$42.17Avg low bid / CY
$43.42Avg of all bids
$41.24Avg engineer's estimate
182Jobs · 2,808,862.86 CY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 12 | 108,928 | $72.78 | $67.41 |
| 2023 | 25 | 268,418 | $55.19 | $65.72 |
| 2022 | 16 | 221,898.7 | $50.10 | $60.58 |
| 2021 | 20 | 236,545.1 | $44.00 | $46.17 |
| 2020 | 13 | 158,057 | $41.34 | $44.27 |
| 2019 | 40 | 795,460.94 | $42.28 | $42.76 |
| 2018 | 36 | 599,176.12 | $33.48 | $38.33 |
| 2017 | 18 | 416,993 | $33.08 | $36.16 |
| 2016 | 2 | 3,386 | $51.76 | $44.93 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 7, 2024 | 0047-13-033 | GraysonParis | 41,823 CY | $76.00 | RPM XCONSTRUCTION, LLC |
| Aug 2, 2024 | 0007-06-267 | EastlandBrownwood | 636 CY | $60.00 | HJC FARMS, INC. |
| Jun 6, 2024 | 0724-02-020 | BosqueWaco | 1,569 CY | $98.00 | KNIFE RIVER CORPORATION - SOUTH |
| Jun 5, 2024 | 0480-07-014 | MillsBrownwood | 26,426 CY | $72.45 | ALLEN KELLER COMPANY |
| May 21, 2024 | 6392-00-001 | TaylorAbilene | 81 CY | $150.00 | BONTKE BROTHERS CONSTRUCTION COMPANY |
| May 3, 2024 | 0624-01-003 | UvaldeSan Antonio | 83 CY | $100.00 | RELMCO, INC. |
| May 3, 2024 | 2121-01-104 | El PasoEl Paso | 3,581 CY | $61.45 | SUNDT CONSTRUCTION, INC. |
| Apr 5, 2024 | 3623-01-008 | CoryellWaco | 592 CY | $94.00 | KNIFE RIVER CORPORATION - SOUTH |
| Apr 4, 2024 | 0195-03-087 | DentonDallas | 31,596 CY | $65.43 | SEMA CONSTRUCTION, INC. |
| Apr 4, 2024 | 6393-14-001 | UvaldeSan Antonio | 494 CY | $265.00 | CK NEWBERRY, LLC |
| Mar 6, 2024 | 0972-03-023 | JonesAbilene | 502 CY | $80.00 | J. H. STRAIN & SONS, INC. |
| Jan 4, 2024 | 3030-01-010 | HillWaco | 1,545 CY | $70.00 | BIG CREEK CONSTRUCTION, LTD. |
| Nov 2, 2023 | 1047-03-079 | DallasDallas | 1,390 CY | $92.00 | TEXAS-REYES GROUP LTD. |
| Nov 1, 2023 | 6438-55-001 | LeonBryan | 35 CY | $50.00 | GARRET SHIELDS INFRASTRUCTURE |
| Oct 5, 2023 | 0257-04-031 | EastlandBrownwood | 1,663 CY | $70.00 | JAY MILLS CONTRACTING, INCORPORATED |
| Sep 7, 2023 | 0183-02-028 | HamiltonWaco | 18,619 CY | $70.00 | BIG CREEK CONSTRUCTION, LTD. |
| Sep 6, 2023 | 1027-01-023 | EastlandBrownwood | 2,192 CY | $80.00 | JAY MILLS CONTRACTING, INCORPORATED |
| Aug 3, 2023 | 1597-04-012 | ComancheBrownwood | 39,266 CY | $57.00 | JAY MILLS CONTRACTING, INCORPORATED |
| Aug 3, 2023 | 0047-18-089 | GraysonParis | 72,638 CY | $30.17 | SEMA CONSTRUCTION, INC. |
| Aug 3, 2023 | 0495-02-064 | Van ZandtTyler | 19,957 CY | $100.00 | INDUS ROAD & BRIDGE, INC. |
