12BidsNov 26, 2024 to Mar 25, 2025
3Wins (low bidder)
25.0%Win rate
$826,854Total won
| Let date | CCSJ | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Mar 25, 2025 | 6479-23-001 | FY25 Lubbock Traffic ControlLubbock · Lubbock | 2 of 2 | $764,900 | $474,625BARRICADES UNLIMITED | +61.2% |
| Feb 27, 2025 | 6479-22-001 | FY25 Plainview Traffic ControlHale · Lubbock | 1 of 2 | $160,929 | $160,929 | Won |
| Feb 27, 2025 | 6479-21-001 | FY25 Littlefield Traffic ControlHockley · Lubbock | 1 of 2 | $217,450 | $217,450 | Won |
| Feb 27, 2025 | 6479-20-001 | FY25 Brownfield Traffic ControlTerry · Lubbock | 1 of 2 | $448,475 | $448,475 | Won |
| Feb 25, 2025 | 6477-50-001 | RAISED PAVEMENT MARKERS - BELL DWBell · Waco | 3 of 5 | $536,470 | $414,448TRP INFRASTRUCTURE SERVICES… | +29.4% |
| Feb 12, 2025 | 6462-79-001 | Raised Pavement Markers 01 0225Navarro · Dallas | 2 of 4 | $61,562 | $48,005TRP INFRASTRUCTURE SERVICES… | +28.2% |
| Feb 12, 2025 | 6469-71-001 | RPM Denton FY 25Denton · Dallas | 3 of 3 | $155,924 | $89,078TRP INFRASTRUCTURE SERVICES… | +75.0% |
| Feb 12, 2025 | 6471-19-001 | Raised Pavement Markers 09 0225Ellis · Dallas | 4 of 4 | $337,983 | $235,372TRP INFRASTRUCTURE SERVICES… | +43.6% |
| Feb 12, 2025 | 6472-59-001 | Raised Pavement Markers 07 1224Collin · Dallas | 3 of 3 | $530,738 | $287,731TRP INFRASTRUCTURE SERVICES… | +84.5% |
| Feb 7, 2025 | 0905-00-124 | FY 2025 RPMsLubbock · Lubbock | 3 of 5 | $1,517,360 | $1,393,454TRP INFRASTRUCTURE SERVICES… | +8.9% |
| Nov 26, 2024 | 6473-27-001 | 2025 Call Out TCP BSP AOHoward · Abilene | 2 of 2 | $472,151 | $410,935AWP SAFETY | +14.9% |
| Nov 26, 2024 | 6473-26-001 | 2025 Call Out TCP ABL AOTaylor · Abilene | 2 of 2 | $582,801 | $418,500AWP SAFETY | +39.3% |
Active prime contracts 7
| CCSJ | Where | Work | Contract | Complete | Report |
|---|---|---|---|---|---|
| 6465-85-001Let Sep 5, 2024 | HendersonTyler · US0175 | MAINTENANCE | $1,051,807 | 76% | |
| 6465-87-001Let Sep 5, 2024 | GreggTyler · US0080 | MAINTENANCE | $1,425,556 | 74% | |
| 6467-46-001Let Jun 5, 2024 | WalkerBryan · SH0030 | MAINTENANCE | $729,909 | 75% | |
| 6463-00-001Let May 3, 2024 | EctorOdessa · IH0020 | MAINTENANCE | $1,691,097 | 119% | |
| 6463-01-001Let May 3, 2024 | PecosOdessa · IH0010 | MAINTENANCE | $1,382,397 | 117% | |
| 6463-02-001Let May 3, 2024 | MidlandOdessa · IH0020 | MAINTENANCE | $1,886,859 | 101% | |
| 6457-85-001Let Mar 6, 2024 | HudspethEl Paso · IH0010 | MAINTENANCE | $934,750 | 102% |
Subcontracts on active jobs 87
