| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$5,000.00 |
$4,000.00 |
$4,300.00 |
$6,120.00 |
$4,000.00 |
$5,500.00 |
$6,000.00 |
$8,000.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 4,113 | CY |
$7.00 |
$5.00 |
$7.36 |
$5.10 |
$6.00 |
$6.35 |
$8.51 |
$6.00 |
| 3 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$7,000.00 |
$2,500.00 |
$2,890.00 |
$3,060.00 |
$3,500.00 |
$3,300.00 |
$2,000.00 |
$4,800.00 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 250 | LF |
$2.00 |
$2.20 |
$2.30 |
$2.03 |
$1.50 |
$2.50 |
$2.00 |
$2.00 |
| 5 | 221(F) 0100 |
TEMPORARY SILT DIKE | 150 | LF |
$10.00 |
$11.00 |
$8.10 |
$10.14 |
$6.50 |
$6.00 |
$7.20 |
$6.00 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 7,050 | SY |
$2.00 |
$1.50 |
$1.34 |
$1.37 |
$1.50 |
$1.85 |
$1.55 |
$1.80 |
| 7 | 233(A) 2817 |
VEGETATIVE MULCHING | 1.5 | AC |
$450.00 |
$545.00 |
$495.00 |
$505.00 |
$150.00 |
$600.00 |
$450.00 |
$275.00 |
| 8 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 412 | CY |
$40.00 |
$39.00 |
$50.84 |
$51.85 |
$67.46 |
$75.00 |
$66.00 |
$49.00 |
| 9 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 271 | TON |
$25.00 |
$25.00 |
$20.02 |
$20.42 |
$21.62 |
$27.00 |
$41.00 |
$26.00 |
| 10 | 408 5774 |
PRIME COAT | 985 | GAL |
$6.00 |
$7.00 |
$6.36 |
$6.12 |
$5.00 |
$7.00 |
$6.00 |
$6.00 |
| 11 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 347 | TON |
$80.00 |
$100.00 |
$83.00 |
$84.66 |
$97.00 |
$93.50 |
$83.00 |
$93.00 |
| 12 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 227 | TON |
$90.00 |
$121.00 |
$103.00 |
$105.06 |
$125.00 |
$113.00 |
$103.00 |
$110.00 |
| 13 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$350.00 |
$250.00 |
$300.00 |
$287.86 |
$200.00 |
$250.00 |
$100.00 |
$220.00 |
| 14 | 619(C) 0924 |
SAWING PAVEMENT | 40 | LF |
$10.00 |
$5.00 |
$10.00 |
$10.20 |
$7.50 |
$10.00 |
$10.00 |
$7.00 |
| 15 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 10 | SF |
$20.00 |
$38.00 |
$32.00 |
$32.64 |
$32.00 |
$50.00 |
$18.00 |
$16.00 |
| 16 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 180 | CY |
$15.00 |
$7.00 |
$8.00 |
$15.30 |
$6.50 |
$10.00 |
$10.00 |
$10.00 |
| 17 | 501(F) 6352 |
GRANULAR BACKFILL | 76 | CY |
$50.00 |
$60.00 |
$54.20 |
$37.48 |
$55.00 |
$66.00 |
$50.00 |
$55.00 |
| 18 | 503(A) 1312 |
PRESTRESSED CONCRETE BEAMS (TYPE III) | 224 | LF |
$180.00 |
$202.00 |
$207.20 |
$193.22 |
$205.00 |
$212.00 |
$205.00 |
$251.00 |
| 19 | 504(B) 1305 |
SAW-CUT GROOVING | 244.63 | SY |
$5.00 |
$4.00 |
$7.35 |
$6.88 |
$7.50 |
$10.75 |
$6.75 |
$8.00 |
| 20 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 211.2 | LF |
$65.00 |
$65.00 |
$55.00 |
$54.00 |
$63.50 |
$60.00 |
$95.00 |
$65.00 |
| 21 | 506(A) 1322 |
STRUCTURAL STEEL | 290 | LB |
$4.00 |
$5.00 |
$3.00 |
$2.95 |
$2.00 |
$2.95 |
$6.00 |
$3.50 |
| 22 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 3 | EA |
