| 1 | 201 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$35,000.00 |
$7,500.00 |
$2,500.00 |
$7,700.00 |
$6,600.00 |
$5,846.27 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 3,279 | CY |
$7.00 |
$3.00 |
$4.50 |
$6.60 |
$5.73 |
$9.55 |
| 3 | 202(C) 0184 |
UNCLASSIFIED BORROW | 450 | CY |
$12.00 |
$10.00 |
$6.00 |
$8.80 |
$5.73 |
$12.81 |
| 4 | 205 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$40,000.00 |
$2,000.00 |
$3,000.00 |
$4,950.00 |
$19,500.00 |
$29,046.80 |
| 5 | 223 2801 |
TEMPORARY SILT FENCE | 3,383 | LF |
$2.75 |
$1.25 |
$0.7000 |
$0.7700 |
$1.50 |
$2.35 |
| 6 | 227 0100 |
TEMPORARY SILT DIKE | 140 | LF |
$8.25 |
$8.50 |
$4.50 |
$4.95 |
$10.00 |
$15.22 |
| 7 | 230(A) 2806 |
SOLID SLAB SODDING | 9,511 | SY |
$2.00 |
$1.60 |
$1.59 |
$1.75 |
$3.00 |
$1.55 |
| 8 | 232(B) 2814 |
SEEDING METHOD B | 5.28 | AC |
$750.00 |
$405.00 |
$200.00 |
$110.00 |
$650.00 |
$734.62 |
| 9 | 233(A) 2817 |
VEGETATIVE MULCHING | 5.28 | AC |
$600.00 |
$205.00 |
$100.00 |
$220.00 |
$900.00 |
$675.85 |
| 10 | 241 2832 |
MOWING | 10.56 | AC |
$98.00 |
$20.00 |
$50.00 |
$55.00 |
$120.00 |
$99.91 |
| 11 | 303 0192 |
AGGREGATE BASE | 578 | CY |
$48.00 |
$45.00 |
$52.00 |
$56.18 |
$65.00 |
$76.53 |
| 12 | 325 5271 |
SEPARATOR FABRIC | 2,909 | SY |
$1.50 |
$1.00 |
$2.25 |
$1.65 |
$2.00 |
$2.35 |
| 13 | 327(J) 4290 |
(SP)MODIFIED SUBGRADE | 4,574 | SY |
$7.00 |
$3.75 |
$6.30 |
$9.01 |
$7.00 |
$8.23 |
| 14 | 403(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 468 | TON |
$25.50 |
$22.00 |
$35.00 |
$29.09 |
$29.50 |
$34.67 |
| 15 | 411(S3) 5945 |
(SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | 1,852 | TON |
$69.00 |
$75.00 |
$74.00 |
$81.95 |
$80.00 |
$94.03 |
| 16 | 411(S4) 5960 |
(SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) | 944 | TON |
$73.00 |
$80.00 |
$78.00 |
$86.90 |
$95.00 |
$111.66 |
| 17 | 417 5267 |
COLD MILLING PAVEMENT | 1,324 | SY |
$2.25 |
$6.50 |
$5.00 |
$6.50 |
$4.00 |
$4.70 |
| 18 | 613(D) 0690 |
24" CORR. GALV. STEEL PIPE | 32 | LF |
$36.00 |
$24.00 |
$26.50 |
$27.70 |
$43.00 |
$33.87 |
| 19 | 613(D) 4527 |
21" X 15" CORR. GALV. STEEL PIPE ARCH | 56 | LF |
$32.00 |
$22.00 |
$23.50 |
$22.34 |
$45.00 |
$34.80 |
| 20 | 613(D) 4528 |
28" X 20" CORR. GALV. STEEL PIPE ARCH | 30 | LF |
$35.00 |
$25.00 |
$28.00 |
$28.24 |
$48.00 |
$38.62 |
| 21 | 613(M) 4516 |
28" X 20" PREFAB. CULVERT END SECTION, ARCH | 2 | EA |
$675.00 |
$240.00 |
$315.00 |
$207.82 |
$300.00 |
$179.27 |
| 22 | 613(M) 5730 |
24" PREFAB. CULVERT END SECTION, ROUND | 2 | EA |
$675.00 |
$240.00 |
$315.00 |
$225.72 |
$300.00 |
$197.92 |
| 23 | 613(P) 1091 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 440 | LF |
$12.00 |
$7.50 |
$25.00 |
$13.80 |
$8.00 |
$14.98 |
| 24 | 613(Q) 1096 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 100 | LF |
$25.00 |
$7.50 |
$25.00 |
$25.09 |
$8.00 |
