| 1 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$80,000.00 |
$70,000.00 |
$70,000.00 |
$130,000.00 |
| 2 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,600 | LF |
$1.75 |
$3.00 |
$2.00 |
$2.00 |
| 3 | 221(F) 0100 |
TEMPORARY SILT DIKE | 280 | LF |
$9.00 |
$10.00 |
$10.00 |
$10.00 |
| 4 | 230(A) 2806 |
SOLID SLAB SODDING | 15,254 | SY |
$2.50 |
$3.91 |
$3.91 |
$4.80 |
| 5 | 233(A) 2817 |
VEGETATIVE MULCHING | 3.15 | AC |
$350.00 |
$1,200.00 |
$700.00 |
$150.00 |
| 6 | 305 0125 |
CALICHE BASE | 658 | CY |
$60.00 |
$10.40 |
$10.40 |
$40.00 |
| 7 | 310(B) 0149 |
SUBGRADE, METHOD B | 2,900 | SY |
$3.50 |
$2.50 |
$2.50 |
$3.50 |
| 8 | 407(B) 0250 |
TACK COAT | 144 | GAL |
$4.00 |
$3.50 |
$3.50 |
$5.50 |
| 9 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 665 | TON |
$130.00 |
$140.00 |
$140.00 |
$168.00 |
| 10 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 315 | TON |
$145.00 |
$140.00 |
$140.00 |
$168.00 |
| 11 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$450.00 |
$650.00 |
$210.00 |
$385.00 |
| 12 | 613(B) 0694 |
48" CORR. GALV. STEEL PIPE | 228 | LF |
$70.00 |
$66.00 |
$70.00 |
$80.00 |
| 13 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 2,365 | SY |
$5.50 |
$2.00 |
$3.00 |
$6.00 |
| 14 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 2,400 | LF |
$1.40 |
$3.00 |
$3.00 |
$3.60 |
| 15 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 200 | CY |
$15.00 |
$25.00 |
$25.00 |
$15.50 |
| 16 | 501(G) 6309 |
CLSM BACKFILL | 98 | CY |
$220.00 |
$225.00 |
$230.00 |
$232.50 |
| 17 | 503(A) 1312 |
PRESTRESSED CONCRETE BEAMS (TYPE III) | 717 | LF |
$240.00 |
$300.00 |
$260.00 |
$250.00 |
| 18 | 504(B) 1305 |
SAW-CUT GROOVING | 591.2 | SY |
$6.00 |
$7.00 |
$9.00 |
$7.70 |
| 19 | 504(C) 6250 |
SEALED EXPANSION JOINT | 66.12 | LF |
$265.00 |
$300.00 |
$450.00 |
$310.00 |
| 20 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 553.4 | LF |
$74.00 |
$90.00 |
$85.00 |
$89.00 |
| 21 | 506(A) 1322 |
STRUCTURAL STEEL | 3,820 | LB |
$3.25 |
$3.50 |
$5.00 |
$5.60 |
| 22 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 9 | EA |
$900.00 |
$550.00 |
$730.00 |
$915.00 |
| 23 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 9 | EA |
$900.00 |
$550.00 |
$730.00 |
$915.00 |
| 24 | 509(A) 1326 |
CLASS AA CONCRETE | 187.2 | CY |
$650.00 |
$700.00 |
$735.00 |
$762.50 |
| 25 | 509(B) 1328 |
CLASS A CONCRETE | 125.6 | CY |
$675.00 |
$700.00 |
$735.00 |
$787.50 |
| 26 | 511(A) 1332 |
REINFORCING STEEL | 66,130 | LB |
$0.8500 |
$0.9000 |
$0.9000 |
$0.8800 |
| 27 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 224 | LF |
$30.00 |
$33.00 |
$45.00 |
$28.00 |
| 28 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 530 | LF |
$35.00 |
$40.00 |
$50.00 |
$44.80 |
| 29 | 514(A) 6016 |
PILES, FURNISHED (HP 14X89) | 816 | LF |
$55.00 |
$63.00 |
$85.00 |
$63.00 |
| 30 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 224 | LF |
$15.50 |
$13.00 |
$8.00 |
$12.00 |
| 31 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 530 | LF |
$15.50 |
$13.00 |
$8.00 |
$19.20 |
| 32 | 514(B) 6297 |
PILES, DRIVEN (HP 14X89) | 816 | LF |
$22.00 |
$13.00 |
$10.00 |
$27.00 |
| 33 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 34 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 887 | TON |
$65.00 |
$85.00 |
$90.00 |
$86.00 |
| 35 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 296 | TON |
$58.00 |
$85.00 |
$75.00 |
$76.00 |
| 36 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 60 | LF |
$30.00 |
$20.00 |
$55.00 |
$48.00 |
| 37 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 30 | LF |
$30.00 |
$20.00 |
$55.00 |
$80.00 |
| 38 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$10,000.00 |
$10,000.00 |
$15,000.00 |
$18,000.00 |
| 39 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$2,000.00 |
$2,200.00 |
$1,700.00 |
$1,860.00 |
| 40 | 623(F) 6029 |
GUARDRAIL ANCHOR UNIT (TYPE A) | 4 | EA |
$2,200.00 |
$1,625.00 |
$1,850.00 |
$2,000.00 |
| 41 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$6,500.00 |
$7,500.00 |
$8,300.00 |
$10,000.00 |
| 42 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$12,000.00 |
$11,000.00 |
$12,500.00 |
$14,000.00 |
| 43 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$3,500.00 |
$2,500.00 |
$3,500.00 |
$4,000.00 |
| 44 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$85,000.00 |
$95,000.00 |
$157,500.00 |
$87,500.00 |