Bid tab 170258

Let Aug 17, 2017 · Division 7 · Grady Sign up free

‹ Aug 2017 results

BRIDGE AND APPROACHES COUNTY ROAD (NS-277): OVER TRIBUTARY TO BUGGY CREEK , 0.8 MILES SOUTH OF SH-37/SH-152 NEAR MINCO. PROJECT LENGTH = 0.227 MILE

Let date
Thursday, August 17, 2017
Contract
170258
J/P numbers
29358(04)
District
Division 7
County
Grady
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (NS-277): OVER TRIBUTARY TO BUGGY CREEK , 0.8 MILES SOUTH OF SH-37/SH-152 NEAR MINCO. PROJECT LENGTH = 0.227 MILE
Project number
CIRB-226D(056)RB

Bidders 11

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 KLAVER CONSTRUCTION COMPANY, INC. Low bidder $449,455
2 T. McDonald Construction, Inc. $519,513 +15.6%
3 Reece Construction Co, Inc. $551,747 +22.8%
4 SEWELL BROS., INC. $570,577 +26.9%
5 HASKELL LEMON CONSTRUCTION CO. $582,886 +29.7%
6 K & R BUILDERS, INC. $583,331 +29.8%
7 Cimarron Construction Company, LLC $592,362 +31.8%
8 Treas Construction Inc $599,456 +33.4%
9 RRY SERVICES LLC $600,333 +33.6%
10 Redlands Contracting, LLC $629,398 +40.0%
11 BRIDGECO CONTRACTORS, INC. $647,615 +44.1%

Bid tab: unit prices 27 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 KLAVER CONSTRUC…#2 T. McDonald Con…#3 Reece Construct…#4 SEWELL BROS., I…#5 HASKELL LEMON C…#6 K & R BUILDERS,…#7 Cimarron Constr…#8 Treas Construct…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $7,000.00 $2,000.00 $3,000.00 $2,000.00 $4,000.00 $10,600.00 $5,250.00 $5,000.00 $3,150.00
2202(H) 0185 EARTHWORK1LSUM $40,500.00 $40,000.00 $35,737.76 $40,000.00 $40,000.00 $54,220.00 $44,700.00 $42,000.00 $44,100.00
3221(C) 2801 TEMPORARY SILT FENCE500LF $1.75 $1.30 $3.00 $1.30 $1.30 $1.35 $1.30 $1.50 $1.28
4221(F) 0100 TEMPORARY SILT DIKE200LF $10.00 $7.15 $8.00 $7.15 $9.65 $7.35 $7.25 $7.25 $15.75
5230(A) 2806 SOLID SLAB SODDING10,485SY $1.75 $1.22 $1.80 $1.22 $1.25 $1.25 $1.45 $1.45 $3.12
6233(A) 2817 VEGETATIVE MULCHING4.34AC $275.00 $50.00 $57.50 $50.00 $110.00 $51.50 $45.00 $50.00 $525.00
7402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E1,180TON $30.00 $26.50 $25.45 $26.50 $31.50 $32.10 $29.50 $31.00 $28.09
8408 5774 PRIME COAT1,580GAL $5.00 $3.50 $5.48 $3.50 $6.00 $6.60 $7.00 $5.00 $4.95
9509(D) 0325 CLASS C CONCRETE10CY $300.00 $325.00 $350.00 $426.00 $350.00 $322.00 $250.00 $250.00 $525.00
10601(A) 0297 TYPE I PLAIN RIPRAP900TON $40.00 $41.75 $40.75 $41.75 $46.00 $43.70 $43.50 $53.00 $42.98
11613(B) 0690 24" CORR. GALV. STEEL PIPE168LF $35.00 $20.00 $26.00 $20.00 $30.00 $45.50 $30.00 $37.00 $37.81
12613(L) 5730 24" PREFAB. CULVERT END SECTION, ROUND8EA $500.00 $200.00 $305.00 $200.00 $200.00 $765.00 $325.00 $415.00 $258.79
13619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $8,000.00 $6,000.00 $4,500.00 $6,000.00 $3,000.00 $11,080.00 $3,625.00 $7,500.00 $4,200.00
14624(C) 4458 FENCE-STYLE SWF (4 BARBED WIRE)1,926LF $4.50 $3.00 $5.00 $4.25 $8.80 $3.10 $6.00 $9.50 $8.40
15624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)1,162LF $5.50 $4.60 $6.00 $4.50 $9.50 $4.75 $6.30 $10.25 $9.03
16624(C) 7181 FENCE-STYLE SWF (6 BARBED WIRE)630LF $6.00 $5.30 $6.50 $4.75 $10.10 $5.45 $7.00 $11.10 $9.66
17624(H) 5920 (PL) GATE4EA $1,500.00 $500.00 $1,000.00 $500.00 $1,100.00 $515.00 $1,150.00 $1,200.00 $1,050.00
18202(A) 1301 UNCLASSIFIED EXCAVATION1,820CY $15.00 $7.00 $6.25 $7.00 $8.25 $9.50 $7.00 $8.35 $7.35
19501(A) 1306 STRUCTURAL EXCAVATION UNCLASSIFIED188CY $15.00 $5.00 $9.00 $14.00 $18.00 $18.30 $14.00 $11.50 $26.25
20509(A) 1326 CLASS AA CONCRETE454.3CY $500.00 $301.83 $350.00 $491.00 $475.00 $430.00 $495.00 $513.00 $420.21
21511(A) 1332 REINFORCING STEEL71,575LB $0.9500 $0.8500 $1.00 $0.8000 $0.7500 $0.9400 $0.8000 $0.8000 $0.9200
22601(B) 1353 TYPE I-A PLAIN RIPRAP700TON $60.00 $41.75 $40.75 $41.75 $46.00 $42.10 $43.50 $46.00 $50.33
23601(C) 1355 TYPE I-A FILTER BLANKET250TON $52.00 $31.75 $28.60 $31.75 $36.00 $36.20 $33.00 $34.00 $39.99
24880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $5,000.00 $2,140.00 $2,461.00 $2,140.00 $2,350.00 $2,204.00 $3,000.00 $2,600.00 $2,247.00
25642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $5,000.00 $3,600.00 $7,400.25 $4,200.00 $6,050.00 $3,708.00 $4,250.00 $4,350.00 $5,775.00
26220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $2,500.00 $4,500.00 $5,000.00 $3,000.00 $2,833.00 $2,500.00 $3,700.00 $2,625.00
27641 1399 MOBILIZATION1LSUM $60,100.00 $30,276.88 $50,000.00 $42,460.00 $30,000.00 $39,282.99 $43,250.00 $15,000.00 $48,007.98

Showing the first 8 bidders. The Excel and CSV downloads include all 11.