| 1 | 202(D) 0184 |
UNCLASSIFIED BORROW | 300 | CY |
$12.00 |
$12.48 |
$33.36 |
$23.06 |
| 2 | 209 0120 |
MACHINE GRADING | 2,612 | LF |
$7.00 |
$1.20 |
$21.66 |
$8.83 |
| 3 | 221(C) 2801 |
TEMPORARY SILT FENCE | 2,500 | LF |
$1.70 |
$1.15 |
$1.17 |
$1.21 |
| 4 | 221(F) 0100 |
TEMPORARY SILT DIKE | 752 | LF |
$6.00 |
$8.92 |
$9.05 |
$9.37 |
| 5 | 230(A) 2806 |
SOLID SLAB SODDING | 61,800 | SY |
$1.45 |
$1.08 |
$1.10 |
$1.13 |
| 6 | 233(A) 2817 |
VEGETATIVE MULCHING | 12.77 | AC |
$300.00 |
$100.00 |
$608.00 |
$628.95 |
| 7 | 241 2832 |
MOWING | 309.48 | AC |
$52.00 |
$24.08 |
$64.50 |
$66.68 |
| 8 | 405 5200 |
PERMEABLE FRICTION COURSE | 10,027 | TON |
$87.00 |
$89.88 |
$91.28 |
$120.12 |
| 9 | 407(B) 0250 |
TACK COAT | 25,238 | GAL |
$2.80 |
$2.19 |
$2.71 |
$3.55 |
| 10 | 408 5774 |
PRIME COAT | 317 | GAL |
$7.00 |
$2.00 |
$4.61 |
$5.05 |
| 11 | 411(C) 5950 |
SUPERPAVE, TYPE S4(PG 76-28 OK) | 19,437 | TON |
$75.00 |
$89.15 |
$82.12 |
$104.24 |
| 12 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 5,947 | TON |
$70.00 |
$81.21 |
$74.73 |
$94.25 |
| 13 | 412 5267 |
COLD MILLING PAVEMENT | 201,635 | SY |
$1.20 |
$0.3600 |
$0.8100 |
$0.7400 |
| 14 | 425 5195 |
DIAMOND GRINDING CONCRETE PAVEMENT | 4,000 | SY |
$9.00 |
$10.00 |
$10.15 |
$6.30 |
| 15 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 4,745 | LF |
$4.50 |
$1.45 |
$1.70 |
$3.41 |
| 16 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 3,750 | LF |
$14.50 |
$15.10 |
$14.45 |
$16.56 |
| 17 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 12 | EA |
$2,200.00 |
$2,065.00 |
$2,132.00 |
$1,953.00 |
| 18 | 623(I) 8675 |
GUARDRAIL BRIDGE CONNECTION-TYPE A | 12 | EA |
$1,350.00 |
$1,265.00 |
$1,285.00 |
$2,310.00 |
| 19 | 425 5195 |
DIAMOND GRINDING CONCRETE PAVEMENT | 475 | SY |
$15.00 |
$12.00 |
$12.20 |
$12.60 |
| 20 | 504 6179 |
BRIDGE TRAFFIC RAIL | 268 | LF |
$140.00 |
$135.00 |
$126.90 |
$131.25 |
| 21 | 505(D) 6080 |
ASPHALT MEMBRANE OVERLAY | 566 | SY |
$30.00 |
$15.50 |
$20.30 |
$21.00 |
| 22 | 509(D) 1331 |
CLASS C CONCRETE | 5 | CY |
$350.00 |
$510.00 |
$609.00 |
$630.00 |
| 23 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 35 | SY |
$350.00 |
$215.00 |
$329.90 |
$341.25 |
| 24 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 20 | SY |
$650.00 |
$525.00 |
$532.90 |
$551.25 |
| 25 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$20,000.00 |
$23,500.00 |
$8,018.50 |
$12,600.00 |
| 26 | 425 5195 |
DIAMOND GRINDING CONCRETE PAVEMENT | 475 | SY |
$15.00 |
$12.00 |
$12.20 |
$12.60 |
| 27 | 504 6179 |
BRIDGE TRAFFIC RAIL | 268 | LF |
$140.00 |
$135.00 |
$126.90 |
$131.25 |
| 28 | 505(D) 6080 |
ASPHALT MEMBRANE OVERLAY | 566 | SY |
$30.00 |
$15.50 |
$20.30 |
$21.00 |
| 29 | 509(D) 1331 |
CLASS C CONCRETE | 5 | CY |
$280.00 |
$510.00 |
$609.00 |
$630.00 |
| 30 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 35 | SY |
$350.00 |
$215.00 |
$329.90 |
$341.25 |
| 31 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 20 | SY |
$650.00 |
$525.00 |
$532.90 |
$551.25 |
| 32 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$20,000.00 |
$23,500.00 |
$8,018.50 |
$12,600.00 |
| 33 | 501(G) 6309 |
CLSM BACKFILL | 10 | CY |
$300.00 |
$305.00 |
$355.25 |
$367.50 |
| 34 | 504(A) 1304 |
APPROACH SLAB | 169 | SY |
$170.00 |
$225.00 |
$255.00 |
$288.75 |
| 35 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 640 | SY |
$45.00 |
$33.00 |
$40.60 |
$42.00 |
| 36 | 506(A) 1322 |
STRUCTURAL STEEL | 1,770 | LB |
$4.00 |
$7.10 |
$3.55 |
$3.68 |
| 37 | 509(D) 1331 |
CLASS C CONCRETE | 5 | CY |
$280.00 |