| Aug 2, 2023 | 0314-05-046 | EastlandBrownwood | 1,854 CY | $108.00 | STERLING DELAWARE HOLDING COMPANY |
| Aug 2, 2023 | 3448-02-007 | McLennanWaco | 7,110 CY | $55.00 | KNIFE RIVER CORPORATION - SOUTH |
| Aug 2, 2023 | 0320-01-079 | BellWaco | 3,476 CY | $65.00 | TEXAS MATERIALS GROUP, INC. |
| Jun 28, 2023 | 1219-02-017 | CoryellWaco | 1,776 CY | $75.00 | KNIFE RIVER CORPORATION - SOUTH |
| Jun 27, 2023 | 0598-01-105 | HarrisHouston | 644 CY | $130.00 | MAIN LANE INDUSTRIES LTD. |
| Jun 27, 2023 | 0197-03-078 | KaufmanDallas | 19,646 CY | $52.00 | GRANITE CONSTRUCTION COMPANY |
| May 5, 2023 | 0251-06-036 | LampasasBrownwood | 735 CY | $110.00 | JAY MILLS CONTRACTING, INCORPORATED |
| May 5, 2023 | 2013-02-014 | BrownBrownwood | 7,748 CY | $52.00 | JAY MILLS CONTRACTING, INCORPORATED |
| May 5, 2023 | 0909-29-046 | HamiltonWaco | 194 CY | $106.00 | KNIFE RIVER CORPORATION - SOUTH |
| May 4, 2023 | 0291-06-053 | BanderaSan Antonio | 325 CY | $83.00 | STERLING DELAWARE HOLDING COMPANY |
| Apr 5, 2023 | 0258-08-038 | McLennanWaco | 212 CY | $125.00 | KNIFE RIVER CORPORATION - SOUTH |
| Apr 5, 2023 | 0909-37-065 | HillWaco | 161 CY | $120.00 | PMCO CONSTRUCTION LLC |
| Feb 2, 2023 | 0320-02-039 | BellWaco | 4,619 CY | $57.76 | JAMES CONSTRUCTION GROUP, LLC |
| Feb 2, 2023 | 0289-04-032 | San SabaBrownwood | 14,223 CY | $60.00 | CK NEWBERRY, LLC |
| Feb 1, 2023 | 0231-02-066 | CoryellWaco | 665 CY | $78.00 | TEXAS MATERIALS GROUP, INC. |
| Jan 6, 2023 | 3469-01-014 | StephensBrownwood | 2,465 CY | $58.00 | PRATER DIRT WORK LLC |
| Jan 6, 2023 | 3508-01-029 | BexarSan Antonio | 46,805 CY | $58.02 | AUSTIN BRIDGE & ROAD SERVICES, LP |
| Nov 2, 2022 | 0909-28-035 | BosqueWaco | 249 CY | $80.00 | HODGES AND SON CONSTRUCTION COMPANY, INC. |
| Sep 8, 2022 | 0748-06-016 | AtascosaSan Antonio | 18,446 CY | $58.42 | HUNTER INDUSTRIES, LTD. |
| Sep 7, 2022 | 0831-01-019 | McLennanWaco | 7,100 CY | $54.10 | KNIFE RIVER CORPORATION - SOUTH |
| Aug 4, 2022 | 0836-02-078 | BellWaco | 692 CY | $75.00 | TEXAS MATERIALS GROUP, INC. |
| Aug 3, 2022 | 0272-05-033 | LampasasBrownwood | 14,876 CY | $45.00 | BIG CREEK CONSTRUCTION, LTD. |
| Jun 30, 2022 | 2570-01-011 | BrownBrownwood | 17,048 CY | $45.00 | JAY MILLS CONTRACTING, INCORPORATED |
| Jun 29, 2022 | 0196-02-132 | DentonDallas | 343 CY | $125.00 | RAGLE CONSTRUCTION, INC. |
| Apr 12, 2022 | 6394-40-001 | LimestoneWaco | 468 CY | $149.80 | TEXAS MATERIALS GROUP, INC. |
| Mar 4, 2022 | 0095-04-069 | KaufmanDallas | 20,522.7 CY | $61.50 | STERLING DELAWARE HOLDING COMPANY, INC. |