| CCSJ | Prime contractor | Where | Work | Share | Value (est.) |
|---|---|---|---|---|---|
| 0261-01-041Let Mar 4, 2026 | HIGHWAY 19 CONSTRUCTION LLC | EllisDallas | INTERCHANGE (NEW OR RECONSTRUCTED) | 0.1% | $64,578 |
| 0581-02-156Let Mar 4, 2026 | HIGHWAY 19 CONSTRUCTION LLC | DallasDallas | BRIDGE REPLACEMENT | 0.21% | $36,012 |
| 0098-03-037Let Feb 5, 2026 | ZACK BURKETT CO. | FoardChildress | REHABILITATION OF EXISTING ROAD | 0.16% | $11,038 |
| 6478-92-001Let Jan 27, 2026 | TI-ZACK CONCRETE, LLC | LubbockLubbock | MAINTENANCE | 0% | $0 |
| 6492-66-001Let Jan 13, 2026 | BARRICADES UNLIMITED | WallerHouston | MAINTENANCE | 0% | $0 |
| 0572-01-074Let Jan 6, 2026 | REECE ALBERT, INC. | EctorOdessa | HAZARD ELIMINATION & SAFETY | 0.44% | $74,962 |
| 6489-58-001Let Dec 4, 2025 | BARRICADES UNLIMITED | El PasoEl Paso | MAINTENANCE | 0% | $0 |
| 0404-02-046Let Dec 3, 2025 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | StephensBrownwood | BRIDGE WIDENING OR REHABILITATION | 2.16% | $30,559 |
| 0906-00-256Let Dec 3, 2025 | SCOUT 5 CONSTRUCTION LLC | EctorOdessa | MISCELLANEOUS CONSTRUCTION | 0.11% | $6,923 |
| 0040-01-051Let Nov 6, 2025 | Missouri Petroleum Products Company | DallamAmarillo | SEAL COAT | 0.84% | $146,814 |
| 0042-12-096Let Nov 6, 2025 | RK HALL, LLC | ChildressChildress | OVERLAY | 0.46% | $23,897 |
| 3327-01-006Let Nov 5, 2025 | EARTH BUILDERS, L.P. | DonleyChildress | MAINTENANCE | 0.39% | $6,984 |
| 0380-04-025Let Oct 9, 2025 | A. L. HELMCAMP, INC. | TerryLubbock | REHABILITATION OF EXISTING ROAD | 0.13% | $29,681 |
| 0903-30-047Let Oct 8, 2025 | SKYLINE BRIDGE LLC | WilbargerWichita Falls | BRIDGE REPLACEMENT | 0.71% | $10,182 |
| 0034-01-130Let Oct 8, 2025 | JAMES CONSTRUCTION GROUP, LLC | TaylorAbilene | MISCELLANEOUS CONSTRUCTION | 0.15% | $111,036 |
| 0172-05-128Let Oct 8, 2025 | FOUTSCO PAVING COMPANY, LLC | EllisDallas | REHABILITATION OF EXISTING ROAD | 0% | $0 |
| 0294-01-041Let Oct 8, 2025 | JAMES HAMILTON CONSTRUCTION CO. | GainesLubbock | HAZARD ELIMINATION & SAFETY | 0.42% | $34,889 |
| 0073-10-053Let Sep 5, 2025 | LONE STAR PAVING COMPANY | AtascosaSan Antonio | RESTORATION | 0.05% | $8,834 |
| 0355-05-046Let Sep 5, 2025 | DUININCK, INC. | HansfordAmarillo | OVERLAY | 0.41% | $51,208 |
| 0461-06-028Let Sep 4, 2025 | PATHFIELD INVESTMENTS LLC | ParmerLubbock | BRIDGE WIDENING OR REHABILITATION | 0.22% | $9,458 |
| 0581-01-171Let Sep 4, 2025 | FOUTSCO PAVING COMPANY, LLC | DallasDallas | REHABILITATION OF EXISTING ROAD | 0.03% | $1,967 |
| 6465-74-001Let Aug 8, 2025 | STX CIVIL | WichitaWichita Falls | MAINTENANCE | 1.04% | $16,248 |
