GRADE, DRAIN, AND SURFACE SH -115: FROM THE US -62 JUNCTION, EXTEND NORTH TO THE WICHITA MOUNTAINS WILDLIFE REFUGE PARK . PROJECT LENGTH = 2.851 MILES

Let date
Thursday, October 21, 2010
Contract
100516
J/P numbers
27478(04)
District
Division 7
County
Comanche
Highway
Limits
GRADE, DRAIN, AND SURFACE SH -115: FROM THE US -62 JUNCTION, EXTEND NORTH TO THE WICHITA MOUNTAINS WILDLIFE REFUGE PARK . PROJECT LENGTH = 2.851 MILES
Project number
STP-116C(194)SS

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,666,805
1 DOBSON BROTHERS CONSTRUCTION CO. Low bidder $2,196,092 -17.7%
2 T & G CONSTRUCTION, INC. $2,396,433 -10.1% +9.1%
3 APAC-CENTRAL, INC. $2,502,556 -6.2% +14.0%
4 LAFORGE AND BUDD CONSTRUCTION COMPANY, INC. $3,034,021 +13.8% +38.2%

Bid tab: unit prices 68 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 DOBSON BROTHERS…#2 T & G CONSTRUCT…#3 APAC-CENTRAL, I…#4 LAFORGE AND BUD…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $30,000.00 $23,000.00 $20,000.00 $39,581.18 $20,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION11,410CY $5.00 $7.75 $5.25 $12.96 $15.00
3205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $40,000.00 $15,000.00 $33,720.00 $38,176.77 $20,000.00
4221(C) 2801 TEMPORARY SILT FENCE11,768LF $2.34 $1.42 $1.75 $1.49 $1.35
5221(D) 2803 TEMPORARY SEDIMENT FILTER1EA $180.00 $105.25 $200.00 $110.65 $100.00
6221(F) 0100 TEMPORARY SILT DIKE2,625LF $7.50 $7.10 $8.20 $7.47 $6.75
7229 4318 DITCH LINER PROTECTION1,128LF $1.70 $1.58 $1.50 $1.66 $1.50
8230(A) 2806 SOLID SLAB SODDING94,156SY $2.00 $1.35 $1.28 $1.42 $1.28
9230(F) 2812 WATERING3,765KGAL $8.00 $6.84 $8.00 $7.19 $6.50
10233(A) 2817 VEGETATIVE MULCHING19.44AC $450.00 $315.74 $200.00 $331.98 $300.00
11234(A) 2824 FERTILIZING (10-20-10)9.42TON $720.00 $526.24 $450.00 $553.30 $500.00
12234(A) 4406 FERTILIZING (0-46-0)1.5TON $876.89 $1,405.07 $500.00 $542.23 $800.00
13241 2832 MOWING40AC $61.77 $52.62 $100.00 $55.33 $50.00
14303(A) 2100 AGGREGATE BASE TYPE A6,426CY $32.00 $33.52 $34.20 $47.67 $42.00
15307(A) 4200 FLY ASH1,554TON $70.00 $72.00 $70.00 $66.34 $65.00
16307(D) 4230 LIME380TON $143.42 $155.00 $150.00 $172.04 $142.00
17307(E) 4240 CEMENTITIOUS STABILIZED SUBGRADE42,200SY $3.20 $1.45 $4.00 $2.32 $5.00
18307(G) 4260 LIME PRETREATMENT7,038SY $1.69 $0.5500 $3.00 $2.21 $12.00
19325 5271 SEPARATOR FABRIC35,190SY $1.14 $1.10 $2.00 $1.19 $1.20
20402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E11,575TON $21.00 $17.27 $17.35 $20.11 $30.00
21407(B) 0250 TACK COAT1,143GAL $2.10 $3.50 $3.00 $2.14 $3.00
22408 5774 PRIME COAT9,273GAL $3.50 $4.62 $6.00 $4.84 $3.50
23409(A) 4242 FABRIC REINFORCEMENT55,894SY $2.95 $0.9100 $2.00 $1.46 $1.50
24409(B) 4268 BITUMINOUS BINDER1,398GAL $2.00 $3.59 $2.60 $3.53 $3.50
25411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)3,563TON $63.00 $63.00 $54.20 $61.18 $65.00
26411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)9,319TON $68.00 $58.00 $59.50 $65.33 $70.00
27412 5267 COLD MILLING PAVEMENT2,240SY $9.00 $4.23 $5.00 $3.32 $3.00
28501(A) 0313 STRUCTURAL EXCAVATION UNCLASSIFIED12CY $24.36 $40.00 $20.00 $55.33 $200.00
29509(A) 0319 CLASS AA CONCRETE44.33CY $452.75 $845.00 $500.00 $1,051.27 $1,000.00
30509(D) 0325 CLASS C CONCRETE60CY $270.33 $300.00 $275.00 $320.91 $250.00
