Bid Day Forecast: 2850-01-020

Walker · Dec 1, 2026 Sign up free
Set your company to personalize scores

Intersection & Operational Imprv

CCSJ 2850-01-020 · lets Dec 1, 2026 · Walker, Bryan · FM 2821 · Construct TWLTL

$1,793,073Engineer's estimate Items at market: $2,343,686 (+30.7%)
$1,641,931Most likely low bid$1,449,788 to $1,790,735 (middle half)
6.0Expected bidders9 plan holders, 9 regular bidders
47/100Weak fitMarket only. Set your company for a personal score

Where the low bid should land

$1,288,295 (1 in 10 go lower)$1,946,483 (1 in 10 go higher)

From 71 comparable let jobs (district, estimates of $717,229 to $4,482,682, last 3 years). 76% of them went under the estimate; the typical low bid was -8.4% vs estimate.

Bid / no-bid score

  • Competition13 / 25Jobs like this draw about 6.0 bidders.
  • Margin8 / 20Low bids land at 92% of the estimate.

Set your company to add your experience, win rate and size fit.

Comparable jobs

Nov 2026 6511-02-001Brazos · 7 bidders $759,200-13.9%
Sep 2026 0917-31-036Madison · 7 bidders $1,143,373+9.9%
Aug 2026 0114-10-102Washington · 6 bidders $4,287,440+1.7%
Aug 2026 6503-26-001Brazos · 4 bidders $987,331-12.1%
Aug 2026 0917-16-040Leon · 8 bidders $2,572,458+23.8%
Jul 2026 0205-01-052Robertson · 3 bidders $1,205,489+4.8%
Jul 2026 6502-50-001Brazos · 8 bidders $1,008,500-57.3%
Jul 2026 6503-27-001Walker · 4 bidders $1,433,238-11.6%

The field: plan holders and how they bid

Last 3 years in Texas
Plan holderBidsWinsIn BryanAvg bid vs est.Avg win vs est.Their typical bid here
BIG CREEK CONSTRUCTION, LTD. SharpestBidders 23910631 of 69 -4.9%-10.4% $1,705,498
KNIFE RIVER CORPORATION - SOUTHBidders 2344821 of 96 2.9%-9.3% $1,845,292
DURWOOD GREENE CONSTRUCTION CO.Bidders 69251 of 3 3.0%-10.6% $1,846,236
TEXAS MATERIALS GROUP, INC.Bidders 7101813 of 59 3.6%-3.6% $1,858,351
LARRY YOUNG PAVING, INC.Bidders 581514 of 42 5.2%-5.6% $1,887,114
A. L. HELMCAMP, INC.Bidders 210383 of 23 8.8%-0.3% $1,951,735
BRAZOS PAVING, INC.Bidders 5455 of 53 8.9%-12.2% $1,952,778
Rucoba & Maya Construction, LLCBidders 930 of 1 14.3%-2.6% $2,049,643
FORDE CONSTRUCTION COMPANY, INC.Bidders 82100 of 8 18.5%-5.7% $2,125,364

"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.

Items that decide this job

83 of 86 items priced from low bids
ItemQtyMarket priceRange of low bidsAt marketShare
500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x 1 LS$523,850.32$0.0010 – $42,200,000.00 $523,85022.4%
344-7020 SP MIXES SP-C SAC-A PG70-2267 low bids · prices swing 3x 3,455 TON$137.95$100.00 – $309.26 $476,60420.3%
344-7001 SP MIXES SP-B PG64-2285 low bids · prices swing 4x 2,098 TON$124.45$83.00 – $325.00 $261,09111.1%
247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8")40 low bids · prices swing 11x 7,627 SY$21.46$11.38 – $122.23 $163,6747.0%
530-7006 DRIVEWAYS (CONC)295 low bids · prices swing 134x 1,111 SY$109.20$29.89 – $4,000.00 $121,3195.2%
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x 6 MO$11,585.04$0.0010 – $273,686.48 $69,5103.0%
100-7002 PREPARING ROW593 low bids · prices swing 86,117,000x 8 STA$6,072.92$0.0100 – $861,170.00 $48,5832.1%
354-7051 PLANE ASPH CONC PAV(2")169 low bids · prices swing 1,333x 26,060 SY$1.86$0.7500 – $1,000.00 $48,3952.1%
132-7006 EMBANK (FNL)(DC)(TY C)183 low bids · prices swing 105x 3,465.21 CY$13.19$3.00 – $315.00 $45,7132.0%
464-7005 RC PIPE (CL III)(24 IN)353 low bids · prices swing 11x 409 LF$108.34$46.00 – $500.00 $44,3101.9%
462-7001 CONC BOX CULV (3 FT X 2 FT)45 low bids · prices swing 6x 116 LF$328.79$209.89 – $1,250.00 $38,1401.6%
344-7077 TACK COAT277 low bids · prices swing 12,500x 10,004 GAL$3.25$0.0100 – $125.00 $32,4911.4%
530-7010 DRIVEWAYS (ACP)299 low bids · prices swing 84x 522 SY$54.96$8.88 – $750.00 $28,6871.2%
275-7028 CEMENT TRT (SUBGRADE)(10")5 low bids · prices swing 5x 8,706 SY$3.15$2.00 – $10.00 $27,4641.2%
432-7013 RIPRAP (MOW STRIP)(4 IN)593 low bids · prices swing 3,900x 43 CY$616.83$1.00 – $3,900.00 $26,5241.1%