$510.00 |
$609.00 |
$630.00 |
| 38 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 20 | SY |
$350.00 |
$215.00 |
$329.90 |
$341.25 |
| 39 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 34 | SY |
$600.00 |
$430.00 |
$507.50 |
$525.00 |
| 40 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 50 | LF |
$150.00 |
$23.00 |
$23.35 |
$24.15 |
| 41 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 2 | GAL |
$200.00 |
$70.00 |
$71.05 |
$73.50 |
| 42 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 20 | SY |
$650.00 |
$525.00 |
$532.90 |
$551.25 |
| 43 | 540 4515 |
(PL)REPAIR BRIDGE ITEM (TYPE A) | 2 | EA |
$3,000.00 |
$2,450.00 |
$4,060.00 |
$4,200.00 |
| 44 | 540 4535 |
(PL)REPAIR BRIDGE ITEM (TYPE C) | 2 | EA |
$20,000.00 |
$20,500.00 |
$24,360.00 |
$25,200.00 |
| 45 | 501(G) 6309 |
CLSM BACKFILL | 10 | CY |
$300.00 |
$305.00 |
$355.25 |
$367.50 |
| 46 | 504(A) 1304 |
APPROACH SLAB | 169 | SY |
$170.00 |
$225.00 |
$255.00 |
$288.75 |
| 47 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 640 | SY |
$45.00 |
$33.00 |
$40.60 |
$42.00 |
| 48 | 506(A) 1322 |
STRUCTURAL STEEL | 1,770 | LB |
$4.00 |
$7.10 |
$3.55 |
$3.68 |
| 49 | 509(D) 1331 |
CLASS C CONCRETE | 5 | CY |
$280.00 |
$510.00 |
$609.00 |
$630.00 |
| 50 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 20 | SY |
$350.00 |
$215.00 |
$329.90 |
$341.25 |
| 51 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 34 | SY |
$600.00 |
$430.00 |
$507.50 |
$525.00 |
| 52 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 50 | LF |
$150.00 |
$23.00 |
$23.35 |
$24.15 |
| 53 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 2 | GAL |
$200.00 |
$70.00 |
$71.05 |
$73.50 |
| 54 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 15 | SY |
$650.00 |
$525.00 |
$532.90 |
$551.25 |
| 55 | 540 4515 |
(PL)REPAIR BRIDGE ITEM (TYPE A) | 2 | EA |
$3,000.00 |
$2,450.00 |
$4,060.00 |
$4,200.00 |
| 56 | 540 4535 |
(PL)REPAIR BRIDGE ITEM (TYPE C) | 2 | EA |
$20,000.00 |
$20,500.00 |
$40,600.00 |
$25,200.00 |
| 57 | 501(G) 6309 |
CLSM BACKFILL | 15 | CY |
$300.00 |
$305.00 |
$355.25 |
$367.50 |
| 58 | 504(A) 1304 |
APPROACH SLAB | 278 | SY |
$170.00 |
$225.00 |
$255.00 |
$288.75 |
| 59 | 504(G) 6390 |
RAPID CURE JOINT SEALANT | 79 | LF |
$20.00 |
$31.00 |
$15.25 |
$15.75 |
| 60 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 1,000 | SY |
$45.00 |
$33.00 |
$40.60 |
$42.00 |
| 61 | 509(D) 1331 |
CLASS C CONCRETE | 5 | CY |
$280.00 |
$510.00 |
$609.00 |
$630.00 |
| 62 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 45 | SY |
$350.00 |
$215.00 |
$329.90 |
$341.25 |
| 63 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 90 | LF |
$150.00 |
$23.00 |
$23.35 |
$24.15 |
| 64 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 3 | GAL |
$200.00 |
$70.00 |
$71.05 |
$73.50 |
| 65 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 25 | SY |
$650.00 |
$525.00 |
$532.90 |
$551.25 |
| 66 | 540 4515 |
(PL)REPAIR BRIDGE ITEM (TYPE A) | 2 | EA |
$3,000.00 |
$2,450.00 |
$4,060.00 |
$4,200.00 |
| 67 | 540 4525 |
(PL)REPAIR BRIDGE ITEM (TYPE B) | 2 | EA |
$25,000.00 |
$24,500.00 |
$26,390.00 |
$36,750.00 |
| 68 | 501(G) 6309 |
CLSM BACKFILL | 15 | CY |
$300.00 |
$305.00 |
$355.25 |
$367.50 |
| 69 | 504(A) 1304 |
APPROACH SLAB | 278 | SY |
$170.00 |
$225.00 |
$255.00 |
$288.75 |
| 70 | 504(G) 6390 |
RAPID CURE JOINT SEALANT | 79 | LF |
$20.00 |
$31.00 |
$15.25 |
$15.75 |
| 71 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 1,000 | SY |
$45.00 |
$33.00 |
$40.60 |
$42.00 |
| 72 | 509(D) 1331 |
CLASS C CONCRETE | 5 | CY |
