111Let jobs
$872,000,869Total low bids
$888,763,177Total estimates
-1.9%Low bids vs estimates
May 2020 results
Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| May 12, 2020 | 6355-62-001MMC - 635562001 | Cherokee Tyler |
LIQUID ASPHALT-MATERIALS ONLYUS 69 · | $113,750 | $65,950 | MARTIN RESOURCE MANAGEMENT CORPORATION | -42.0% | 2 |
| May 12, 2020 | 6355-65-001MMC - 635565001 | Anderson Tyler |
LIQUID ASPHALT-MATERIALS ONLYUS 79 · | $113,750 | $65,950 | MARTIN RESOURCE MANAGEMENT CORPORATION | -42.0% | 2 |
| May 8, 2020 | 0610-07-113NH 2020(455) | Bowie Atlanta |
GR,STR,BASE,SURF & PAV MRKIH 30 · | $74,732,487 | $88,870,749 | LONGVIEW BRIDGE AND ROAD, LTD. | +18.9% | 6 |
| May 8, 2020 | 1183-01-014STP 2020(751) | Reeves Odessa |
ROADWAY REHABILITATIONFM 2119 · | $63,857,120 | $62,350,992 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | -2.4% | 7 |
| May 8, 2020 | 0102-04-099NH 2020(871) | Kleberg Corpus Christi |
CONSTRUCT MAINLANES, FRONTAGE ROADS AND STRUCTURESUS 77 · | $48,109,867 | $55,237,175 | BAY LTD. | +14.8% | 4 |
| May 8, 2020 | 6351-58-001RMC - 635158001 | McLennan Waco |
ROUTINE MAINTENANCE OF IH - 35 CORRIDORIH 35 · | $28,080,845 | $26,575,153 | CROSS PLUS CONSTRUCTION, LLC | -5.4% | 3 |
| May 8, 2020 | 0068-09-012STP 2020(861) | Lynn Lubbock |
SAFETY WIDENINGSL 76 · | $20,572,612 | $23,982,637 | ALLEN BUTLER CONSTRUCTION, INC. | +16.6% | 3 |
| May 8, 2020 | 0912-72-391STP 1802(783)MM | Harris Houston |
WIDENING TO A 4-LANE DIVIDED ROADWAYCS · | $21,371,336 | $20,384,047 | SER CONSTRUCTION PARTNERS, LLC | -4.6% | 7 |
| May 8, 2020 | 0275-01-205BR 2020(793) | Potter Amarillo |
BRIDGE MAINTENANCE AND REPAIRIH 40 · | $14,312,032 | $15,820,659 | GIBSON & ASSOCIATES, INC. | +10.5% | 4 |
| May 8, 2020 | 1545-02-023STP 2020(917) | La Salle Laredo |
GRADE, ACP, STR, MBGF, PAV MRKS, SIGNSFM 468 · | $16,533,179 | $15,239,643 | ANDERSON COLUMBIA CO., INC. | -7.8% | 5 |
| May 8, 2020 | 0157-05-064C 157-5-64 | Jones Abilene |
SPOT REPAIR, OVERLAYUS 277 · | $21,588,660 | $15,184,947 | ZACK BURKETT CO. | -29.7% | 9 |
| May 8, 2020 | 0257-05-045C 257-5-45 | Comanche Brownwood |
REBUILD 2 LANES TO 4, STORM SEWER, SIGNAL, & ILLUMSH 6 · | $9,054,864 | $10,287,230 | BIG CREEK CONSTRUCTION, LTD. | +13.6% | 3 |
| May 8, 2020 | 7774-01-001STP 2020(789)MM | Bexar San Antonio |
EXPAND 4 TO 6 LNS DIVIDED & INTERSECT OPERATIONSPA 1502 · | $7,468,133 | $7,947,752 | AUSTIN BRIDGE & ROAD SERVICES, LP | +6.4% | 6 |
