Asph/Oils/Emuls-WAO (Materials Only)
- Let date
- Tuesday, February 18, 2025
- CCSJ
- 6476-93-001
- District
- Yoakum
- County
- Wharton
- Highway
- US0059
- Limits
- Wharton, Matagorda, Austin, and Colorado to .
- Classification
- Material Maintenance Project · Maintenance
- Project number
- MMC - A00212906
- Working days
- 365
- DBE goal
- 0%
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $656,875 | ||
| 1 | WRIGHT ASPHALT PRODUCTS COMPANY LLC Low bidder | $567,231 | -13.6% | |
| 2 | ERGON ASPHALT & EMULSIONS, INC. | $626,556 | -4.6% | +10.5% |
| 3 | MARTIN RESOURCE MANAGEMENT CORPORATION | $630,872 | -4.0% | +11.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 WRIGHT ASPHALT … | #2 ERGON ASPHALT &… | #3 MARTIN RESOURCE… |
|---|---|---|---|---|---|---|---|---|
| 1 | 8003-7077 | CRS-2 (DEL)(SITE 1) | 50 | TON | $630.00 | $505.25 | $650.28 | $612.44 |
| 2 | 8003-7078 | CRS-2 (DEL)(SITE 2) | 50 | TON | $630.00 | $505.25 | $650.28 | $613.67 |
| 3 | 8003-7079 | CRS-2 (DEL)(SITE 3) | 50 | TON | $630.00 | $505.25 | $650.28 | $609.98 |
| 4 | 8003-7080 | CRS-2 (DEL)(SITE 4) | 50 | TON | $630.00 | $505.25 | $650.28 | $613.67 |
| 5 | 8003-7133 | CRS-2P (DEL)(SITE 1) | 25 | TON | $725.00 | $587.50 | $720.78 | $683.70 |
| 6 | 8003-7134 | CRS-2P (DEL)(SITE 2) | 25 | TON | $725.00 | $587.50 | $720.78 | $684.93 |
| 7 | 8003-7135 | CRS-2P (DEL)(SITE 3) | 25 | TON | $725.00 | $587.50 | $720.78 | $681.24 |
| 8 | 8003-7136 | CRS-2P (DEL)(SITE 4) | 25 | TON | $725.00 | $587.50 | $720.78 | $684.93 |
| 9 | 8003-7246 | RC-250 (DEL) (SITE 1) | 100 | TON | $965.00 | $857.75 | $893.52 | $926.15 |
| 10 | 8003-7247 | RC-250 (DEL) (SITE 2) | 175 | TON | $965.00 | $857.75 | $893.52 | $927.38 |
| 11 | 8003-7248 | RC-250 (DEL) (SITE 3) | 100 | TON | $965.00 | $857.75 | $893.52 | $923.69 |
| 12 | 8003-7249 | RC-250 (DEL) (SITE 4) | 100 | TON | $965.00 | $857.75 | $893.52 | $927.38 |