FY 2025 RPMs
- Let date
- Friday, February 7, 2025
- CCSJ
- 0905-00-124
- District
- Lubbock
- County
- Lubbock
- Highway
- Various
- Limits
- VARIOUS LOCATIONS IN to THE LUBBOCK DISTRICT
- Classification
- Traffic Control Devices · Construction
- Project number
- C 905-00-124
- Working days
- 68
- DBE goal
- 0%
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,520,504 | ||
| 1 | TRP INFRASTRUCTURE SERVICES, LLC Low bidder | $1,393,454 | -8.4% | |
| 2 | L&L COMPANY | $1,470,538 | -3.3% | +5.5% |
| 3 | FC TRAFFIC CONTROL, INC. | $1,517,360 | -0.2% | +8.9% |
| 4 | DOUBLE A CONTRACTING, L.P. | $1,605,185 | +5.6% | +15.2% |
| 5 | GREY SKY CONSTRUCTION LLC | $1,929,794 | +26.9% | +38.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 TRP INFRASTRUCT… | #2 L&L COMPANY | #3 FC TRAFFIC CONT… | #4 DOUBLE A CONTRA… | #5 GREY SKY CONSTR… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-7001 | MOBILIZATION | 1 | LS | $138,227.60 | $100,000.00 | $1.00 | $2.50 | $80,000.00 | $190,000.00 |
| 2 | 502-7001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 | MO | $1,000.00 | $1.00 | $1.00 | $1.00 | $6,500.00 | $8,500.00 |
| 3 | 505-7003 | TMA (MOBILE OPERATION) | 408 | DAY | $100.00 | $1.00 | $1.00 | $1.00 | $350.00 | $450.00 |
| 4 | 672-7001 | REFL PAV MRKR TY I-A | 6,772 | EA | $4.00 | $3.87 | $4.40 | $5.00 | $4.50 | $6.00 |
| 5 | 672-7002 | REFL PAV MRKR TY I-C | 20,046 | EA | $4.00 | $3.87 | $4.40 | $5.00 | $4.50 | $4.50 |
| 6 | 672-7004 | REFL PAV MRKR TY II-A-A | 166,623 | EA | $4.00 | $3.87 | $4.40 | $4.50 | $4.00 | $4.50 |
| 7 | 672-7006 | REFL PAV MRKR TY II-C-R | 140,678 | EA | $4.00 | $3.87 | $4.40 | $4.50 | $4.00 | $4.50 |