| May 8, 2020 | 1433-01-029STP 2020(824)MM | Bexar San Antonio |
INTERSECT OPER IMPROV & INCL WIDEN CIBOLO CRK BRDGFM 2252 · | $6,643,535 | $6,580,023 | HARPER BROTHERS CONSTRUCTION LLC | -1.0% | 10 |
| May 8, 2020 | 0697-03-029STP 2020(804)HES | Kaufman Dallas |
RUMBLE STRIPS & PAV SURF WIDTHFM 429 · | $6,562,103 | $6,206,913 | KNIFE RIVER CORPORATION - SOUTH | -5.4% | 9 |
| May 8, 2020 | 0013-10-084C 13-10-84 | Tarrant Fort Worth |
RESURFACE ROADWAYBU 287P · | $5,406,173 | $4,404,395 | FOUTSCO PAVING COMPANY, LLC | -18.5% | 8 |
| May 8, 2020 | 0722-03-014STP 2020(836)HES | Red River Paris |
PROVIDE ADDITIONAL PAVED SURFACE WIDTHFM 911 · | $4,639,084 | $3,889,515 | H. H. HOWARD & SONS, INC. | -16.2% | 7 |
| May 8, 2020 | 0108-09-050STP 2020(830)HES | Hopkins Paris |
SAFETY TREAT FIXED OBJECTSSH 19 · | $2,866,877 | $2,754,447 | HIGHWAY 19 CONSTRUCTION LLC | -3.9% | 5 |
| May 8, 2020 | 0038-03-041STP 2020(851)HES | Zapata Pharr |
SAFETY IMPROVEMENT PROJECTSUS 83 · | $3,471,537 | $2,749,449 | TRAF-TEX, INC. | -20.8% | 5 |
| May 8, 2020 | 0025-06-056BR 2020(848) | Gonzales Yoakum |
MISC BRIDGE REPAIRUA 90 · | $3,443,456 | $2,603,774 | OLYMPUS PAINTING CONTRACTORS, INC. | -24.4% | 8 |
| May 8, 2020 | 1835-02-059NH 2020(839) | Bell Waco |
CONSTRUCT SIDEWALK AND PEDESTRIAN BRIDGEFM 1741 · | $2,664,586 | $2,447,065 | TTG UTILITIES, LP | -8.2% | 8 |
| May 8, 2020 | 6359-28-001RMC - 635928001 | El Paso El Paso |
REHABILITATION OF ROADWAYSL 375 · | $2,828,049 | $2,225,975 | J. A. R. CONCRETE, INC. | -21.3% | 7 |
| May 8, 2020 | 0912-31-310STP 2020(803)TP | Brazoria Houston |
BICYCLE INFRASTRUCTURE IMPROVEMENTSVA · | $2,320,568 | $2,194,263 | ANGEL BROTHERS HOLDINGS CORP. | -5.4% | 5 |
| May 8, 2020 | 0047-06-168C 47-6-168 | Collin Dallas |
FULL DEPTH CONCRETE REPAIRSUS 75 · | $2,595,290 | $2,150,064 | O. TREVINO CONSTRUCTION, LLC | -17.2% | 4 |
| May 8, 2020 | 0976-03-104STP 2020(664)TP | Galveston Houston |
CONSTRUCTION OF A 10' WIDE SHARED USED PATHFM 518 · | $2,236,122 | $2,146,674 | ARANDA BROTHERS CONSTRUCTION CO., INC. | -4.0% | 11 |
| May 8, 2020 | 6360-02-001RMC - 636002001 | Dallas Dallas |
SWEEPING & DEBRIS REMOVALUS 175 · | $2,811,389 | $2,040,652 | SWEEPING SERVICES OF TEXAS - OPERATING, L.P. | -27.4% | 2 |
| May 8, 2020 | 0002-05-050C 2-5-50 | Hudspeth El Paso |
REPLACE SUBSTANDARD METAL BEAM GUARD FENCEIH 10 · | $2,203,954 | $1,883,865 | SYNERGY PROJECT CONTRACTORS, INC. | -14.5% | 7 |