31511(A) 0332 REINFORCING STEEL5,750LB $1.00 $1.50 $1.10 $1.11 $0.7500
32601(B) 0536 TYPE I-A PLAIN RIPRAP52TON $40.00 $45.00 $50.00 $49.80 $100.00
33601(C) 0538 TYPE I-A FILTER BLANKET26TON $30.00 $45.00 $50.00 $30.99 $100.00
34609(B) 1525 2'-8" COMB. CURB & GUTTER (6" BARRIER)38LF $41.31 $25.00 $30.00 $19.92 $35.00
35611(G) 5389 INLET CDI RCB DES. 31EA $2,800.00 $4,500.00 $3,000.00 $2,655.84 $3,000.00
36611(H) 5538 ADD'L DEPTH IN INLET CDI RCB DES. 31VF $2,200.00 $275.00 $2,500.00 $663.97 $500.00
37613(A) 0491 18" R.C.PIPE CLASS III66LF $60.00 $40.00 $50.00 $154.92 $40.00
38613(B) 0689 18" CORR. GALV. STEEL PIPE98LF $30.00 $35.00 $22.00 $36.55 $20.00
39613(L) 5726 18" PREFAB. CULVERT END SECTION, ROUND4EA $2,200.00 $750.00 $1,000.00 $768.40 $850.00
40613(P) 0760 18" GALV. STEEL CULVERT END SECTION ROUND4EA $850.00 $250.00 $400.00 $356.31 $350.00
41613(S) 1186 STANDARD BEDDING MATERIAL, CLASS B23CY $28.00 $30.00 $25.00 $30.98 $65.00
42613(V) 1180 TRENCH EXCAVATION29CY $8.60 $20.00 $10.00 $22.13 $200.00
43619(B) 0291 REMOVAL OF HEADWALL7EA $629.81 $125.00 $1,000.00 $1,383.25 $4,000.00
44619(B) 4726 REMOVAL OF CURB AND GUTTER66LF $8.12 $15.00 $5.00 $8.40 $25.00
45619(B) 4728 REMOVAL OF ASPHALT PAVEMENT19SY $2.60 $5.00 $5.00 $16.62 $300.00
46619(B) 5918 REMOVAL OF EXISTING PIPE74LF $12.41 $15.00 $5.00 $10.26 $50.00
47619(C) 0924 SAWING PAVEMENT100LF $5.04 $8.50 $5.00 $3.23 $35.00
48805(A) 8722 (PL)REMOVAL OF EXISTING SIGNS1LSUM $600.00 $263.12 $1,000.00 $276.65 $800.00
49850(A) 8110 SHEET ALUMINUM SIGNS170SF $15.83 $14.73 $8.00 $15.49 $8.00
50851(C) 8324 2" SQUARE TUBE POST261LF $5.81 $8.42 $15.50 $8.85 $15.50
51853 9033 DELINEATORS(TYPE 2, CODE 1)20EA $25.00 $18.94 $15.00 $19.92 $15.00
52855(A) 8812 TRAFFIC STRIPE(PLASTIC)(4" WIDE)48,089LF $0.4700 $0.3700 $0.3700 $0.3900 $0.3700
53855(A) 8825 TRAFFIC STRIPE(PLASTIC)(24" WIDE)24LF $5.70 $10.53 $2.25 $11.07 $2.25
54857(A) 8839 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE)32,000LF $0.2000 $0.1100 $0.1400 $0.1100 $0.1400
55857(E) 8887 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-16,200EA $0.8000 $0.4700 $0.5000 $0.7600 $0.6000
56880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF5,544SD $0.3200 $1.05 $0.0200 $1.11 $0.0200
57880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF1,512SD $1.22 $1.05 $0.0200 $1.11 $0.0200
58880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF3,150SD $1.22 $1.05 $0.0200 $1.11 $0.0200
59880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)1,512SD $0.5400 $0.1100 $0.0200 $0.1100 $0.0200
60880(C) 8848 WING BARRICADES840SD $0.7900 $1.05 $0.0200 $1.11 $0.0200
61880(E) 8860 WARNING LIGHTS(TYPE A)6,804SD $0.1100 $0.0200 $0.0200 $0.0200 $0.0200
62880(E) 8872 WARNING LIGHTS(TYPE C)1,008SD $0.1400 $0.5300 $0.0200 $0.5500 $0.0200
63880(G) 8890 CHANNELIZER CONES15,120SD $0.0700 $0.1100 $0.0200 $0.1100 $0.0200
64880(I) 8902 FLAGGER210SD $136.04 $225.00 $150.00 $7.89 $750.00
65220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $6,750.87 $5,000.00 $5,000.00 $869.38 $10,000.00
66640(A) 1426 FIELD OFFICE1EA $9,000.00 $2,000.00 $10,000.00 $8,048.04 $5,000.00
67641 1552 MOBILIZATION1LSUM $150,000.00 $75,000.00 $100,000.00 $53,136.79 $140,000.00
68642(A) 0095 CONSTRUCTION STAKING LEVEL I1LSUM $50,000.00 $35,000.00 $40,000.00 $8,299.52 $20,000.00