$14.98 |
| 25 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$27,000.00 |
$1,000.00 |
$1,500.00 |
$9,900.00 |
$7,000.00 |
$10,607.47 |
| 26 | 619(B) 4725 |
REMOVAL OF FENCE | 2,603 | LF |
$3.00 |
$1.00 |
$1.00 |
$1.10 |
$1.50 |
$2.72 |
| 27 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 3,196 | SY |
$3.50 |
$3.00 |
$5.50 |
$3.30 |
$4.00 |
$4.70 |
| 28 | 619(C) 0924 |
SAWING PAVEMENT | 2,310 | LF |
$4.00 |
$2.00 |
$3.00 |
$3.30 |
$3.50 |
$4.11 |
| 29 | 624(C) 4459 |
(SP)FENCE-STYLE SWF (5 BARBED WIRE) | 2,591 | LF |
$4.00 |
$4.40 |
$3.75 |
$4.72 |
$4.75 |
$5.04 |
| 30 | 653(C) 5946 |
OUTLET LATERAL HEADWALL | 2 | EA |
$625.00 |
$350.00 |
$775.00 |
$645.04 |
$500.00 |
$1,095.75 |
| 31 | 202(A) 1301 |
UNCLASSIFIED EXCAVATION | 10,680 | CY |
$5.50 |
$3.00 |
$3.50 |
$2.20 |
$4.73 |
$7.95 |
| 32 | 501(A) 1306 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 256 | CY |
$15.00 |
$4.00 |
$30.00 |
$19.80 |
$6.00 |
$18.19 |
| 33 | 509(A) 1326 |
CLASS AA CONCRETE | 714.5 | CY |
$500.00 |
$324.00 |
$270.00 |
$351.29 |
$360.00 |
$512.83 |
| 34 | 511(A) 1332 |
REINFORCING STEEL | 98,820 | LB |
$0.8000 |
$0.7000 |
$0.7000 |
$0.8200 |
$0.8000 |
$0.7200 |
| 35 | 601(A-1)1353 |
TYPE I-A PLAIN RIPRAP | 160 | TON |
$40.00 |
$34.00 |
$40.00 |
$33.13 |
$45.00 |
$34.62 |
| 36 | 601(A-2)1355 |
TYPE I-A FILTER BLANKET | 35 | TON |
$35.00 |
$31.00 |
$41.00 |
$28.39 |
$45.00 |
$29.63 |
| 37 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$7,500.00 |
$2,000.00 |
$15,000.00 |
$7,700.00 |
$4,000.00 |
$8,830.29 |
| 38 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 4,600 | LF |
$0.5000 |
$0.7000 |
$0.6800 |
$0.7500 |
$0.7500 |
$0.8000 |
| 39 | 856(A) 8839 |
CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 4,600 | LF |
$0.1500 |
$0.1100 |
$0.1000 |
$0.1100 |
$0.5000 |
$0.1200 |
| 40 | 856(G) 8887 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 750 | EA |
$0.5000 |
$0.9600 |
$0.9500 |
$1.05 |
$1.00 |
$1.12 |
| 41 | 859(A) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 200 | LF |
$0.1500 |
$0.5500 |
$0.5000 |
$0.5500 |
$1.00 |
$0.5900 |
| 42 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$9,730.75 |
$4,225.00 |
$4,220.00 |
$4,642.00 |
$5,000.00 |
$4,960.14 |
| 43 | 882(B) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 240 | SD |
$15.50 |
$19.00 |
$18.80 |
$20.68 |
$20.00 |
$22.10 |
| 44 | 642 0098 |
STAKING | 1 | LSUM |
$9,025.47 |
$9,400.00 |
$8,500.00 |
$9,075.00 |
$8,500.00 |
$7,052.33 |
| 45 | 220 2800 |
(SP)SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$1,500.00 |
$3,000.00 |
$3,300.00 |
$10,000.00 |
$4,759.21 |
| 46 | 640 1398 |
FIELD OFFICE | 1 | EA |
$5,000.00 |
$2,000.00 |
$5,000.00 |
$5,500.00 |
$5,400.00 |
$5,220.49 |
| 47 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$47,372.64 |
$21,642.75 |
$40,250.00 |
$36,195.51 |
$38,000.00 |
$27,232.25 |