| May 8, 2020 | 6360-03-001RMC - 636003001 | Dallas Dallas |
SWEEPING & DEBRIS REMOVALSH 78 · | $2,389,440 | $1,840,568 | STRIPE-A-ZONE, INC. | -23.0% | 2 |
| May 8, 2020 | 6353-21-001RMC - 635321001 | Travis Austin |
DISTRICTWIDE CONCRETE REPAIRIH 35 · | $1,406,870 | $1,650,555 | ROY JORGENSEN ASSOCIATES, INC. | +17.3% | 3 |
| May 8, 2020 | 0789-04-006BR 2020(862) | Swisher Lubbock |
BRIDGE REPLACEMENTFM 2301 · | $1,624,216 | $1,543,188 | BLACKSTONE CONCRETE VENTURES, LLC | -5.0% | 4 |
| May 8, 2020 | 6360-01-001RMC - 636001001 | Dallas Dallas |
SWEEPING & DEBRIS REMOVALSL 12 · | $2,096,091 | $1,452,681 | SWEEPING SERVICES OF TEXAS - OPERATING, L.P. | -30.7% | 3 |
| May 8, 2020 | 6351-83-001RMC - 635183001 | Harris Houston |
TRAFFIC CONTROLIH 10 · | $1,591,060 | $1,426,510 | BATTERSON, LLP | -10.3% | 5 |
| May 8, 2020 | 6358-80-001RMC - 635880001 | Dallas Dallas |
FLEXIBLE PAVEMENT STRUCTURE REPAIRIH 20 · | $1,519,882 | $1,317,013 | TEXAS MATERIALS GROUP, INC. | -13.3% | 4 |
| May 8, 2020 | 6357-61-001RMC - 635761001 | Bexar San Antonio |
MILL AND INALYPA 1502 · | $1,378,180 | $1,301,146 | CLARK CONSTRUCTION OF TEXAS, INC. | -5.6% | 5 |
| May 8, 2020 | 6361-47-001MMC - 636147001 | Grayson Paris |
AGGREGATE - MATERIALS ONLYUS 75 · | $1,034,750 | $1,138,554 | RK HALL, LLC | +10.0% | 1 |
| May 8, 2020 | 6357-99-001RMC - 635799001 | Collin Dallas |
REFLECTORIZED PAVEMENT MARKINGS & MARKERUS 75 · | $1,109,443 | $1,103,015 | TOTAL HIGHWAY MAINTENANCE, LLC | -0.6% | 3 |
| May 8, 2020 | 6359-38-001RMC - 635938001 | Gregg Tyler |
TRAFFIC CONTROLSH 31 · | $1,038,625 | $1,028,550 | AREA WIDE PROTECTIVE, INC. | -1.0% | 3 |
| May 8, 2020 | 6339-19-001RMC - 633919001 | Taylor Abilene |
CALL OUT ILLUMINATION AND TRAFFIC SIGNAL REPAIRIH 20 · | $1,163,374 | $992,225 | WILLIS ELECTRIC CO., LP | -14.7% | 2 |
| May 8, 2020 | 6355-36-001MMC - 635536001 | Hood Fort Worth |
DENSE-GRADED HOTMIX ASPHALT MATL ONLYUS 377 · | $713,260 | $911,249 | NORTHEASTERN PAVERS, LLC | +27.8% | 3 |
| May 8, 2020 | 6359-35-001RMC - 635935001 | Henderson Tyler |
TRAFFIC CONTROLSH 31 · | $915,535 | $880,358 | AREA WIDE PROTECTIVE, INC. | -3.8% | 4 |
| May 8, 2020 | 6355-79-001RMC - 635579001 | McLennan Waco |
BASE FAILURE PAVEMENT REPAIRSSH 6 · | $1,416,652 | $827,444 | TEXAS MATERIALS GROUP, INC. | -41.6% | 4 |
| May 8, 2020 | 0700-01-046CC 700-1-46 | Burnet Austin |
INTERSECTION IMPROVEMENTSSH 71 · | $849,710 | $759,382 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. | -10.6% | 7 |
