Bid tab 180284

Let Nov 15, 2018 · Division 3 · Garvin Sign up free

‹ Nov 2018 results

RESURFACE (ASPHALT ) SH-19/SH-74: SH-19, FROM 0.32 MILES WEST OF SH -74, EXTEND EAST. SH-74, FROM SH-19, EXTEND SOUTH NEAR MAYSVILLE . PROJECT LENGTH = 8.000 MILES

Let date
Thursday, November 15, 2018
Contract
180284
J/P numbers
33325(04)
District
Division 3
County
Garvin
Highway
Limits
RESURFACE (ASPHALT ) SH-19/SH-74: SH-19, FROM 0.32 MILES WEST OF SH -74, EXTEND EAST. SH-74, FROM SH-19, EXTEND SOUTH NEAR MAYSVILLE . PROJECT LENGTH = 8.000 MILES
Project number
SSR-225C(077)SR

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,072,399
1 THE CUMMINS CONSTRUCTION CO., INC. Low bidder $1,122,621 +4.7%
2 OVERLAND CORPORATION $1,207,544 +12.6% +7.6%
3 SCHIRALLI CONSTRUCTION CORP. $1,338,445 +24.8% +19.2%
4 MARKWELL PAVING COMPANY, INC. $1,358,502 +26.7% +21.0%
5 Silver Star Construction Company, Inc. $1,438,360 +34.1% +28.1%
6 HASKELL LEMON CONSTRUCTION CO. $1,442,696 +34.5% +28.5%

Bid tab: unit prices 9 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 THE CUMMINS CON…#2 OVERLAND CORPOR…#3 SCHIRALLI CONST…#4 MARKWELL PAVING…#5 Silver Star Con…#6 HASKELL LEMON C…
1202(D) 0184 UNCLASSIFIED BORROW937CY $8.00 $8.30 $21.00 $16.68 $8.50 $30.00 $30.00
2209 0120 MACHINE GRADING70,700LF $0.0800 $0.1000 $0.2500 $0.2800 $2.00 $0.5500 $1.55
3407(B) 0250 TACK COAT7,813GAL $2.30 $2.15 $3.50 $3.39 $2.35 $3.00 $4.00
4411(D) 5970 SUPERPAVE, TYPE S5(PG 70-28 OK)12,163TON $80.00 $84.35 $84.40 $98.50 $89.56 $102.00 $97.25
5412 5267 COLD MILLING PAVEMENT9,466SY $1.15 $1.60 $1.50 $1.76 $3.00 $3.20 $3.50
6855(A) 8812 TRAFFIC STRIPE(PLASTIC)(4" WIDE)94,689LF $0.4800 $0.4600 $0.4000 $0.4600 $0.3700 $0.4000 $0.5000
7855(A) 8818 TRAFFIC STRIPE(PLASTIC)(12" WIDE)192LF $3.65 $1.60 $3.20 $1.58 $3.00 $3.25 $1.60
8880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $10,000.00 $4,100.00 $63,000.00 $16,055.01 $36,850.00 $36,409.20 $8,015.00
9882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN60SD $20.00 $31.95 $10.00 $31.72 $10.00 $35.00 $35.00