Bid tab 130357

Let Oct 17, 2013 · Division 2 · Bryan Sign up free

‹ Oct 2013 results

BRIDGE AND APPROACHES COUNTY ROAD (NS-382.5): OVER ISLAND BAYOU CREEK 3.2 MILES NORTH OF THE TOWN OF YUBA . PROJECT LENGTH = 0.236 MILE

Let date
Thursday, October 17, 2013
Contract
130357
J/P numbers
22488(04)
District
Division 2
County
Bryan
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (NS-382.5): OVER ISLAND BAYOU CREEK 3.2 MILES NORTH OF THE TOWN OF YUBA . PROJECT LENGTH = 0.236 MILE
Project number
STP-107D(098)CI

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$522,209
1 HUB Construction, Inc. Low bidder $549,044 +5.1%
2 K & R BUILDERS, INC. $592,428 +13.4% +7.9%
3 L & N BRIDGE, LLC $615,397 +17.8% +12.1%
4 EARTH BUILDERS, L.P. $721,427 +38.1% +31.4%

Bid tab: unit prices 41 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 HUB Constructio…#2 K & R BUILDERS,…#3 L & N BRIDGE, L…#4 EARTH BUILDERS,…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $5,000.00 $9,000.00 $14,170.00 $10,000.00 $10,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION4,530CY $4.00 $6.00 $7.50 $4.25 $10.00
3202(D) 0184 UNCLASSIFIED BORROW5,240CY $5.00 $7.00 $9.65 $12.25 $10.00
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $12,227.78 $3,500.00 $8,000.00 $10,000.00 $5,000.00
5221(C) 2801 TEMPORARY SILT FENCE2,293LF $3.00 $3.00 $1.60 $1.39 $1.50
6221(F) 0100 TEMPORARY SILT DIKE182LF $8.00 $6.00 $10.00 $8.66 $10.00
7230(A) 2806 SOLID SLAB SODDING17,608SY $1.00 $2.00 $1.72 $1.54 $2.00
8233(A) 2817 VEGETATIVE MULCHING3.64AC $500.00 $350.00 $537.50 $644.00 $1,000.00
9402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E1,062TON $30.00 $28.00 $26.57 $25.00 $30.00
10509(D) 0325 CLASS C CONCRETE10CY $250.00 $300.00 $275.00 $275.00 $300.00
11613(B) 4530 42" X 29" CORR. GALV. STEEL PIPE ARCH54LF $50.00 $50.00 $47.00 $50.00 $75.00
12613(P) 4573 42" X 29" GALV. STEEL CULVERT END SECTION ARCH2EA $500.00 $500.00 $532.00 $500.00 $600.00
13624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)1,059LF $4.00 $5.00 $4.70 $5.00 $9.00
14624(D) 4470 GATE, GALVANIZED STEEL1EA $500.00 $150.00 $896.00 $700.00 $2,500.00
15501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON84CY $25.00 $12.00 $10.50 $35.00 $20.00
16501(G) 6309 CLSM BACKFILL82CY $100.00 $140.00 $170.00 $175.00 $150.00
17503(A) 1313 PRESTRESSED CONCRETE BEAMS (TYPE IV)416.67LF $200.00 $205.00 $186.75 $232.00 $225.00
18504(B) 1305 SAW-CUT GROOVING319.6SY $4.50 $7.00 $7.00 $6.25 $7.00
19504(D) 6239 CONCRETE RAIL (TR3)275LF $75.00 $75.00 $73.00 $95.00 $90.00
20506(A) 1322 STRUCTURAL STEEL1,810LB $3.50 $2.50 $2.70 $2.25 $5.00
21507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY4EA $750.00 $750.00 $800.00 $500.00 $1,000.00
22507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY4EA $750.00 $750.00 $800.00 $500.00 $1,000.00
23509(A) 1326 CLASS AA CONCRETE80.6CY $450.00 $600.00 $585.00 $650.00 $600.00
24509(B) 1328 CLASS A CONCRETE60.1CY $400.00 $650.00 $615.00 $650.00 $600.00
25511(A) 1332 REINFORCING STEEL26,558LB $1.00 $1.00 $0.9000 $1.00 $1.00
26514(A) 6010 PILES, FURNISHED (HP 10X42)80LF $30.00 $35.00 $39.55 $30.00 $30.00
27514(A) 6011 PILES, FURNISHED (HP 12X53)882LF $35.00 $40.00 $33.25 $32.00 $35.00
28514(B) 6292 PILES, DRIVEN (HP 10X42)80LF $15.00 $10.00 $16.95 $16.00 $40.00
29514(B) 6294 PILES, DRIVEN (HP 12X53)882LF $15.00 $10.00 $14.25 $14.00 $40.00
30601(D) 1357 TYPE II SPECIAL PLAIN RIPRAP1,610TON $30.00 $35.00 $36.28 $32.00 $40.00
31602(C) 4205 FILTER FABRIC1,000SY $7.00 $2.00 $3.00 $2.00 $35.00
32619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $2,500.00 $5,000.00 $4,850.00 $7,500.00 $20,000.00
33623(F) 6033 GUARDRAIL ANCHOR UNIT (TYPE II)3EA $2,200.00 $2,200.00 $2,465.00 $2,000.00 $2,500.00
34623(F) 6034 GUARDRAIL ANCHOR UNIT (TYPE III)1EA $2,000.00 $1,950.00 $1,905.00 $1,700.00 $2,500.00
35850(A) 8110 SHEET ALUMINUM SIGNS17SF $18.00 $18.00 $15.68 $14.00 $25.00
36851(D) 8597 FLANGE CHANNEL POSTS(4 LB/FT)34LF $14.00 $20.00 $8.96 $8.00 $25.00
37853 9033 DELINEATORS(TYPE 2, CODE 1)16EA $20.00 $30.00 $20.16 $18.00 $50.00
38880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $2,000.00 $3,500.00 $2,300.00 $1,800.00 $3,500.00
39642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $6,000.00 $5,000.00 $9,400.00 $2,500.00 $5,000.00
40220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $1,500.00 $2,800.00 $2,500.00 $3,000.00
41641 1399 MOBILIZATION1LSUM $47,000.00 $10,000.00 $35,925.00 $50,000.00 $35,000.00