| May 8, 2020 | 0907-00-222STP 2020(886) | Tom Green San Angelo |
PROFILE PAVEMENT MARKINGSVA · | $967,447 | $725,159 | L&L COMPANY | -25.0% | 10 |
| May 8, 2020 | 6352-14-001RMC - 635214001 | Brazos Bryan |
SPOT PAVEMENT MARKINGSSH 6 · | $852,900 | $707,400 | INTERSTATE BARRICADES & MARKINGS, INC. | -17.1% | 5 |
| May 8, 2020 | 6358-82-001RMC - 635882001 | Dallas Dallas |
FLEXIBLE PAVEMENT STRUCTURE REPAIRFM 1382 · | $695,905 | $598,357 | FOUTSCO PAVING COMPANY, LLC | -14.0% | 4 |
| May 8, 2020 | 0114-09-078STP 2020(798)HES | Washington Bryan |
INSTALL INTERSECTION FLASHING BEACONUS 290 · | $866,342 | $584,899 | ALLSTATE SIGNAL & CONSTRUCTION, LLC | -32.5% | 5 |
| May 8, 2020 | 6358-23-001RMC - 635823001 | Dallas Dallas |
FLEXIBLE PAVEMENT STRUCTURE REPAIRSL 12 · | $604,936 | $558,310 | TEXAS MATERIALS GROUP, INC. | -7.7% | 4 |
| May 8, 2020 | 6355-35-001MMC - 635535001 | Johnson Fort Worth |
DENSE-GRADED HOTMIX ASPHALT MATL ONLYIH 35W · | $430,880 | $540,763 | TEXAS MATERIALS GROUP, INC. | +25.5% | 3 |
| May 8, 2020 | 6358-30-001RMC - 635830001 | Galveston Houston |
FULL DEPTH CONCRETE REPAIRFM 518 · | $612,046 | $536,850 | ISI CONTRACTING, INC. | -12.3% | 2 |
| May 8, 2020 | 6339-57-001BPM - 633957001 | El Paso El Paso |
BPMUS 54 · | $526,870 | $485,855 | MARTINEZ BROS. CONTRACTORS, LLC | -7.8% | 9 |
| May 8, 2020 | 6355-77-001RMC - 635577001 | Limestone Waco |
BASE FAILURE PAVEMENT REPAIRSH 164 · | $598,290 | $434,031 | BIG CREEK CONSTRUCTION, LTD. | -27.5% | 5 |
| May 8, 2020 | 6361-75-001RMC - 636175001 | Potter Amarillo |
CLEANING & SWEEPING HIGHWAYSIH 40 · | $377,645 | $343,519 | PANHANDLE SWEEPING & MAINTENANCE, LLC | -9.0% | 1 |
| May 8, 2020 | 6353-57-001RMC - 635357001 | Jefferson Beaumont |
CABLE BARRIER REPAIRIH 10 · | $345,950 | $333,490 | ELITE CASTLE RESOURCES LLC | -3.6% | 2 |
| May 8, 2020 | 0116-04-104STP 2020(787)HES | Brazos Bryan |
INSTALL TRAFFIC SIGNALSH 21 · | $338,125 | $263,629 | BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. | -22.0% | 6 |
| May 8, 2020 | 6361-91-001RMC - 636191001 | Maverick Laredo |
CLEANING & SWEEPING OF HWY & LITTER REMOVALUS 277 · | $328,190 | $229,979 | PAVEMENT PARTNERS, LLC | -29.9% | 3 |
| May 8, 2020 | 1024-01-078STP 1802(599)HES | Chambers Beaumont |
SFT- SAFETY IMPROVEMENT PROJECTSFM 565 · | $140,987 | $206,939 | TEXAS MATERIALS GROUP, INC. | +46.8% | 3 |
| May 7, 2020 | 0581-02-124NH 1902(201) | Dallas Dallas |