$1,000.00 |
$800.00 |
$867.00 |
$1,445.00 |
$1,350.00 |
$650.00 |
$800.00 |
$870.00 |
| 23 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 3 | EA |
$1,000.00 |
$800.00 |
$890.00 |
$1,466.00 |
$1,350.00 |
$670.00 |
$800.00 |
$870.00 |
| 24 | 509(A) 1326 |
CLASS AA CONCRETE | 60.1 | CY |
$500.00 |
$500.00 |
$400.00 |
$449.06 |
$445.00 |
$400.00 |
$450.00 |
$500.00 |
| 25 | 509(B) 1328 |
CLASS A CONCRETE | 66.8 | CY |
$450.00 |
$450.00 |
$400.00 |
$470.03 |
$475.00 |
$400.00 |
$450.00 |
$500.00 |
| 26 | 511(A) 1332 |
REINFORCING STEEL | 23,290 | LB |
$0.8000 |
$0.9000 |
$0.8700 |
$0.9700 |
$0.8300 |
$1.05 |
$1.50 |
$1.10 |
| 27 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 76 | LF |
$25.00 |
$25.00 |
$25.50 |
$28.33 |
$30.00 |
$30.00 |
$20.00 |
$40.00 |
| 28 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 156 | LF |
$30.00 |
$29.00 |
$34.85 |
$37.28 |
$40.00 |
$36.50 |
$22.00 |
$49.00 |
| 29 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 76 | LF |
$12.00 |
$11.00 |
$15.00 |
$10.20 |
$20.00 |
$25.00 |
$10.00 |
$13.00 |
| 30 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 156 | LF |
$20.00 |
$13.00 |
$15.00 |
$15.30 |
$20.00 |
$25.00 |
$11.00 |
$13.00 |
| 31 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 1,010 | TON |
$30.00 |
$33.00 |
$33.28 |
$35.40 |
$33.50 |
$33.00 |
$29.50 |
$37.00 |
| 32 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 210 | TON |
$28.00 |
$28.00 |
$27.85 |
$28.99 |
$27.00 |
$32.00 |
$23.75 |
$34.00 |
| 33 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 52 | LF |
$20.00 |
$20.00 |
$20.00 |
$26.95 |
$28.00 |
$10.00 |
$50.00 |
$8.00 |
| 34 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 50 | LF |
$15.00 |
$20.00 |
$15.00 |
$11.65 |
$28.00 |
$10.00 |
$20.00 |
$8.00 |
| 35 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$8,000.00 |
$2,500.00 |
$7,500.00 |
$3,500.00 |
$4,500.00 |
$5,000.00 |
$8,000.00 |
$4,500.00 |
| 36 | 623(A) 1418 |
BEAM GUARDRAIL W-BEAM SINGLE | 137.5 | LF |
$25.00 |
$20.00 |
$14.75 |
$15.05 |
$17.00 |
$20.00 |
$16.15 |
$20.00 |
| 37 | 623(F) 6033 |
GUARDRAIL ANCHOR UNIT (TYPE II) | 4 | EA |
$2,500.00 |
$2,225.00 |
$1,775.00 |
$1,810.50 |
$1,900.00 |
$1,800.00 |
$1,669.00 |
$2,000.00 |
| 38 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$5,000.00 |
$2,400.00 |
$1,500.00 |
$1,530.00 |
$2,000.00 |
$2,200.00 |
$3,000.00 |
$4,000.00 |
| 39 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$5,000.00 |
$3,700.00 |
$5,400.00 |
$5,508.00 |
$3,900.00 |
$6,000.00 |
$3,550.00 |
$4,500.00 |
| 40 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$1,000.00 |
$4,000.00 |
$1,020.00 |
$2,500.00 |
$2,500.00 |
$2,000.00 |
$1,800.00 |
| 41 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$26,600.00 |
$12,000.00 |
$17,500.00 |
$20,873.00 |
$23,000.00 |
$18,000.00 |
$10,000.00 |
$21,000.00 |