US 290WB F: FM 1155 T: Waller CL -RER 26
0114-10-102 · let Aug 6, 2026 · Washington, Bryan · Rehabilitation of Existing Road
$4,287,440Low bid: BIG CREEK CONSTRUCTION, LTD.+1.7% vs estimate $4,214,219
$204,897Left on the table4.8% gap to the second bid
6BiddersSpread 43% low to high
73Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $4,287,440 | 1.7% | $204,897 | 1+$64,403 | 2-$354,531 | |
| 2 | KNIFE RIVER CORPORATION - SOUTH | $4,492,337 | +4.8% | 6.6% | $237,118 | 1+$36,953 | 1-$386,850 |
| 3 | BRAZOS PAVING, INC. | $4,729,455 | +10.3% | 12.2% | $303,964 | 2+$116,702 | 2-$361,321 |
| 4 | TEXAS MATERIALS GROUP, INC. | $5,033,419 | +17.4% | 19.4% | $1,344 | 3+$153,336 | 1-$81,435 |
| 5 | LARRY YOUNG PAVING, INC. | $5,034,763 | +17.4% | 19.5% | $1,084,638 | 3+$165,405 | 2-$458,703 |
| 6 | DURWOOD GREENE CONSTRUCTION CO. | $6,119,401 | +42.7% | 45.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs KNIFE RIVER CORPORATION - SOUTH, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 342-7001 PFC-C PG76-22 SAC-A | 5,053 TON | $165.00 | $195.00 | $170.34 | $151,590 |
| 344-7019 SP MIXES SP-C PG70-22 | 9,962 TON | $110.00 | $124.60 | $142.22 | $145,445 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 2,430 LF | $30.00 | $70.30 | $40.65 | $97,929 |
| 500-7001 MOBILIZATION | 1 LS | $222,000.00 | $137,000.00 | $523,850.32 | -$85,000 |
| 276-7209 CEM TRT(PLNT MX)(CL M)(TYA)(GR1-2)(12") | 6,956 SY | $65.00 | $55.46 | $53.93 | -$66,360 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 3,660 LF | $30.00 | $22.50 | $12.40 | -$27,450 |
| 105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV | 6,956 SY | $15.00 | $11.55 | $8.86 | -$23,998 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 202.1 CY | $650.00 | $767.00 | $616.83 | $23,646 |
| 533-7005 FILL MILLED ASPH RUMBLE STRIPS (SHLDR) | 12,190 LF | $3.50 | $1.70 | $3.00 | -$21,942 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $5,000.00 | $7,680.00 | $11,585.04 | $21,440 |
| 134-7004 BACKFILL (TY A OR B) | 161.77 STA | $250.00 | $124.00 | $211.21 | -$20,383 |
| 420-7067 CL C CONC (MISC) | 2 CY | $4,000.00 | $12,700.00 | $1,569.38 | $17,400 |
| 344-7001 SP MIXES SP-B PG64-22 | 3,775 TON | $110.00 | $114.20 | $124.45 | $15,855 |
| 505-7001 TMA (STATIONARY) | 98 DAY | $250.00 | $400.00 | $217.57 | $14,700 |
| 512-7053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) | 2,430 LF | $17.00 | $11.00 | $13.39 | -$14,580 |
| 168-7001 VEGETATIVE WATERING | 1,374 TGL | $5.00 | $14.50 | $8.43 | $13,053 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $9,000.00 | $4,460.00 | $9,253.78 | -$9,080 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 3 EA | $5,500.00 | $8,500.00 | $8,780.51 | $9,000 |
| 260-7007 LIME TRT (EXIST MATL)(8") | 7,561 SY | $5.00 | $3.82 | $4.35 | -$8,922 |
| 543-7018 CABLE BARRIER TERM SEC (INSTL)(TL-4) | 6 EA | $5,000.00 | $3,611.00 | $2,822.11 | -$8,334 |
Positive: the low bidder was cheaper on that item. These 20 items account for $224,008 of the $204,897 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 2BRAZOS PAVING, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 2,430 LF | $74.50 | $40.65 | 1.83x | $82,261 |
| 168-7001 VEGETATIVE WATERING | 1,374 TGL | $33.50 | $8.43 | 3.97x | $34,441 |
| 500-7001 MOBILIZATION | 1 LS | $195,500.00 | $523,850.32 | 0.37x | -$328,350 |
| 533-7005 FILL MILLED ASPH RUMBLE STRIPS (SHLDR) | 12,190 LF | $0.3000 | $3.00 | 0.10x | -$32,970 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 3,660 LF | $30.00 | $12.40 | 2.42x | $64,403 |
| 105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV | 6,956 SY | $18.00 | $8.86 | 2.03x | $63,576 |
| 260-7007 LIME TRT (EXIST MATL)(8") | 7,561 SY | $7.70 | $4.35 | 1.77x | $25,357 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $1,405.66 | $11,585.04 | 0.12x | -$81,435 |
LARRY YOUNG PAVING, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV | 6,956 SY | $18.00 | $8.86 | 2.03x | $63,576 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 3,660 LF | $28.00 | $12.40 | 2.26x | $57,083 |
| 168-7001 VEGETATIVE WATERING | 1,374 TGL | $41.00 | $8.43 | 4.86x | $44,746 |
| 500-7001 MOBILIZATION | 1 LS | $110,000.00 | $523,850.32 | 0.21x | -$413,850 |
| 530-7010 DRIVEWAYS (ACP) | 1,361 SY | $22.00 | $54.96 | 0.40x | -$44,852 |