Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Feb 19, 2025 | 6475-48-001RMC - A00212574 | Houston Lufkin |
2024-11 Houston Tree and Brush RemovalUS0287 · Routine Maintenance Project | $299,375 | $227,400 | J AND J CUSTOM TREE SERVICE LLC | -24.0% | 10 |
| Feb 19, 2025 | 6479-57-001MMC - A00213880 | Jim Wells Corpus Christi |
6479-57-001 Emulsion Alice Area OfficeUS0281 · Material Maintenance Project | $228,600 | $223,380 | ERGON ASPHALT & EMULSIONS, INC. | -2.3% | 1 |
| Feb 19, 2025 | 6475-49-001RMC - A00212576 | Polk Lufkin |
2024-11 Polk Tree And Brush RemovalUS0059 · Routine Maintenance Project - Sealed | $189,525 | $131,060 | LAKEY, INC. | -30.8% | 8 |
| Feb 19, 2025 | 6478-74-001RMC - A00213546 | Nacogdoches Lufkin |
2025-02 Nacogdoches MBGFUS0059 · Routine Maintenance Project - Sealed | $130,180 | $98,012 | ACE CONTRACTORS, INC. | -24.7% | 5 |
| Feb 19, 2025 | 6480-96-001SUP - A00214312 | Carson Amarillo |
Debris Pickup Pampa AE FY 25IH0040 · State Use Project | $113,259 | — | 0 | ||
| Feb 19, 2025 | 6477-71-001SUP - A00213111 | Hopkins Paris |
Janitorial Maint - HopkinsIH0030 · State Use Project | $19,926 | — | 0 | ||
| Feb 18, 2025 | 6476-59-001MMC - A00212837 | Matagorda Yoakum |
Hot Mix-Matagorda (Materials Only)SH0035 · Material Maintenance Project | $987,000 | $976,500 | QUALITY HOT MIX, INC. | -1.1% | 3 |
| Feb 18, 2025 | 6476-58-001MMC - A00212835 | Austin Yoakum |
Hot Mix - Austin County (Materials Only)IH0010 · Material Maintenance Project | $976,500 | $971,250 | QUALITY HOT MIX, INC. | -0.5% | 2 |
| Feb 18, 2025 | 6476-60-001MMC - A00212838 | Wharton Yoakum |
Hot Mix-Wharton County (Materials Only)US0059 · Material Maintenance Project | $955,500 | $945,000 | QUALITY HOT MIX, INC. | -1.1% | 4 |
| Feb 18, 2025 | 6476-61-001MMC - A00212839 | Colorado Yoakum |
Hot Mix-Colorado County (Materials Only)SH0071 · Material Maintenance Project | $945,000 | $892,500 | BRAUNTEX MATERIALS, INC. | -5.6% | 4 |
| Feb 18, 2025 | 6476-56-001MMC - A00212831 | Wharton Yoakum |
LRA-WAO (Materials Only)US0059 · Material Maintenance Project | $643,000 | $635,010 | MARTIN MARIETTA MATERIALS, INC. | -1.2% | 2 |
| Feb 18, 2025 | 6476-93-001MMC - A00212906 | Wharton Yoakum |
Asph/Oils/Emuls-WAO (Materials Only)US0059 · Material Maintenance Project | $656,875 | $567,231 | WRIGHT ASPHALT PRODUCTS COMPANY LLC | -13.6% | 3 |
| Feb 18, 2025 | 6476-57-001MMC - A00212832 | Wharton Yoakum |
Flexbase-WAO (Materials Only)US0059 · Material Maintenance Project | $587,600 | $560,700 | COLORADO MATERIALS, LTD. | -4.6% | 6 |
| Feb 18, 2025 | 6476-51-001MMC - A00212821 | Wharton Yoakum |
Aggregate-WAO (Materials Only)US0059 · Material Maintenance Project | $428,100 | $419,800 | QUALITY HOT MIX, INC. | -1.9% | 5 |