INTERCHANGE IMPROVEMENTSSL 12 · | $365,498,137 | $355,097,341 | WEBBER, LLC | -2.8% | 6 |
| May 7, 2020 | 0011-05-051STP 2020(692) | Shackelford Abilene |
MILL AND FILL AND EXCAVATIONUS 180 · | $12,774,849 | $10,086,760 | A. L. HELMCAMP, INC. | -21.0% | 4 |
| May 7, 2020 | 0343-04-044STP 2020(720) | Erath Fort Worth |
RESURFACE ROADWAYSH 108 · | $5,355,996 | $6,936,074 | JAY MILLS CONTRACTING, INCORPORATED | +29.5% | 1 |
| May 7, 2020 | 0508-01-357STP 2020(059)TP | Harris Houston |
BICYCLE AND PEDESTRIAN IMPROVEMENTSIH 10 · | $7,146,353 | $5,499,460 | SER CONSTRUCTION PARTNERS, LLC | -23.0% | 13 |
| May 7, 2020 | 6357-02-001RMC - 635702001 | Harris Houston |
GENERAL MAINTEANCE OF IH 45IH 45 · | $4,578,304 | $5,431,786 | ROY JORGENSEN ASSOCIATES, INC. | +18.6% | 3 |
| May 7, 2020 | 0809-03-040C 809-3-40 | San Augustine Lufkin |
CONSTRUCT NEW ROADWAY LANESUS 96 · | $5,763,105 | $4,885,972 | MADDEN CONTRACTING COMPANY, LLC. | -15.2% | 5 |
| May 7, 2020 | 0150-04-049C 150-4-49 | Llano Austin |
CONSTRUCT SUPER 2 PASSING LANESSH 29 · | $5,031,370 | $4,653,515 | ACME BRIDGE COMPANY, INC. | -7.5% | 10 |
| May 7, 2020 | 6340-26-001RMC - 634026001 | Travis Austin |
TOLL-LARGE SIGN MAINTENANCESH 130 · | $4,709,444 | $4,629,814 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. | -1.7% | 4 |
| May 7, 2020 | 0048-01-063NH 2020(819) | Dallas Dallas |
CONCRETE FULL DEPTH REPAIR, OV & PVMT MRKGSSH 342 · | $4,353,934 | $4,268,178 | GIBSON & ASSOCIATES, INC. | -2.0% | 3 |
| May 7, 2020 | 1534-02-008STP 2020(977)HES | Gillespie Austin |
SAFETY IMPROVEMENT PROJECTSRM 1623 · | $4,412,413 | $4,041,365 | RAY FARIS, INC. | -8.4% | 8 |
| May 7, 2020 | 0904-00-195C 904-00-195 | Potter Amarillo |
INSTALL CABLE MEDIAN BARRIERVA · | $4,654,169 | $3,940,371 | HJC FARMS, INC. | -15.3% | 5 |
| May 7, 2020 | 6343-73-001RMC - 634373001 | Denton Dallas |
GUARDRAIL/CABLE BARRIER REPAIRIH 35W · | $4,667,025 | $3,826,340 | K-BAR SERVICES, INC. | -18.0% | 2 |
| May 7, 2020 | 0008-15-052C 8-15-52 | Tarrant Fort Worth |
RESURFACE ROADWAYIH 820 · | $4,833,226 | $3,195,838 | O. TREVINO CONSTRUCTION, LLC | -33.9% | 6 |
| May 7, 2020 | 0915-00-230C 915-00-230 | Bexar San Antonio |
INTERSECTION OPERATIONAL IMPROVEMENTSVA · | $3,159,866 | $3,053,201 | ACME BRIDGE COMPANY, INC. | -3.4% | 6 |
| May 7, 2020 | 0924-06-601C 924-6-601 | El Paso El Paso |
FY 2020 BRIDGE MAINTENANCE (EL PASO COUNTY)VA · | $2,896,650 | $2,570,503 | J.D. ABRAMS, L.P. | -11.3% | 10 |