| Feb 4, 2022 | 2121-01-094 | El PasoEl Paso | 22,018 CY | $35.00 | SUNDT CONSTRUCTION, INC. |
| Jan 7, 2022 | 0032-07-029 | StonewallAbilene | 28,884 CY | $58.09 | DELHUR INDUSTRIES, INC. |
| Jan 7, 2022 | 0099-01-035 | ColemanBrownwood | 14,219 CY | $45.00 | J. H. STRAIN & SONS, INC. |
| Jan 6, 2022 | 0079-01-038 | BrownBrownwood | 2,868 CY | $50.00 | PRATER DIRT WORK LLC |
| Jan 6, 2022 | 0257-03-033 | EastlandBrownwood | 11,833 CY | $45.00 | BIG CREEK CONSTRUCTION, LTD. |
| Jan 6, 2022 | 0033-01-038 | StonewallAbilene | 20,360 CY | $55.00 | J. H. STRAIN & SONS, INC. |
| Jan 6, 2022 | 0867-01-017 | HamiltonWaco | 41,972 CY | $45.00 | BIG CREEK CONSTRUCTION, LTD. |
| Dec 1, 2021 | 0724-01-056 | CoryellWaco | 11,443 CY | $44.00 | BIG CREEK CONSTRUCTION, LTD. |
| Oct 8, 2021 | 2121-01-094 | El PasoEl Paso | 25,960 CY | $41.00 | JORDAN FOSTER CONSTRUCTION, LLC |
| Sep 2, 2021 | 0257-04-029 | EastlandBrownwood | 23,645 CY | $50.00 | BIG CREEK CONSTRUCTION, LTD. |
| Sep 1, 2021 | 2975-01-009 | AtascosaSan Antonio | 13,110 CY | $59.02 | HUNTER INDUSTRIES, LTD. |
| Aug 5, 2021 | 2502-01-021 | BellWaco | 33,536 CY | $30.54 | JAMES CONSTRUCTION GROUP, LLC |
| Aug 5, 2021 | 0120-03-031 | BosqueWaco | 21,998 CY | $45.65 | TEXAS MATERIALS GROUP, INC. |
| Aug 5, 2021 | 0258-09-142 | McLennanWaco | 62,812 CY | $45.39 | WEBBER, LLC |
| Aug 5, 2021 | 0079-03-051 | ComancheBrownwood | 2,227 CY | $46.00 | JAY MILLS CONTRACTING, INCORPORATED |
| Aug 4, 2021 | 1191-03-033 | LimestoneWaco | 1,203 CY | $77.00 | STATELINE CONSTRUCTION, LLC |
| Aug 4, 2021 | 0183-01-053 | ComancheBrownwood | 5,353.1 CY | $41.25 | JAY MILLS CONTRACTING, INCORPORATED |
| Aug 4, 2021 | 0162-01-097 | McLennanWaco | 18,037 CY | $40.00 | WEBBER, LLC |
| Aug 4, 2021 | 1077-01-026 | FallsWaco | 3,514 CY | $43.15 | KNIFE RIVER CORPORATION - SOUTH |
| Jul 2, 2021 | 0567-04-022 | McLennanWaco | 5,383 CY | $50.00 | BIG CREEK CONSTRUCTION, LTD. |
| Jul 1, 2021 | 0834-02-031 | HillWaco | 2,073 CY | $52.00 | KNIFE RIVER CORPORATION - SOUTH |
| Jun 4, 2021 | 0288-03-032 | EastlandBrownwood | 1,420 CY | $75.00 | PIERCE R & B LLC |
| Jun 3, 2021 | 0513-01-017 | CoryellWaco | 3,142 CY | $40.00 | BIG CREEK CONSTRUCTION, LTD. |
| Apr 7, 2021 | 0909-22-180 | McLennanWaco | 209 CY | $60.00 | HODGES AND SON CONSTRUCTION COMPANY, INC. |
| Mar 4, 2021 | 0368-04-033 | JeffersonBeaumont | 235 CY | $91.00 | TREVWAY, INC. |
| Feb 5, 2021 | 0915-00-224 | BexarSan Antonio | 1,223 CY | $58.00 | RELMCO, INC. |