| 1480-02-035Let Aug 8, 2025 | TI-ZACK CONCRETE, LLC | RandallAmarillo | MISCELLANEOUS CONSTRUCTION | 0.25% | $29,595 |
| 0380-01-094Let Aug 8, 2025 | MASSANA CONSTRUCTION INC. | LubbockLubbock | HAZARD ELIMINATION & SAFETY | 0.57% | $18,626 |
| 0195-02-081Let Aug 7, 2025 | INDUS ROAD & BRIDGE, INC. | DentonDallas | WIDEN FREEWAY | 0.1% | $130,759 |
| 0461-09-023Let Aug 7, 2025 | JAMES HAMILTON CONSTRUCTION CO. | GainesLubbock | TRAFFIC PROTECTION DEVICES | 2.78% | $22,919 |
| 0905-00-142Let Jul 2, 2025 | STX CIVIL | LubbockLubbock | MISCELLANEOUS CONSTRUCTION | 0.58% | $20,338 |
| 0982-05-011Let Jul 2, 2025 | C & W SOUTHERN LLC | ThrockmortonWichita Falls | BRIDGE REPLACEMENT | 0.92% | $6,811 |
| 0704-06-016Let Jul 1, 2025 | STX CIVIL | MotleyChildress | BRIDGE REPLACEMENT | 0.82% | $15,392 |
| 0904-00-219Let Jun 5, 2025 | YUNEX LLC | PotterAmarillo | TRAFFIC SIGNAL | 0% | $0 |
| 0181-01-069Let May 2, 2025 | A. L. HELMCAMP, INC. | TaylorAbilene | WIDEN NON-FREEWAY | 0.26% | $30,122 |
| 0910-00-147Let May 2, 2025 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | SmithTyler | BRIDGE WIDENING OR REHABILITATION | 1.14% | $38,348 |
| 0052-01-043Let May 1, 2025 | A. L. HELMCAMP, INC. | ParmerLubbock | REHABILITATION OF EXISTING ROAD | 0.31% | $96,276 |
| 0910-00-146Let May 1, 2025 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | SmithTyler | REMOVE HAZARDOUS PAINT (BRG REHAB) | 1.15% | $98,371 |
| 0581-01-184Let Apr 4, 2025 | YUNEX LLC | DallasDallas | TRAFFIC SIGNAL | 0.89% | $23,310 |
| 0909-00-101Let Apr 4, 2025 | ICOS MANAGEMENT, LLC | MclennanWaco | BRIDGE WIDENING OR REHABILITATION | 1.45% | $47,256 |
| 0557-01-033Let Apr 4, 2025 | TI-ZACK CONCRETE, LLC | MooreAmarillo | MISCELLANEOUS CONSTRUCTION | 0.23% | $23,546 |
| 0918-47-403Let Apr 3, 2025 | YUNEX LLC | DallasDallas | TRAFFIC SIGNAL | 0.82% | $29,756 |
| 2588-01-022Let Mar 5, 2025 | GRANITE CONSTRUCTION COMPANY | KaufmanDallas | WIDEN NON-FREEWAY | 0.01% | $8,125 |
| 0397-02-041Let Mar 5, 2025 | RK HALL, LLC | WheelerChildress | MISCELLANEOUS CONSTRUCTION | 0.23% | $33,439 |
| 1337-01-026Let Mar 4, 2025 | EARTH BUILDERS, L.P. | LipscombAmarillo | BRIDGE REPLACEMENT | 0.07% | $13,233 |
| 0042-06-077Let Feb 7, 2025 | HODGES AND SON CONSTRUCTION COMPANY, INC. | DonleyChildress | BRIDGE REPLACEMENT | 0.48% | $21,414 |
| 0140-13-020Let Feb 6, 2025 | KIEWIT INFRASTRUCTURE SOUTH CO. | CrockettSan Angelo | OVERLAY | 0.25% | $59,336 |
| 0461-04-026Let Jan 8, 2025 | JAMES HAMILTON CONSTRUCTION CO. | CochranLubbock | RESTORATION | 0.18% | $62,943 |
