$0.9267Avg low bid / LF
$1.12Avg of all bids
$0.4090Avg engineer's estimate
9Jobs · 257,754 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 2 | 55,316 | $2.90 | $1.45 |
| 2020 | 4 | 51,430 | $0.8555 | $2.07 |
| 2019 | 2 | 80,308 | $0.3440 | $1.02 |
| 2018 | 1 | 70,700 | $0.1000 | $0.7883 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| May 20, 2021 | 210156 | SeminoleDivision 3 | 53,012 LF | $2.50 | Rosscon, LLC |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 2,304 LF | $12.00 | OVERLAND CORPORATION |
| Sep 17, 2020 | 200276 | Cotton | 5,000 LF | $0.6000 | OVERLAND CORPORATION |
| Aug 20, 2020 | 200268 | PittsburgDivision 2 | 43,031 LF | $0.5000 | Rosscon, LLC |
| Jun 18, 2020 | 200221 | AtokaDivision 2 | 1,236 LF | $5.00 | HUB Construction, Inc. |
| Mar 19, 2020 | 200120 | Pontotoc | 2,163 LF | $6.15 | OVERLAND CORPORATION |
| Jun 20, 2019 | 190092 | Pontotoc | 79,000 LF | $0.3000 | OVERLAND CORPORATION |
| Feb 14, 2019 | 190090 | PittsburgDivision 2 | 1,308 LF | $3.00 | HUB Construction, Inc. |
| Nov 15, 2018 | 180284 | GarvinDivision 3 | 70,700 LF | $0.1000 | THE CUMMINS CONSTRUCTION CO., INC. |
| Oct 18, 2018 | 180322 | ChoctawDivision 2 | 13,200 LF | $2.60 | THE CUMMINS CONSTRUCTION CO., INC. |