| Feb 4, 2021 | 6375-25-001 | MadisonBryan | 22 CY | $100.00 | BIG CREEK CONSTRUCTION, LTD. |
| Oct 2, 2020 | 0923-06-077 | BrownBrownwood | 411 CY | $60.00 | HODGES AND SON CONSTRUCTION COMPANY, INC. |
| Oct 2, 2020 | 0909-40-076 | LimestoneWaco | 328 CY | $75.00 | FUQUA CONSTRUCTION CO., INC. |
| Aug 5, 2020 | 0915-12-657 | BexarSan Antonio | 2,068 CY | $40.00 | DAN WILLIAMS COMPANY |
| Aug 5, 2020 | 0181-02-032 | CallahanAbilene | 3,446 CY | $49.20 | CONTRACT PAVING CO. |
| Jul 8, 2020 | 0833-06-019 | FallsWaco | 10,215 CY | $34.00 | KNIFE RIVER CORPORATION - SOUTH |
| Jul 8, 2020 | 0909-40-075 | LimestoneWaco | 483 CY | $50.00 | A. L. HELMCAMP, INC. |
| Jun 4, 2020 | 0231-04-060 | BellWaco | 41,317 CY | $34.17 | JAMES CONSTRUCTION GROUP, L.L.C. |
| May 8, 2020 | 0257-05-045 | ComancheBrownwood | 11,685 CY | $50.00 | BIG CREEK CONSTRUCTION, LTD. |
| May 7, 2020 | 0581-02-124 | DallasDallas | 12,055 CY | $48.50 | WEBBER, LLC |
| Apr 9, 2020 | 0257-05-046 | ComancheBrownwood | 50,082 CY | $39.75 | KNIFE RIVER CORPORATION - SOUTH |
| Mar 5, 2020 | 0366-05-048 | WilsonSan Antonio | 5,494 CY | $67.00 | ANGEL BROTHERS HOLDINGS CORP. |
| Feb 7, 2020 | 0658-01-044 | BexarSan Antonio | 6,426 CY | $45.00 | J3 COMPANY, LLC |
| Feb 7, 2020 | 0120-05-026 | HamiltonWaco | 14,047 CY | $45.00 | BIG CREEK CONSTRUCTION, LTD. |
| Dec 4, 2019 | 1664-01-019 | LimestoneWaco | 1,370 CY | $35.00 | TEXAS MATERIALS GROUP, INC. |
| Dec 4, 2019 | 0714-05-021 | EastlandBrownwood | 3,890.1 CY | $44.00 | JAY MILLS CONTRACTING, INCORPORATED |
| Dec 4, 2019 | 1187-02-018 | McLennanWaco | 597 CY | $45.00 | KNIFE RIVER CORPORATION - SOUTH |
| Dec 3, 2019 | 0259-01-036 | ErathFort Worth | 22,721 CY | $33.00 | JAY MILLS CONTRACTING, INCORPORATED |
| Dec 3, 2019 | 0480-08-027 | San SabaBrownwood | 7,148.4 CY | $38.53 | JAMES CONSTRUCTION GROUP, L.L.C. |
| Nov 6, 2019 | 0185-01-030 | BellWaco | 248,187 CY | $36.00 | J.D. ABRAMS, L.P. |
| Nov 6, 2019 | 0258-06-040 | BosqueWaco | 25,627 CY | $45.00 | BIG CREEK CONSTRUCTION, LTD. |
| Nov 6, 2019 | 0924-07-013 | PresidioEl Paso | 12.8 CY | $250.00 | DAN WILLIAMS COMPANY |
| Nov 6, 2019 | 0259-03-055 | Somervell | 10,574 CY | $40.00 | JAY MILLS CONTRACTING, INCORPORATED |
| Oct 2, 2019 | 3469-01-013 | StephensBrownwood | 7,131.3 CY | $66.00 | A. L. HELMCAMP, INC. |
| Oct 2, 2019 | 0909-38-079 | FallsWaco | 155 CY | $60.00 | ELLIS-MCGINNIS CONSTRUCTION CO. |
| Sep 6, 2019 | 0126-01-039 | ShackelfordAbilene | 1,183 CY | $70.00 | A. L. HELMCAMP, INC. |