| May 7, 2020 | 0326-05-003C 326-5-3 | Nueces Corpus Christi |
OVERLAY WITH SPOT BASE REPAIR AND SIGNSBS 286A · | $2,945,952 | $2,555,406 | HAAS-ANDERSON CONSTRUCTION, LTD. | -13.3% | 3 |
| May 7, 2020 | 0055-05-051C 55-5-51 | Coryell Waco |
INSTALL MILLED CENTERLINE; INSTALL PROFILE EDGELINUS 84 · | $2,423,516 | $1,945,672 | D. I. J. CONSTRUCTION, INC. | -19.7% | 6 |
| May 7, 2020 | 6351-61-001RMC - 635161001 | Milam Bryan |
US 79 OVERLAYUS 79 · | $2,608,347 | $1,914,086 | KNIFE RIVER CORPORATION - SOUTH | -26.6% | 5 |
| May 7, 2020 | 0089-07-155STP 2020(849)HES | Wharton Yoakum |
IMPROVE GUARDRAIL TO DESIGN STANDARD,ETC.US 59 · | $2,165,237 | $1,842,177 | 3LW CIVIL LLC | -14.9% | 7 |
| May 7, 2020 | 0908-24-050BR 1902(092) | Jones Abilene |
BRIDGE REPLACMENTCR · | $1,645,976 | $1,790,933 | J. H. STRAIN & SONS, INC. | +8.8% | 5 |
| May 7, 2020 | 6363-34-001RMC - 636334001 | Jim Wells Corpus Christi |
STRIPING & PAVEMENT MARKINGSUS 281 · | $2,000,036 | $1,720,526 | HIGHWAY BARRICADES AND SERVICES, LLC | -14.0% | 7 |
| May 7, 2020 | 6360-04-001RMC - 636004001 | Dallas Dallas |
SWEEPING & DEBRIS REMOVALUS 67 · | $2,086,527 | $1,711,134 | STRIPE-A-ZONE, INC. | -18.0% | 3 |
| May 7, 2020 | 6355-96-001RMC - 635596001 | Harris Houston |
CLEANING AND SWEEPING HIGHWAYSSL 8 · | $2,194,850 | $1,642,860 | SWEEPING SERVICES OF TEXAS - OPERATING, L.P. | -25.1% | 3 |
| May 7, 2020 | 6359-36-001RMC - 635936001 | Wood Tyler |
TRAFFIC CONTROLUS 80 · | $1,198,250 | $1,480,960 | ALTUS TRAFFIC MANAGEMENT LLC | +23.6% | 3 |
| May 7, 2020 | 6351-65-001MMC - 635165001 | Tarrant Fort Worth |
DENSE-GRADED HOTMIX ASPHALT (MATERIALS ONLY)IH 35W · | $1,087,500 | $1,387,598 | AUSTIN ASPHALT, INC. | +27.6% | 2 |
| May 7, 2020 | 6358-76-001RMC - 635876001 | Ellis Dallas |
FLEXIBLE PAVEMENT STRUCTURE REPAIRUS 287 · | $1,775,940 | $1,369,229 | KNIFE RIVER CORPORATION - SOUTH | -22.9% | 5 |
| May 7, 2020 | 6363-39-001RMC - 636339001 | Taylor Abilene |
CALL OUT MBGF REPAIRIH 20 · | $1,602,224 | $1,365,822 | HJC FARMS, INC. | -14.8% | 3 |
| May 7, 2020 | 6363-40-001RMC - 636340001 | Howard Abilene |
CALL OUT MBGF REPAIR, ETC. IN VARIOUS COUNTIESIH 20 · | $1,602,224 | $1,363,364 | HJC FARMS, INC. | -14.9% | 3 |
| May 7, 2020 | 1007-01-026STP 2020(850)HES | Lavaca Yoakum |
SAFETY TREAT FIXED OBJECTSFM 532 · | $1,335,001 | $1,237,926 | BECK-REIT & SONS, LTD. | -7.3% | 10 |
| May 7, 2020 | 0195-03-092STP 2B20(009)HES | Denton Dallas |
