SPOT PAVEMENT MARKINGS
- Let date
- Friday, May 8, 2020
- CCSJ
- 6352-14-001
- District
- Bryan
- County
- Brazos
- Highway
- SH 6
- Limits
- VARIOUS to VARIOUS
- Classification
- Maintenance
- Project number
- RMC - 635214001
- Working days
- 730
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $852,900 | ||
| 1 | INTERSTATE BARRICADES & MARKINGS, INC. Low bidder | $707,400 | -17.1% | |
| 2 | PMI PAVEMENT MARKING, LLC | $719,550 | -15.6% | +1.7% |
| 3 | TOTAL HIGHWAY MAINTENANCE, LLC | $853,650 | +0.1% | +20.7% |
| 4 | D. I. J. CONSTRUCTION, INC. | $854,400 | +0.2% | +20.8% |
| 5 | STRIPING TECHNOLOGY, L.P. | $876,753 | +2.8% | +23.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 INTERSTATE BARR… | #2 PMI PAVEMENT MA… | #3 TOTAL HIGHWAY M… | #4 D. I. J. CONSTR… | #5 STRIPING TECHNO… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6033 | MOBILIZATION (CALLOUT) | 45 | EA | $3,950.00 | $1,750.00 | $1,500.00 | $3,250.00 | $3,200.00 | $2,000.00 |
| 2 | 666-6167 | REFL PAV MRK TY II (W) 4" (BRK) | 75,000 | LF | $0.1300 | $0.1100 | $0.1300 | $0.1200 | $0.1700 | $0.1500 |
| 3 | 666-6170 | REFL PAV MRK TY II (W) 4" (SLD) | 2,700,000 | LF | $0.1200 | $0.1100 | $0.1150 | $0.1200 | $0.1300 | $0.1500 |
| 4 | 666-6178 | REFL PAV MRK TY II (W) 8" (SLD) | 30,000 | LF | $0.3600 | $0.3000 | $0.3400 | $0.2500 | $0.3500 | $0.5000 |
| 5 | 666-6205 | REFL PAV MRK TY II (Y) 4" (BRK) | 270,000 | LF | $0.1800 | $0.1200 | $0.1300 | $0.1200 | $0.1550 | $0.1500 |
| 6 | 666-6207 | REFL PAV MRK TY II (Y) 4" (SLD) | 2,100,000 | LF | $0.1200 | $0.1200 | $0.1150 | $0.1200 | $0.1400 | $0.1500 |
| 7 | 6185-6005 | TMA (MOBILE OPERATION) | 300 | DAY | $100.00 | $100.00 | $150.00 | $275.00 | $1.00 | $0.0100 |