Bid tab 180322

Let Oct 18, 2018 · Division 2 · Choctaw Sign up free

‹ Oct 2018 results

RESURFACE (ASPHALT ) COUNTY ROAD (CRYSTAL ROAD /NS-401): FROM 2.5 MILES NORTH OF THE US-70 JUNCTION, EXTEND NORTH NEAR BOSWELL . PROJECT LENGTH = 2.500 MILES

Let date
Thursday, October 18, 2018
Contract
180322
J/P numbers
29965(04)
District
Division 2
County
Choctaw
Highway
Limits
RESURFACE (ASPHALT ) COUNTY ROAD (CRYSTAL ROAD /NS-401): FROM 2.5 MILES NORTH OF THE US-70 JUNCTION, EXTEND NORTH NEAR BOSWELL . PROJECT LENGTH = 2.500 MILES
Project number
STP-212C(043)CI

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$789,926
1 THE CUMMINS CONSTRUCTION CO., INC. Low bidder $698,934 -11.5%
2 OVERLAND CORPORATION $746,983 -5.4% +6.9%
3 RK Hall Construction $1,432,675 +81.4% +105.0%

Bid tab: unit prices 9 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 THE CUMMINS CON…#2 OVERLAND CORPOR…#3 RK Hall Constru…
1209 0120 MACHINE GRADING13,200LF $5.40 $2.60 $2.35 $2.30
2402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E500TON $37.50 $38.10 $20.00 $100.00
3407(D) 0401 (SP) NT TACK MATERIAL4,770GAL $3.75 $3.35 $0.0100 $6.20
4411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)2,570TON $84.50 $70.50 $74.50 $160.00
5411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)4,841TON $79.50 $79.70 $82.20 $157.00
6412 5267 COLD MILLING PAVEMENT25,520SY $1.80 $1.45 $2.10 $3.20
7854(A) 8800 TRAFFIC STRIPE(PAINT)(4" WIDE)45,600LF $0.3300 $0.1300 $0.1300 $0.1500
8880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $2,500.00 $2,640.00 $5,000.00 $3,000.00
9641 1399 MOBILIZATION1LSUM $16,500.00 $17,000.00 $52,000.00 $60,000.00