FY25 - Freestone Mowing - 02
- Let date
- Wednesday, February 12, 2025
- CCSJ
- 6479-12-001
- District
- Bryan
- County
- Freestone
- Highway
- SH0075
- Limits
- Various to Various
- Classification
- Routine Maintenance Project · Maintenance
- Project number
- RMC - A00213818
- Working days
- 365
- DBE goal
- 0%
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $325,300 | ||
| 1 | ABESCAPE GROUP LLC Low bidder | $276,271 | -15.1% | |
| 2 | SERNA CONTRACTORS, LLC | $281,410 | -13.5% | +1.9% |
| 3 | GREG SCRUGGS | $322,118 | -1.0% | +16.6% |
| 4 | CROSS PLUS CONSTRUCTION, LLC | $401,725 | +23.5% | +45.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 ABESCAPE GROUP … | #2 SERNA CONTRACTO… | #3 GREG SCRUGGS | #4 CROSS PLUS CONS… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-7002 | MOBILIZATION (CALLOUT) | 4 | EA | $400.00 | $1.00 | $1,250.00 | $0.0010 | $1.00 |
| 2 | 505-7002 | TMA (MOBILE OPERATION) | 24 | HR | $150.00 | $500.00 | $1.00 | $75.00 | $300.00 |
| 3 | 730-7022 | FULL - WIDTH MOWING | 7,941 | AC | $40.00 | $33.00 | $34.65 | $39.95 | $49.00 |
| 4 | 734-7004 | LITTER REMOVAL - TRACT (1) | 123 | AC | $20.00 | $18.00 | $10.00 | $25.00 | $44.00 |