| Feb 18, 2025 | 6472-92-001RMC - A00212082 | Chambers Beaumont |
FY 25 MBGFIH0010 · Routine Maintenance Project - Sealed | $368,260 | $258,947 | HAZMAT INTERNATIONAL, INC. | -29.7% | 6 |
| Feb 18, 2025 | 6476-64-001MMC - A00212845 | Matagorda Yoakum |
Hot Mix CL-Matagorda (Materials Only)SH0035 · Material Maintenance Project | $247,500 | $246,250 | QUALITY HOT MIX, INC. | -0.5% | 5 |
| Feb 18, 2025 | 6476-63-001MMC - A00212842 | Wharton Yoakum |
Hot Mix CL-Wharton (Materials Only)US0059 · Material Maintenance Project | $232,500 | $227,500 | BRAUNTEX MATERIALS, INC. | -2.2% | 5 |
| Feb 18, 2025 | 6476-65-001MMC - A00212847 | Austin Yoakum |
Hot Mix CL-Austin Co. (Materials Only)IH0010 · Material Maintenance Project | $235,000 | $225,000 | BRAUNTEX MATERIALS, INC. | -4.3% | 5 |
| Feb 18, 2025 | 6476-62-001MMC - A00212840 | Colorado Yoakum |
Hot Mix CL-Colorado (Materials Only)SH0071 · Material Maintenance Project | $227,500 | $217,500 | BRAUNTEX MATERIALS, INC. | -4.4% | 4 |
| Feb 18, 2025 | 6479-48-001MMC - A00213868 | Jefferson Beaumont |
FY 25 Hydraulic CementSH0347 · Material Maintenance Project - Sealed | $190,784 | $183,776 | TOUCHSTONE RESOURCES, LLC | -3.7% | 2 |
| Feb 18, 2025 | 6476-54-001MMC - A00212828 | Wharton Yoakum |
Asph Patching Mat-WAO (Materials Only)US0059 · Material Maintenance Project | $125,500 | $126,125 | WALLER COUNTY ASPHALT INC. | +0.5% | 1 |
| Feb 18, 2025 | 6476-53-001MMC - A00212827 | Wharton Yoakum |
Rock/Riprap-WAO (Materials Only)US0059 · Material Maintenance Project | $119,000 | $123,550 | TOUCHSTONE RESOURCES, LLC | +3.8% | 3 |
| Feb 18, 2025 | 6476-52-001MMC - A00212822 | Wharton Yoakum |
Lime-WAO (Materials Only)US0059 · Material Maintenance Project | $79,250 | $101,872 | SOUTHERN SOURCING SOLUTIONS, LLC | +28.5% | 2 |
| Feb 18, 2025 | 6476-55-001MMC - A00212829 | Wharton Yoakum |
Hydraulic Cement-WAO (Materials Only)US0059 · Material Maintenance Project | $104,063 | $101,419 | AKA-MATERIALS | -2.5% | 3 |
| Feb 18, 2025 | 6476-95-001SUP - A00212909 | Bowie Atlanta |
Litter Pickup & Disposal Bowie & CassIH0030 · State Use Project | $147,574 | — | 0 | ||
| Feb 18, 2025 | 6477-72-001SUP - A00213113 | Grayson Paris |
Janitorial Maint - GraysonUS0075 · State Use Project | $36,025 | — | 0 | ||
| Feb 13, 2025 | 6480-68-001SUP - A00214251 | Jefferson Beaumont |
PORT ARTHUR LITTER MAINT.SH0347 · State Use Project | $213,449 | — | 0 | ||
| Feb 13, 2025 | 6480-67-001SUP - A00214244 | Jefferson Beaumont |
BEAUMONT AO/MO GROUNDS MAINT.US0069 · State Use Project | $6,309 | — | 0 | ||
| Feb 13, 2025 | 6480-59-001SUP - A00214194 | Chambers Beaumont |