| Aug 7, 2019 | 0025-02-219 | BexarSan Antonio | 395 CY | $113.00 | JORDAN FOSTER CONSTRUCTION, LLC |
| Aug 6, 2019 | 3409-01-006 | BellWaco | 7,981 CY | $55.00 | TEXAS MATERIALS GROUP, INC. |
| Aug 6, 2019 | 0081-01-051 | TarrantFort Worth | 26 CY | $430.00 | JAGOE-PUBLIC COMPANY |
| Jul 10, 2019 | 6345-39-001 | LimestoneWaco | 409 CY | $100.00 | TEXAS MATERIALS GROUP, INC. |
| Jun 5, 2019 | 0048-03-050 | EllisDallas | 1,978.1 CY | $54.99 | FLUOR HEAVY CIVIL, LLC |
| Jun 5, 2019 | 0291-07-034 | BanderaSan Antonio | 8,485.24 CY | $58.84 | HUNTER INDUSTRIES, LTD. |
| Jun 5, 2019 | 0909-38-082 | FallsWaco | 466 CY | $65.00 | ELLIS-MCGINNIS CONSTRUCTION CO. |
| Jun 5, 2019 | 0301-06-018 | FrioSan Antonio | 123,220 CY | $50.00 | ANDERSON COLUMBIA CO., INC. |
| Jun 4, 2019 | 0016-04-116 | ComalSan Antonio | 2,127 CY | $32.41 | HUNTER INDUSTRIES, LTD. |
| Jun 4, 2019 | 0231-03-145 | BellWaco | 52,924 CY | $30.00 | J.D. ABRAMS, L.P. |
| Jun 4, 2019 | 0301-07-013 | FrioSan Antonio | 84,003 CY | $60.00 | ANGEL BROTHERS HOLDINGS CORP. |
| Jun 4, 2019 | 0016-04-117 | ComalSan Antonio | 12,339 CY | $40.00 | WEBBER, LLC |
| May 8, 2019 | 0183-03-050 | HamiltonWaco | 17,438 CY | $38.00 | BIG CREEK CONSTRUCTION, LTD. |
| May 8, 2019 | 0833-03-045 | McLennanWaco | 30,519 CY | $39.12 | KNIFE RIVER CORPORATION - SOUTH |
| May 8, 2019 | 0867-07-013 | San SabaBrownwood | 908 CY | $125.00 | BIG CREEK CONSTRUCTION, LTD. |
| May 7, 2019 | 0909-38-080 | LimestoneWaco | 584 CY | $51.01 | JAMES CONSTRUCTION GROUP, L.L.C. |
| May 7, 2019 | 0048-09-029 | HillWaco | 1,909 CY | $50.00 | SACYR CONSTRUCTION USA LLC |
| May 7, 2019 | 0256-02-031 | StephensBrownwood | 60 CY | $80.00 | PEACHTREE CONSTRUCTION, LTD. |
| May 7, 2019 | 0053-15-024 | NolanAbilene | 7,711 CY | $68.00 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
| Apr 3, 2019 | 0072-06-074 | KendallSan Antonio | 10,275 CY | $44.00 | AUSTIN BRIDGE & ROAD SERVICES, LP |
| Apr 3, 2019 | 0561-01-024 | KaufmanDallas | 1,185 CY | $66.00 | TEXAS MATERIALS GROUP, INC. |
| Apr 2, 2019 | 0909-22-176 | McLennanWaco | 354 CY | $65.00 | KNIFE RIVER CORPORATION - SOUTH |
| Mar 5, 2019 | 0909-38-081 | FallsWaco | 498 CY | $52.00 | ELLIS-MCGINNIS CONSTRUCTION CO. |
| Feb 6, 2019 | 0867-07-013 | San SabaBrownwood | 1,508 CY | $125.00 | BIG CREEK CONSTRUCTION, LTD. |
| Feb 6, 2019 | 0257-06-027 | ErathFort Worth | 9,908 CY | $36.85 | JAY MILLS CONTRACTING, INCORPORATED |
| Feb 5, 2019 | 2452-04-016 | BexarSan Antonio | 46,043 CY | $12.00 | MARIO SINACOLA & SONS EXCAVATING, INC. |