| 0022-01-032Let Jan 7, 2025 | STX CIVIL | TerrellOdessa | BRIDGE REPLACEMENT | 0.34% | $16,664 |
| 0283-03-024Let Jan 7, 2025 | SKYLINE BRIDGE LLC | ArcherWichita Falls | BRIDGE REPLACEMENT | 0.23% | $7,710 |
| 0003-06-103Let Nov 7, 2024 | FNF CONSTRUCTION, INC. | ReevesOdessa | REHABILITATION OF EXISTING ROAD | 0.03% | $10,904 |
| 0035-03-047Let Nov 7, 2024 | 3LW CIVIL LLC | ConchoSan Angelo | TRAFFIC SIGNAL | 0.22% | $32,986 |
| 0066-05-081Let Nov 7, 2024 | MISSOURI PETROLEUM PRODUCTS COMPANY LLC | MooreAmarillo | MAINTENANCE | 0.62% | $116,775 |
| 0204-09-045Let Nov 7, 2024 | LARRY YOUNG PAVING, INC. | RobertsonBryan | BRIDGE REPLACEMENT | 0.24% | $45,878 |
| 0003-06-101Let Nov 6, 2024 | FNF CONSTRUCTION, INC. | ReevesOdessa | REHABILITATION OF EXISTING ROAD | 0.03% | $9,733 |
| 0090-05-109Let Oct 2, 2024 | GILVIN-TERRILL, LTD. | PotterAmarillo | HAZARD ELIMINATION & SAFETY | 0.1% | $31,190 |
| 0054-04-113Let Oct 1, 2024 | ICOS MANAGEMENT, LLC | ColemanBrownwood | BRIDGE WIDENING OR REHABILITATION | 1.05% | $29,585 |
| 0047-18-088Let Oct 1, 2024 | INDUS ROAD & BRIDGE, INC. | GraysonParis | WIDEN FREEWAY | 0.08% | $118,623 |
| 0923-08-030Let Oct 1, 2024 | SKYLINE BRIDGE LLC | ColemanBrownwood | BRIDGE REPLACEMENT | 0.8% | $14,308 |
| 0196-03-289Let Sep 6, 2024 | GIBSON & ASSOCIATES, INC. | DallasDallas | REHABILITATION OF EXISTING ROAD | 0.21% | $49,921 |
| 0197-04-086Let Aug 2, 2024 | GRANITE CONSTRUCTION COMPANY | KaufmanDallas | MISCELLANEOUS CONSTRUCTION | 0.37% | $20,879 |
| 0340-01-043Let Aug 2, 2024 | MP HEAVY CONSTRUCTION INC | HoustonLufkin | BRIDGE REPLACEMENT | 0.2% | $18,064 |
| 0907-00-237Let Aug 1, 2024 | AMERICAN LIGHTING AND SIGNALIZATION, LLC | Tom GreenSan Angelo | TRAFFIC PROTECTION DEVICES | 0.24% | $7,013 |
| 0816-04-104Let Jul 10, 2024 | HARPER BROTHERS CONSTRUCTION LLC | CollinDallas | BRIDGE REPLACEMENT | 0.32% | $31,343 |
| 0902-00-290Let Jul 10, 2024 | YUNEX LLC | TarrantFort Worth | MISCELLANEOUS CONSTRUCTION | 0.11% | $2,358 |
| 3592-01-009Let Jul 9, 2024 | SUNDT CONSTRUCTION, INC. | El PasoEl Paso | INTERCHANGE (NEW OR RECONSTRUCTED) | 1.08% | $2,646,775 |
| 0033-05-089Let Jul 9, 2024 | FNF CONSTRUCTION, INC. | JonesAbilene | REHABILITATION OF EXISTING ROAD | 0.59% | $235,658 |
| 0548-04-025Let Jun 6, 2024 | WESTFIELD INSURANCE COMPANY | HowardAbilene | BRIDGE REPLACEMENT | 0.14% | $3,552 |
| 0137-03-085Let Jun 5, 2024 | A. L. HELMCAMP, INC. | WichitaWichita Falls | WIDEN NON-FREEWAY | 0.18% | $37,065 |