ANAHUAC JANITORIAL MNT.FM0563 · State Use Project | $6,279 | — | 0 | ||
| Feb 13, 2025 | 6468-51-001SUP - A00210153 | Galveston Houston |
SUP 6468-51-001 JANITORIAL MAINTENANCEIH0045 · State Use Project | $69,064 | — | 0 | ||
| Feb 13, 2025 | 6480-72-001SUP - A00214258 | Jasper Beaumont |
JASPER JANITORIAL MAINTENANCEUS0190 · State Use Project | $14,008 | — | 0 | ||
| Feb 13, 2025 | 6480-75-001SUP - A00214272 | Newton Beaumont |
NEWTON JANITORIAL MAINT.US0190 · State Use Project | $10,159 | — | 0 | ||
| Feb 13, 2025 | 6480-85-001SUP - A00214285 | Tyler Beaumont |
WOODVILLE JANITORIAL MAINT.US0069 · State Use Project | $15,566 | — | 0 | ||
| Feb 12, 2025 | 6479-31-001MMC - A00213846 | Milam Bryan |
FY25 - Milam HMA -02SH0036 · Material Maintenance Project | $519,000 | $390,150 | LONE STAR PAVING COMPANY | -24.8% | 4 |
| Feb 12, 2025 | 6475-60-001MMC - A00212606 | Kaufman Dallas |
Aggregate (Matls Only)06 0225FM2728 · Material Maintenance Project | $270,000 | $290,000 | ARCOSA LWS, LLC | +7.4% | 1 |
| Feb 12, 2025 | 6479-28-001MMC - A00213842 | Washington Bryan |
FY25 - Brenham AO Riprap -02SH0036 · Material Maintenance Project | $297,000 | $288,300 | TOUCHSTONE RESOURCES, LLC | -2.9% | 4 |
| Feb 12, 2025 | 6472-59-001RMC - A00212005 | Collin Dallas |
Raised Pavement Markers 07 1224US0075 · Routine Maintenance Project - Sealed | $599,729 | $287,731 | TRP INFRASTRUCTURE SERVICES, LLC | -52.0% | 3 |
| Feb 12, 2025 | 6479-12-001RMC - A00213818 | Freestone Bryan |
FY25 - Freestone Mowing - 02SH0075 · Routine Maintenance Project | $325,300 | $276,271 | ABESCAPE GROUP LLC | -15.1% | 4 |
| Feb 12, 2025 | 6475-35-001MMC - A00212538 | Ellis Dallas |
Hot Mix Material 09 1124FM0876 · Material Maintenance Project | $337,800 | $275,000 | TEXAS MATERIALS GROUP, INC. | -18.6% | 2 |
| Feb 12, 2025 | 6468-13-001RMC - A00210084 | Travis Austin |
FY25 Travis Co. MowingUS0183 · Routine Maintenance Project - Sealed | $261,384 | $253,920 | ABESCAPE GROUP LLC | -2.9% | 3 |
| Feb 12, 2025 | 6471-19-001RMC - A00211526 | Ellis Dallas |
Raised Pavement Markers 09 0225IH0035E · Routine Maintenance Project - Sealed | $340,923 | $235,372 | TRP INFRASTRUCTURE SERVICES, LLC | -31.0% | 4 |
| Feb 12, 2025 | 6475-58-001MMC - A00212604 | Kaufman Dallas |
HMAC (Matls Only)06 0225FM2728 · Material Maintenance Project | $211,800 | $234,000 | TEXAS MATERIALS GROUP, INC. | +10.5% | 2 |
| Feb 12, 2025 | 6479-14-001RMC - A00213820 | Madison Bryan |
FY25 - Madison Mowing -02US0190 · Routine Maintenance Project | $248,760 | $193,951 | ROY LEE WALKER | -22.0% | 4 |
| Feb 12, 2025 | 6475-55-001RMC - A00212584 | Denton Dallas |
