FY27 - District Spot Pave. Mrk - 07
6502-50-001 · let Jul 2, 2026 · Brazos, Bryan · Routine Maintenance Project
$1,008,500Low bid: STRIPE-A-ZONE, LLC-57.3% vs estimate $2,360,250
$188,210Left on the table18.7% gap to the second bid
8BiddersSpread 61% low to high
11Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRIPE-A-ZONE, LLC | $1,008,500 | -57.3% | $188,210 | 0 | 1-$8,070 | |
| 2 | FC TRAFFIC CONTROL, LLC | $1,196,710 | +18.7% | -49.3% | $67,640 | 1+$49,430 | 1-$45,319 |
| 3 | DOUBLE A CONTRACTING, L.P. | $1,264,350 | +25.4% | -46.4% | $81,048 | 1+$101,180 | 1-$43,919 |
| 4 | STRIPE LINES, INC. | $1,345,398 | +33.4% | -43.0% | $8,602 | 1+$27,028 | 0 |
| 5 | TRP INFRASTRUCTURE SERVICES, LLC | $1,354,000 | +34.3% | -42.6% | $119,750 | 2+$350,761 | 0 |
| 6 | L&L COMPANY | $1,473,750 | +46.1% | -37.6% | $860 | ||
| 7 | PAVEMENT MARKINGS INC. | $1,474,610 | +46.2% | -37.5% | $153,340 | ||
| 8 | CENTERLINE TECHNOLOGIES, LLC | $1,627,950 | +61.4% | -31.0% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
STRIPE-A-ZONE, LLC vs FC TRAFFIC CONTROL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 666-7175 RE PM TY II (W) 6" (SLD) | 3,000,000 LF | $0.1700 | $0.2000 | $0.1701 | $90,000 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 2,000,000 LF | $0.1800 | $0.2100 | $0.1749 | $60,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 23 EA | $250.00 | $2,750.00 | $600.85 | $57,500 |
| 505-7003 TMA (MOBILE OPERATION) | 200 DAY | $250.00 | $3.00 | $229.60 | -$49,400 |
| 666-7211 RE PM TY II (Y) 6" (BRK) | 275,000 LF | $0.1700 | $0.2300 | $0.1759 | $16,500 |
| 666-7172 RE PM TY II (W) 6" (BRK) | 60,000 LF | $0.1800 | $0.2500 | $0.2347 | $4,200 |
| 666-7179 RE PM TY II (W) 8" (SLD) | 32,000 LF | $0.3500 | $0.4800 | $0.4127 | $4,160 |
| 666-7181 RE PM TY II (W) 12" (LNDP) | 5,000 LF | $0.7500 | $1.10 | $1.66 | $1,750 |
| 666-7182 RE PM TY II (W) 12" (SLD) | 5,000 LF | $1.25 | $1.55 | $2.13 | $1,500 |
| 666-7177 RE PM TY II (W) 8" (DOT) | 5,000 LF | $0.5000 | $0.7500 | $0.5160 | $1,250 |
| 666-7173 RE PM TY II (W) 6" (DOT) | 5,000 LF | $0.3000 | $0.4500 | $0.4797 | $750 |
Positive: the low bidder was cheaper on that item. These 11 items account for $188,210 of the $188,210 gap.
STRIPE-A-ZONE, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 23 EA | $250.00 | $600.85 | 0.42x | -$8,070 |
FC TRAFFIC CONTROL, LLC: unbalanced items
Placed 2DOUBLE A CONTRACTING, L.P.: unbalanced items
Placed 3STRIPE LINES, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 23 EA | $1,776.00 | $600.85 | 2.96x | $27,028 |