INSTALLATION OF TRAFFIC SIGNALSIH 35E · | $1,200,960 | $1,105,009 | SIEMENS MOBILITY, INC. | -8.0% | 6 |
| May 7, 2020 | 0009-15-028STP 2020(828)HES | Hunt Paris |
TRAFFIC SIGNAL IMPROVEMENTSUS 69 · | $1,083,776 | $1,027,449 | SIEMENS MOBILITY, INC. | -5.2% | 4 |
| May 7, 2020 | 0048-08-052C 48-8-52 | Ellis Dallas |
FULL DEPTH CONCRETE REPAIRIH 35E · | $1,078,966 | $1,024,455 | O. TREVINO CONSTRUCTION, LLC | -5.1% | 5 |
| May 7, 2020 | 6361-29-001MMC - 636129001 | Lamar Paris |
FLEX BASE & ASPHALT TRTMNT - (MATERIALS ONLY)BU 271B · | $799,500 | $985,245 | RK HALL, LLC | +23.2% | 2 |
| May 7, 2020 | 0045-09-104STP 2020(829)HES | Lamar Paris |
IMPROVE TRAFFIC SIGNALS, INTERCONNECT SIGNALSUS 82 · | $920,695 | $951,964 | SIEMENS MOBILITY, INC. | +3.4% | 3 |
| May 7, 2020 | 0365-01-049STP 2019(935) | Parker Fort Worth |
RESURFACE ROADWAYSH 171 · | $1,254,995 | $936,540 | NORTHEASTERN PAVERS, LLC | -25.4% | 6 |
| May 7, 2020 | 6359-37-001RMC - 635937001 | Smith Tyler |
TRAFFIC CONTROLUS 69 · | $837,125 | $832,200 | FIREMAN EXCAVATING, INC. | -0.6% | 4 |
| May 7, 2020 | 6359-24-001RMC - 635924001 | Dallas Dallas |
FLEXIBLE PAVEMENT STRUCTURE REPAIRSH 183 · | $939,235 | $824,855 | PEACHTREE CONSTRUCTION, LTD. | -12.2% | 5 |
| May 7, 2020 | 6355-81-001RMC - 635581001 | Hill Waco |
BASE FAILURE PAVEMENT REPAIRFM 3267 · | $1,305,288 | $812,252 | KNIFE RIVER CORPORATION - SOUTH | -37.8% | 6 |
| May 7, 2020 | 6353-74-001RMC - 635374001 | Clay Wichita Falls |
CULVERT REPLACEMENTSH 79 · | $683,209 | $619,585 | CDM HOLDINGS, LLC | -9.3% | 9 |
| May 7, 2020 | 6361-88-001RMC - 636188001 | El Paso El Paso |
CLEANING & SWEEPINGIH 10 · | $740,500 | $605,650 | E. G. L. CONSTRUCTION, INC. | -18.2% | 5 |
| May 7, 2020 | 0923-17-087BR 2020(459) | Comanche Brownwood |
REPLACE BRIDGE AND APPROACHESCR · | $592,163 | $591,668 | ENCINO LANDSCAPE, INC. | -0.1% | 10 |
| May 7, 2020 | 0915-13-030STP 2020(791) | Atascosa San Antonio |
CONSTRUCT CURB RAMPS, SIDEWALK, PED INFRASTRUCTUREVA · | $653,847 | $584,272 | DELGADO'S CONTRACTORS, LLC | -10.6% | 11 |
| May 7, 2020 | 6352-84-001BPM - 635284001 | Garza Maintenance Division |
BRIDGE PREVENTIVE MAINTENANCEUS 84 · | $530,939 | $517,185 | BLACKSTONE CONCRETE VENTURES, LLC | -2.6% | 9 |
| May 7, 2020 | 6349-21-001RMC - 634921001 | Chambers Beaumont |
MILL AND OVERLAYSH 61 · | $604,766 | $495,428 | ANGEL BROTHERS HOLDINGS CORP. | -18.1% | 4 |
1–100 of 111Next ›
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.