Culvert Cleaning 04 0225IH0035W · Routine Maintenance Project - Sealed | $176,750 | $150,022 | BK FIELD OPERATIONS LLC | -15.1% | 6 |
| Feb 12, 2025 | 6469-20-001MMC - A00210438 | Denton Dallas |
CRS2P 04 0225US0380 · Material Maintenance Project | $178,200 | $142,560 | ERGON ASPHALT & EMULSIONS, INC. | -20.0% | 3 |
| Feb 12, 2025 | 6474-21-001RMC - A00212338 | Navarro Dallas |
01 Driftwood Removal 0225FM3041 · Routine Maintenance Project - Sealed | $191,950 | $136,521 | BK FIELD OPERATIONS LLC | -28.9% | 8 |
| Feb 12, 2025 | 6478-23-001RMC - A00213235 | Brazos Bryan |
FY25 - District Illumination -01SH0006 · Routine Maintenance Project - Sealed | $161,490 | $124,451 | LAKEY, INC. | -22.9% | 5 |
| Feb 12, 2025 | 6478-45-001MMC - A00213351 | Collin Dallas |
Hydraulic Cement FY25SH0005 · Material Maintenance Project | $142,400 | $124,000 | AKA-MATERIALS | -12.9% | 3 |
| Feb 12, 2025 | 6479-26-001MMC - A00213838 | Washington Bryan |
FY25 - Brenham AO TY B Gr 5 - 02SH0036 · Material Maintenance Project | $127,500 | $112,500 | TOUCHSTONE RESOURCES, LLC | -11.8% | 4 |
| Feb 12, 2025 | 6469-71-001RMC - A00210587 | Denton Dallas |
RPM Denton FY 25IH0035 · Routine Maintenance Project - Sealed | $149,439 | $89,078 | TRP INFRASTRUCTURE SERVICES, LLC | -40.4% | 3 |
| Feb 12, 2025 | 6471-06-001MMC - A00211497 | Denton Dallas |
04 Hot Mix Material - 10/2024US0380 · Material Maintenance Project | $86,800 | $78,950 | JAGOE-PUBLIC COMPANY | -9.0% | 4 |
| Feb 12, 2025 | 6462-79-001RMC - A00206885 | Navarro Dallas |
Raised Pavement Markers 01 0225IH0045 · Routine Maintenance Project - Sealed | $73,172 | $48,005 | TRP INFRASTRUCTURE SERVICES, LLC | -34.4% | 4 |
| Feb 12, 2025 | 6478-32-001SUP - A00213264 | Brazoria Houston |
SUP Brazoria Janitorial FY25-FY26FM0523 · State Use Project | $31,590 | — | 0 | ||
| Feb 11, 2025 | 6476-12-001MMC - A00212750 | Gregg Tyler |
FY25 Emulsion LongviewUS0259 · Material Maintenance Project | $875,500 | $884,010 | ERGON ASPHALT & EMULSIONS, INC. | +1.0% | 1 |
| Feb 11, 2025 | 6472-81-001RMC - A00212048 | Jefferson Beaumont |
FY 25 Striping RMCIH0010 · Routine Maintenance Project | $719,054 | $847,583 | TRP INFRASTRUCTURE SERVICES, LLC | +17.9% | 3 |
| Feb 11, 2025 | 6477-10-001RMC - A00212932 | Henderson Tyler |
FY 25 Henderson Co. ROW MowingUS0175 · Routine Maintenance Project | $943,587 | $736,320 | 12TWELVE ROAD AND BRIDGE LLC | -22.0% | 6 |
| Feb 11, 2025 | 6476-16-001MMC - A00212759 | Henderson Tyler |
FY25 Emulsion - AthensSH0031 · Material Maintenance Project | $680,750 | $591,400 | ERGON ASPHALT & EMULSIONS, INC. | -13.1% | 1 |
| Feb 11, 2025 | 6467-49-001MMC - A00209742 | El Paso El Paso |
Hot Mix Asphalt- HMA- El Paso CountyIH0010 · Material Maintenance Project | $595,000 | $547,600 | JOBE MATERIALS, L.P. | -8.0% | 1 |