| 0906-00-236Let May 3, 2024 | WILLIS ELECTRIC CO., LP | EctorOdessa | TRAFFIC SIGNAL | 2.49% | $70,593 |
| 2121-01-104Let May 3, 2024 | SUNDT CONSTRUCTION, INC. | El PasoEl Paso | WIDEN FREEWAY | 1.74% | $2,116,282 |
| 1314-01-014Let May 2, 2024 | JAMES HAMILTON CONSTRUCTION CO. | CulbersonEl Paso | REHABILITATION OF EXISTING ROAD | 0.19% | $57,130 |
| 0005-14-094Let Mar 6, 2024 | SUNDT CONSTRUCTION, INC. | MidlandOdessa | WIDEN FREEWAY | 0.94% | $1,554,293 |
| 0905-06-095Let Feb 2, 2024 | LONE STAR DIRT & PAVING, LTD. | LubbockLubbock | WIDEN NON-FREEWAY | 0.21% | $39,828 |
| 0168-09-083Let Feb 1, 2024 | WEBBER, LLC | RandallAmarillo | WIDEN FREEWAY | 0.07% | $220,337 |
| 0047-14-053Let Jan 4, 2024 | MARIO SINACOLA & SONS EXCAVATING, INC. | CollinDallas | WIDEN FREEWAY | 0.35% | $283,863 |
| 0005-13-064Let Nov 2, 2023 | SUNDT CONSTRUCTION, INC. | EctorOdessa | WIDEN FREEWAY | 0.6% | $1,450,735 |
| 0168-02-032Let Oct 5, 2023 | WEBBER, LLC | ParmerLubbock | BRIDGE WIDENING OR REHABILITATION | 0.08% | $58,543 |
| 0047-06-158Let Aug 3, 2023 | WEBBER, LLC | CollinDallas | HAZARD ELIMINATION & SAFETY | 0.1% | $61,140 |
| 0902-00-289Let Jun 28, 2023 | YUNEX LLC | TarrantFort Worth | MISCELLANEOUS CONSTRUCTION | 0.16% | $3,245 |
| 0197-03-078Let Jun 27, 2023 | GRANITE CONSTRUCTION COMPANY | KaufmanDallas | NEW LOCATION FREEWAY | 0.01% | $5,790 |
| 0004-02-063Let Jun 27, 2023 | JAMES CONSTRUCTION GROUP, LLC | WardOdessa | BRIDGE REPLACEMENT | 0.13% | $38,038 |
| 0905-06-116Let Jun 27, 2023 | WEBBER, LLC | LubbockLubbock | WIDEN NON-FREEWAY | 0.19% | $72,140 |
| 0353-02-037Let Apr 4, 2023 | MARIO SINACOLA & SONS EXCAVATING, INC. | DentonDallas | WIDEN NON-FREEWAY | 0.01% | $10,166 |
| 0005-01-113Let Mar 7, 2023 | RAGLE CONSTRUCTION, INC. | EctorOdessa | REHABILITATION OF EXISTING ROAD | 0.14% | $35,463 |
| 1639-01-016Let Mar 7, 2023 | A. L. HELMCAMP, INC. | ReevesOdessa | REHABILITATION OF EXISTING ROAD | 0.17% | $138,904 |
| 0043-17-031Let Feb 2, 2023 | ZACK BURKETT CO. | WichitaWichita Falls | WIDEN NON-FREEWAY | 0.32% | $30,548 |
| 0003-05-055Let Feb 1, 2023 | FNF CONSTRUCTION, INC. | ReevesOdessa | REHABILITATION OF EXISTING ROAD | 0.57% | $386,043 |
| 0047-04-031Let Dec 2, 2022 | HARPER BROTHERS CONSTRUCTION LLC | CollinDallas | WIDEN NON-FREEWAY | 0.39% | $157,334 |
| 0045-18-046Let Nov 2, 2022 | ATLANTIC SPECIALTY INSURANCE COMPANY | GraysonParis | HAZARD ELIMINATION & SAFETY | 0% | $0 |
| 0902-90-108Let Jul 2, 2021 | AMERICAN LIGHTING AND SIGNALIZATION, LLC | TarrantFort Worth | MISCELLANEOUS CONSTRUCTION | 0.22% | $9,495 |