| Jan 9, 2019 | 1192-01-024 | McLennanWaco | 20,673 CY | $34.00 | KNIFE RIVER CORPORATION - SOUTH |
| Jan 8, 2019 | 0125-04-033 | ShackelfordAbilene | 22,938 CY | $76.00 | A. L. HELMCAMP, INC. |
| Dec 6, 2018 | 0517-02-042 | McMullenSan Antonio | 2,709 CY | $65.80 | DEAN WORD COMPANY, LTD. |
| Dec 6, 2018 | 0210-03-025 | MilamBryan | 78 CY | $66.00 | KNIFE RIVER CORPORATION - SOUTH |
| Nov 6, 2018 | 0056-02-033 | LimestoneWaco | 10,106 CY | $35.00 | BIG CREEK CONSTRUCTION, LTD. |
| Oct 2, 2018 | 2061-02-030 | McLennanWaco | 33,705 CY | $38.00 | BIG CREEK CONSTRUCTION, LTD. |
| Aug 8, 2018 | 1503-02-011 | HowardAbilene | 28,192 CY | $44.33 | DELHUR INDUSTRIES, INC. |
| Aug 8, 2018 | 0909-38-078 | FallsWaco | 158 CY | $65.00 | KNIFE RIVER CORPORATION - SOUTH |
| Aug 7, 2018 | 0484-01-023 | JonesAbilene | 54,458 CY | $38.00 | J. H. STRAIN & SONS, INC. |
| Aug 7, 2018 | 0909-29-040 | HamiltonWaco | 425 CY | $60.00 | ELLIS-MCGINNIS CONSTRUCTION CO. |
| Aug 7, 2018 | 0016-08-036 | BexarSan Antonio | 342 CY | $50.00 | E-Z BEL CONSTRUCTION, LLC |
| Aug 7, 2018 | 0909-38-071 | FallsWaco | 151 CY | $60.00 | ELLIS-MCGINNIS CONSTRUCTION CO. |
| Jul 11, 2018 | 0184-01-063 | CoryellWaco | 29,058 CY | $30.00 | BIG CREEK CONSTRUCTION, LTD. |
| Jul 11, 2018 | 0909-39-127 | CoryellWaco | 199 CY | $85.00 | CAPITAL EXCAVATION COMPANY |
| Jul 10, 2018 | 0253-04-138 | BexarSan Antonio | 118,953 CY | $17.00 | ZACHRY CONSTRUCTION CORPORATION |
| Jun 6, 2018 | 0909-40-074 | LimestoneWaco | 128 CY | $75.00 | ELLIS-MCGINNIS CONSTRUCTION CO. |
| Jun 5, 2018 | 0231-03-146 | BellWaco | 3,157 CY | $39.00 | CAPITAL EXCAVATION COMPANY |
| Jun 5, 2018 | 2452-03-118 | BexarSan Antonio | 8,052 CY | $28.20 | Curran Contracting Company |
| May 15, 2018 | 6325-53-001 | FallsWaco | 515 CY | $69.00 | KNIFE RIVER CORPORATION - SOUTH |
| May 2, 2018 | 0613-02-063 | AtascosaSan Antonio | 2,214 CY | $45.00 | HARPER BROTHERS CONSTRUCTION LLC |
| May 2, 2018 | 0127-02-142 | EastlandBrownwood | 519 CY | $80.00 | BIG CREEK CONSTRUCTION, LTD. |
| May 1, 2018 | 2561-01-011 | McCullochBrownwood | 17,643 CY | $37.60 | ALLEN KELLER COMPANY |
| May 1, 2018 | 1051-01-037 | EllisDallas | 4,303 CY | $72.00 | STERLING DELAWARE HOLDING COMPANY, INC. |
| Apr 4, 2018 | 0127-01-031 | EastlandBrownwood | 35,006 CY | $36.40 | RAY FARIS, INC. |
| Apr 4, 2018 | 0253-03-072 | ComalSan Antonio | 1,041 CY | $38.62 | HUNTER INDUSTRIES, LTD. |
| Apr 4, 2018 | 0909-22-175 | McLennanWaco | 324 CY | $31.60 | PROJECT ALLIED RESOURCES, LLC |