| Feb 11, 2025 | 6478-95-001RMC - A00213677 | Brazos Bryan |
FY25 - District Shortline - 02SH0006 · Routine Maintenance Project | $574,688 | $542,050 | RHINO EQUITY, LLC | -5.7% | 6 |
| Feb 11, 2025 | 6479-18-001MMC - A00213827 | Walker Bryan |
FY25 - Huntsville AO Hyd. Cement - 02IH0045 · Material Maintenance Project | $536,016 | $521,178 | TOUCHSTONE RESOURCES, LLC | -2.8% | 3 |
| Feb 11, 2025 | 6477-26-001MMC - A00212970 | Ector Odessa |
6477-26-001 Hot MixIH0020 · Material Maintenance Project | $578,000 | $492,692 | SOUTHERN SOURCING SOLUTIONS, LLC | -14.8% | 2 |
| Feb 11, 2025 | 6479-32-001MMC - A00213847 | Robertson Bryan |
FY25 - Robertson HMA -02SH0006 · Material Maintenance Project | $597,500 | $481,500 | BIG CREEK CONSTRUCTION, LTD. | -19.4% | 3 |
| Feb 11, 2025 | 6479-11-001RMC - A00213817 | Burleson Bryan |
FY25 - Brenham AO Tree RemovalSH0036 · Routine Maintenance Project | $523,900 | $410,528 | ICOS MANAGEMENT, LLC | -21.6% | 5 |
| Feb 11, 2025 | 6479-30-001MMC - A00213845 | Burleson Bryan |
FY25 - Burleson HMA -02SH0036 · Material Maintenance Project | $502,000 | $401,000 | BIG CREEK CONSTRUCTION, LTD. | -20.1% | 4 |
| Feb 11, 2025 | 6479-13-001RMC - A00213819 | Robertson Bryan |
FY25 - Robertson Mowing -02US0190 · Routine Maintenance Project | $382,988 | $352,364 | R&M INCORPORATED | -8.0% | 5 |
| Feb 11, 2025 | 6477-24-001RMC - A00212968 | Pecos Odessa |
6477-24-001 Striping CalloutIH0010 · Routine Maintenance Project | $304,000 | $242,300 | L&L COMPANY | -20.3% | 4 |
| Feb 11, 2025 | 6477-22-001MMC - A00212966 | Pecos Odessa |
6477-22-001 Hot MixIH0010 · Material Maintenance Project | $280,000 | $237,500 | A. L. HELMCAMP, INC. | -15.2% | 2 |
| Feb 11, 2025 | 6479-19-001RMC - A00213828 | Liberty Beaumont |
FY 25 Liberty Tree and Brush RemovalUS0090 · Routine Maintenance Project | $273,650 | $218,625 | GV LANDSCAPE AND CONSTRUCTION LLC | -20.1% | 8 |
| Feb 11, 2025 | 6479-37-001MMC - A00213854 | Jefferson Beaumont |
FY 25 Asphalt Patching MaterialUS0069 · Material Maintenance Project - Sealed | $208,500 | $193,390 | WALLER COUNTY ASPHALT INC. | -7.2% | 1 |
| Feb 11, 2025 | 6479-27-001MMC - A00213839 | Walker Bryan |
FY25 - Huntsville AO TY B Gr 5 - 02IH0045 · Material Maintenance Project | $170,000 | $146,895 | SOUTHERN SOURCING SOLUTIONS, LLC | -13.6% | 5 |
| Feb 7, 2025 | 0009-11-254F 2025(365) | Dallas Dallas |
IH 30 Canyon from IH 35E to IH 45IH 30 · Widen Freeway | $795,333,911 | $888,696,937 | BALFOUR BEATTY INFRASTRUCTURE, INC. | +11.7% | 3 |
| Feb 7, 2025 | 0275-02-075BR 2025(429) | Carson Amarillo |
BI 40D EB Bridge ReplacementIH 40 · Bridge Replacement | $10,602,018 | $9,874,035 | ALTUS CONSTRUCTION LLC | -6.9% | 6 |