$280.00 |
$510.00 |
$609.00 |
$630.00 |
| 73 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 45 | SY |
$350.00 |
$215.00 |
$329.90 |
$341.25 |
| 74 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 50 | LF |
$150.00 |
$23.00 |
$23.35 |
$24.15 |
| 75 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 2 | GAL |
$200.00 |
$70.00 |
$71.05 |
$73.50 |
| 76 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 10 | SY |
$650.00 |
$525.00 |
$532.90 |
$551.25 |
| 77 | 540 4515 |
(PL)REPAIR BRIDGE ITEM (TYPE A) | 2 | EA |
$3,000.00 |
$2,450.00 |
$4,060.00 |
$4,200.00 |
| 78 | 540 4525 |
(PL)REPAIR BRIDGE ITEM (TYPE B) | 2 | EA |
$25,000.00 |
$24,500.00 |
$40,600.00 |
$36,750.00 |
| 79 | 805(D) 8756 |
(PL)REMOVE & RESET EXISTING SIGNS | 8 | EA |
$186.91 |
$50.00 |
$96.43 |
$52.50 |
| 80 | 853 9042 |
DELINEATORS(TYPE 1, CODE 1, FLEXIBLE) | 84 | EA |
$18.41 |
$35.00 |
$14.25 |
$36.75 |
| 81 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 92,188 | LF |
$0.4500 |
$0.3600 |
$0.2800 |
$0.3800 |
| 82 | 856(A) 8535 |
TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 14,160 | LF |
$0.6600 |
$0.5500 |
$0.2900 |
$0.5800 |
| 83 | 856(A) 8540 |
TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) | 800 | LF |
$0.9700 |
$1.00 |
$2.05 |
$1.05 |
| 84 | 856(A) 8555 |
TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) | 48 | LF |
$11.69 |
$2.00 |
$10.70 |
$2.10 |
| 85 | 413(A) 4861 |
RUMBLE STRIP-METHOD HMA-CON | 89,014 | LF |
$0.1400 |
$0.0800 |
$0.0800 |
$0.1300 |
| 86 | 857(A) 8839 |
CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 142,200 | LF |
$0.1600 |
$0.0900 |
$0.0700 |
$0.0900 |
| 87 | 857(E) 8887 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 5,000 | EA |
$0.5600 |
$0.4500 |
$0.6000 |
$0.4700 |
| 88 | 857(F) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 5,000 | LF |
$0.2100 |
$0.2000 |
$0.3000 |
$0.2100 |
| 89 | 870(A) 8485 |
SAND FILLED IMPACT ATTENUATION MODULE | 7,125 | SD |
$1.18 |
$1.00 |
$1.02 |
$1.05 |
| 90 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 3,400 | LF |
$23.00 |
$17.50 |
$18.30 |
$60.29 |
| 91 | 877(C) 8486 |
RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 6,800 | LF |
$4.85 |
$1.04 |
$3.81 |
$6.54 |
| 92 | 880(A) 8812 |
ARROW DISPLAY(TYPE C) | 250 | SD |
$6.80 |
$4.00 |
$5.10 |
$4.20 |
| 93 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 14,375 | SD |
$0.2500 |
$0.0500 |
$0.0300 |
$0.0500 |
| 94 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 3,125 | SD |
$0.5600 |
$1.00 |
$0.1000 |
$1.05 |
| 95 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 4,375 | SD |
$1.00 |
$0.7500 |
$0.1000 |
$1.05 |
| 96 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 3,125 | SD |
$0.4200 |
$0.1500 |
$0.0500 |
$0.1600 |
| 97 | 880(C) 8848 |
WING BARRICADES | 500 | SD |
$1.00 |
$1.00 |
$0.4100 |
$1.05 |
| 98 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 10,625 | SD |
$0.1100 |
$0.0500 |
$0.0300 |
$0.0500 |
| 99 | 880(F) 8878 |
DRUMS | 6,250 | SD |
$0.1100 |
$0.2500 |
$0.7600 |
$0.7400 |
| 100 | 880(G) 8890 |
CHANNELIZER CONES | 37,500 | SD |
$0.1300 |
$0.3000 |
$0.5600 |
$0.7400 |
| 101 | 880(L) 8911 |
TRAFFIC SURVEILLANCE, POLICE | 420 | HOUR |
$55.00 |
$40.00 |
$55.85 |
$57.75 |
| 102 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 250 | SD |
$10.48 |
$20.00 |
$18.30 |
$21.00 |
| 103 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$2,000.00 |
$722.37 |
$2,000.00 |
$2,625.00 |
| 104 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$248,130.00 |
$260,000.00 |
$357,840.00 |
$240,216.42 |