840.00 $458.04
20619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $1,000.00 $3,000.00 $5,750.00 $1,500.00 $2,000.00 $3,700.00 $9,500.00 $3,072.01
21619(B) 4728 REMOVAL OF ASPHALT PAVEMENT3,601SY $4.00 $2.50 $2.50 $3.00 $1.80 $4.60 $1.35 $1.88
22619(C) 0924 SAWING PAVEMENT45LF $5.00 $8.00 $9.00 $10.00 $45.00 $5.00 $5.00 $6.14
23623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE200LF $16.00 $16.00 $16.50 $17.00 $13.95 $16.60 $16.00 $17.14
24623(G) 8571 GUARDRAIL END TREATMENT (GET)4EA $2,300.00 $2,100.00 $2,277.00 $2,225.00 $2,000.00 $2,300.00 $2,400.00 $2,457.61
25623(I) 8675 GUARDRAIL BRIDGE CONNECTION-TYPE A4EA $1,000.00 $1,985.00 $1,413.50 $2,400.00 $1,885.00 $1,450.00 $2,250.00 $2,316.30
26850(A) 8110 SHEET ALUMINUM SIGNS5.18SF $28.00 $35.00 $14.00 $16.50 $20.00 $15.50 $24.00 $24.58
27851(C) 8327 2 1/4" SQUARE TUBE POST12.5LF $15.00 $30.00 $12.00 $14.00 $15.00 $13.80 $18.00 $18.43
28854(A) 8800 TRAFFIC STRIPE(PAINT)(4" WIDE)3,200LF $0.2000 $0.6200 $0.2800 $0.3800 $0.3100 $0.2800 $0.4000 $0.3800
29501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON84CY $16.00 $10.00 $8.25 $10.00 $34.00 $15.00 $12.00 $11.09
30501(D) 6353 UNCLASSIFIED BACKFILL80CY $20.00 $12.00 $10.00 $10.00 $34.00 $15.00 $18.50 $8.48
31503(A) 1312 PRESTRESSED CONCRETE BEAMS (TYPE III)890LF $190.00 $164.25 $162.50 $165.00 $191.00 $175.00 $195.00 $198.13
32504(B) 1305 SAW-CUT GROOVING828SY $5.00 $5.05 $4.40 $7.00 $4.05 $4.50 $6.50 $9.22
33504(C) 6250 SEALED EXPANSION JOINT35.42LF $200.00 $260.00 $235.00 $270.00 $101.00 $220.00 $245.00 $188.79
34504(E) 1380 CONCRETE RAIL (TR1)507LF $70.00 $48.00 $66.50 $65.00 $69.00 $95.00 $80.00 $63.65
35506(A) 1322 STRUCTURAL STEEL734LB $3.00 $1.95 $3.25 $3.50 $2.00 $3.00 $4.00 $7.68
36507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY12EA $1,700.00 $625.00 $840.00 $1,000.00 $902.00 $760.00 $960.00 $579.59
37507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY12EA $1,700.00 $625.00 $840.00 $1,000.00 $902.00 $760.00 $960.00 $579.59
38509(A) 1326 CLASS AA CONCRETE204.9CY $480.00 $420.00 $480.00 $500.00 $562.00 $580.00 $650.00 $463.79
39509(B) 1328 CLASS A CONCRETE103.5CY $480.00 $420.00 $530.00 $500.00 $615.00 $480.00 $650.00 $430.69
40511(A) 1332 REINFORCING STEEL69,240LB $0.8000 $1.02 $0.8800 $1.00 $0.8000 $0.9000 $1.00 $0.9400
41514(A) 6010 PILES, FURNISHED (HP 10X42)977LF $30.00 $29.00 $23.80 $24.00 $36.00 $25.00 $37.00 $25.84
42514(B) 6292 PILES, DRIVEN (HP 10X42)977LF $10.00 $10.00 $10.20 $11.00 $7.00 $18.00 $23.00 $10.94
43516(A) 6095 DRILLED SHAFTS 54" DIAMETER197LF $530.00 $465.00 $500.00 $550.00 $607.00 $450.00 $590.00 $411.96
44601(B) 1353 TYPE I-A PLAIN RIPRAP2,753TON $25.00 $39.00 $41.33 $40.00 $57.00 $55.00 $53.00 $38.22
45601(C) 1355 TYPE I-A FILTER BLANKET596TON $30.00 $34.00 $35.36 $33.00 $49.00 $55.00 $46.00 $19.69
46619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $3,000.00 $25,000.00 $10,500.00 $7,000.00 $28,700.00 $22,000.00 $25,000.00 $24,576.10
47880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $3,000.00 $3,700.00 $4,000.00 $4,000.00 $2,700.00 $4,000.00 $3,000.00 $3,624.98
48642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $4,000.00 $5,500.00 $5,000.00 $4,700.00 $4,250.00 $7,300.00 $10,000.00 $5,068.82
49220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $3,000.00 $2,800.00 $3,400.00 $2,500.00 $2,000.00 $3,200.00 $8,000.00 $4,300.82
50641 1399 MOBILIZATION1LSUM $25,000.00 $40,000.00 $23,750.00 $40,000.00 $37,600.00 $51,187.00 $18,000.00 $61,440.26