| Feb 7, 2025 | 0053-08-079C 53-8-79 | Scurry Abilene |
US 84 0053-08 N OF FM 1611 TO AVE E WBUS 84 · Overlay | $10,972,084 | $8,390,976 | RK HALL, LLC | -23.5% | 5 |
| Feb 7, 2025 | 0072-12-201C 72-12-201 | Bexar San Antonio |
IH 10: 0072-12-201: OVIH 10 · Overlay | $8,104,179 | $6,824,351 | LONE STAR PAVING COMPANY | -15.8% | 5 |
| Feb 7, 2025 | 0156-06-066C 156-6-66 | Baylor Wichita Falls |
US 82; US 183 to CR 218US 82 · Overlay | $6,736,851 | $5,952,851 | A. L. HELMCAMP, INC. | -11.6% | 5 |
| Feb 7, 2025 | 0319-04-091F 2B24(066) | Angelina Lufkin |
SH 94_E of SL 287 to Herndon St - OVSH 94 · Overlay | $4,212,021 | $4,633,048 | TEXAS MATERIALS GROUP, INC. | +10.0% | 2 |
| Feb 7, 2025 | 0042-06-077BR 2025(364) | Donley Childress |
US 287 @ Drainage DitchUS 287 · Bridge Replacement | $3,194,305 | $4,458,100 | HODGES AND SON CONSTRUCTION COMPANY, INC. | +39.6% | 3 |
| Feb 7, 2025 | 0206-05-033C 206-5-33 | Cherokee Tyler |
US79,RUSKC/L-SH110,RRRUS 79 · Rehabilitation of Existing Road | $6,215,435 | $4,258,941 | MADDEN CONTRACTING COMPANY, LLC. | -31.5% | 7 |
| Feb 7, 2025 | 0049-13-010C 49-13-10 | Falls Waco |
Rehab & Widen | FM 46 |SH 6| RoberstonCLFM 46 · Rehabilitation of Existing Road | $4,914,109 | $3,949,757 | BIG CREEK CONSTRUCTION, LTD. | -19.6% | 6 |
| Feb 7, 2025 | 0903-00-128C 903-00-128 | Wichita Wichita Falls |
FY 25 District wide Bridge PMVarious · Bridge Maintenance | $4,035,462 | $3,651,021 | THK CONSTRUCTION LLC | -9.5% | 8 |
| Feb 7, 2025 | 0110-03-084C 110-3-84 | Montgomery Houston |
SH 75, SL 336N to SH 105SH 75 · Overlay | $4,233,683 | $3,303,124 | VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC | -22.0% | 6 |
| Feb 7, 2025 | 0739-02-183F 2025(460) | Jefferson Beaumont |
IH 10FR(HAMSHIRE RD-N. FORK TAYLOR BAYOUIH 10 · Rehabilitation of Existing Road | $4,738,305 | $3,084,194 | TEXAS MATERIALS GROUP, INC. | -34.9% | 6 |
| Feb 7, 2025 | 0363-01-148C 363-1-148 | Tarrant Fort Worth |
SH 183; E US 377 to W Big Fossil CrkSH 183 · Overlay | $3,511,801 | $3,019,197 | JAGOE-PUBLIC COMPANY | -14.0% | 5 |
| Feb 7, 2025 | 0495-07-087F 2025(411) | Gregg Tyler |
IH 20, UPRR - HARRISON CLIH 20 · Restoration | $2,575,629 | $2,992,886 | GREY SKY CONSTRUCTION LLC | +16.2% | 3 |
| Feb 7, 2025 | 6477-70-001RMC - A00213106 | Brown Brownwood |
THERMOPLASTIC STRIPING AND PAVEMENTUS0183 · Routine Maintenance Project - Sealed | $2,970,423 | $2,694,773 | D. I. J. CONSTRUCTION, INC. | -9.3% | 7 |
| Feb 7, 2025 | 0141-18-008BR 2025(379) | Kimble San Angelo |
0141-18-008 Bridge RehabRM 1674 · Bridge Maintenance | $2,310,598 | $1,716,914 | MPB, INC. | -25.7% | 9 |
| Feb 7, 2025 | 0915-00-271F 2025(465) | Bexar San Antonio |
VA: 0915-00-271; TCDVarious · Traffic Control Devices | $1,462,178 | $1,500,970 | ELECNOR BELCO ELECTRIC, INC. | +2.7% | 3 |
| Feb 7, 2025 | 0045-12-096C 45-12-96 | Red River Paris |
US 82 SidewalkBU 82J · Pedestrian, Sidewalks & Curb Ramps | $1,743,510 | $1,486,446 | AAD CONTRACTING INC. | -14.7% | 11 |
| Feb 7, 2025 | 0922-00-088C 922-00-88 | Webb Laredo |
Districtwide PVMTVarious · Traffic Control Devices | $1,995,220 | $1,443,019 | CENTERLINE TECHNOLOGIES, LLC | -27.7% | 9 |
| Feb 7, 2025 | 0905-00-124C 905-00-124 | Lubbock Lubbock |
FY 2025 RPMsVarious · Traffic Control Devices | $1,520,504 | $1,393,454 | TRP INFRASTRUCTURE SERVICES, LLC | -8.4% | 5 |
| Feb 7, 2025 | 0210-02-029STP 2025(361)HES | Milam Bryan |
US 77 at FM 1712 - Turn Lane FY 24US 77 · Safety Improvement Projects | $1,917,132 | $1,382,358 | LARRY YOUNG PAVING, INC. | -27.9% | 7 |
| Feb 7, 2025 | 0912-00-615F 2025(242) | Harris Houston |
Districtwide Lighting FM 2234 & FM 518Various · Traffic Control Devices | $1,501,240 | $1,290,192 | THIRD COAST SERVICES LLC | -14.1% | 10 |
| Feb 7, 2025 | 0151-09-149F 2025(430) | Travis Austin |
US 183 from IH 135 to US290US 183 · Overlay | $1,418,010 | $1,181,539 | LONE STAR PAVING COMPANY | -16.7% | 3 |
| Feb 7, 2025 | 0918-46-355C 918-46-355 | Denton Dallas |
Various Locations in Denton CountyVarious · Rehabilitation of Existing Road | $1,928,563 | $1,152,494 | STRIPE-A-ZONE, LLC | -40.2% | 4 |
| Feb 7, 2025 | 0906-00-247C 906-00-247 | Ector Odessa |
Traffic Signal Program (2025)Various · Traffic Control Devices | $1,075,350 | $1,136,733 | GREY SKY CONSTRUCTION LLC | +5.7% | 3 |
| Feb 7, 2025 | 6477-55-001RMC - A00213065 | Lamar Paris |
Site Specific TY I Striping FY25US0082 · Routine Maintenance Project - Sealed | $1,605,550 | $1,063,284 | STRIPE-A-ZONE, LLC | -33.8% | 8 |
| Feb 7, 2025 | 6476-41-001MMC - A00212806 | Wichita Wichita Falls |
2025 - EmulsionUS0287 · Material Maintenance Project | $1,304,200 | $1,044,600 | ERGON ASPHALT & EMULSIONS, INC. | -19.9% | 2 |
| Feb 7, 2025 | 6468-09-001RMC - A00210073 | Burnet Austin |
FY 25 Burnet Co. GuardrailUS0281 · Routine Maintenance Project - Sealed | $3,830,745 | $1,043,063 | BK FIELD OPERATIONS LLC | -72.8% | 4 |
| Feb 7, 2025 | 0271-07-352F 2025(301) | Harris Houston |
IH 10 at Brittmoore Rd.IH 10 · Freeway Operational Improvements | $1,407,604 | $926,322 | MC2 CIVIL, LLC | -34.2% | 3 |
| Feb 7, 2025 | 0151-05-123C 151-5-123 | Williamson Austin |
US 183 - Detention PondUS 183 · Environmental Work Activities | $1,098,651 | $922,697 | AARON CONCRETE CONTRACTORS, LLC | -16.0% | 4 |
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.