CR 444 AT BEDIAS CREEK
0917-31-036 · let Sep 3, 2026 · Madison, Bryan · Bridge Replacement
$1,143,373Low bid: FUQUA CONSTRUCTION CO., INC.+9.9% vs estimate $1,040,840
$3,262Left on the table0.3% gap to the second bid
7BiddersSpread 20% low to high
64Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FUQUA CONSTRUCTION CO., INC. | $1,143,373 | 9.9% | $3,262 | 0 | 3-$518,669 | |
| 2 | R CONSTRUCTION CIVIL, LLC | $1,146,635 | +0.3% | 10.2% | $15,540 | 3+$50,710 | 2-$493,833 |
| 3 | THK CONSTRUCTION LLC | $1,162,175 | +1.6% | 11.7% | $3,480 | 2+$54,673 | 3-$545,986 |
| 4 | PMCO CONSTRUCTION LLC | $1,165,655 | +1.9% | 12.0% | $61,415 | 2+$113,354 | 4-$533,906 |
| 5 | A. L. HELMCAMP, INC. | $1,227,070 | +7.3% | 17.9% | $49,127 | 2+$39,711 | 3-$489,988 |
| 6 | KNIFE RIVER CORPORATION - SOUTH | $1,276,197 | +11.6% | 22.6% | $100,586 | ||
| 7 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $1,376,783 | +20.4% | 32.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
FUQUA CONSTRUCTION CO., INC. vs R CONSTRUCTION CIVIL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $166,498.28 | $60,000.00 | $523,850.32 | -$106,498 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 887 CY | $81.83 | $160.00 | $184.74 | $69,338 |
| 100-7002 PREPARING ROW | 7.1 STA | $8,288.27 | $1,850.00 | $6,072.92 | -$45,712 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $1,579.92 | $6,950.00 | $11,585.04 | $37,591 |
| 420-7012 CL C CONC (ABUT) | 65.6 CY | $1,264.90 | $695.00 | $1,307.98 | -$37,386 |
| 450-7008 RAIL (TY T223) | 380 LF | $95.19 | $160.00 | $141.07 | $24,626 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 1,938 SY | $1.29 | $11.00 | $1.43 | $18,824 |
| 110-7002 EXCAV (CHANNEL) | 645 CY | $14.41 | $41.00 | $16.69 | $17,151 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 436 CY | $15.24 | $51.00 | $13.19 | $15,594 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $29,700.00 | $37,000.00 | $28,021.15 | $14,600 |
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 1,587 SY | $33.54 | $28.00 | $21.46 | -$8,790 |
| 454-7001 TYPE A JOINT | 112 LF | $25.83 | $104.00 | $64.16 | $8,755 |
| 400-7010 CEM STABIL BKFL | 156 CY | $77.00 | $130.00 | $138.14 | $8,268 |
| 416-7005 DRILL SHAFT (30 IN) | 540 LF | $302.52 | $290.00 | $239.74 | -$6,762 |
| 422-7005 REINF CONC SLAB (BOX BEAM) | 3,926 SF | $21.44 | $20.00 | $35.96 | -$5,650 |
| 100-7003 PREP ROW (TREE REMOVE) (0"-12" DIA) | 2 EA | $620.94 | $3,000.00 | $506.92 | $4,758 |
| 540-7006 MTL BEAM GD FEN TRANS (TL2) | 8 EA | $1,727.00 | $1,150.00 | $1,367.97 | -$4,616 |
| 110-7001 EXCAV (ROADWAY) | 77 CY | $13.46 | $41.00 | $11.68 | $2,120 |
| 425-7029 PRESTR CONC BOX BEAM (5B28) | 297.88 LF | $299.53 | $293.00 | $277.03 | -$1,945 |
| 658-7002 INSTL DEL ASSM (D-SW)SZ 1(WFLX)GF2(BI) | 16 EA | $55.00 | $29.00 | $27.13 | -$416 |
Positive: the low bidder was cheaper on that item. These 20 items account for $3,850 of the $3,262 gap.
FUQUA CONSTRUCTION CO., INC.: unbalanced items
Placed 1R CONSTRUCTION CIVIL, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 160-7002 FURN & PLACE TOPSOIL (4") | 1,938 SY | $11.00 | $1.43 | 7.70x | $18,548 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 436 CY | $51.00 | $13.19 | 3.87x | $16,484 |
| 110-7002 EXCAV (CHANNEL) | 645 CY | $41.00 | $16.69 | 2.46x | $15,677 |
| 500-7001 MOBILIZATION | 1 LS | $60,000.00 | $523,850.32 | 0.11x | -$463,850 |
| 100-7002 PREPARING ROW | 7.1 STA | $1,850.00 | $6,072.92 | 0.30x | -$29,983 |
THK CONSTRUCTION LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 1,587 SY | $40.00 | $21.46 | 1.86x | $29,423 |
| 400-7010 CEM STABIL BKFL | 156 CY | $300.00 | $138.14 | 2.17x | $25,250 |
| 500-7001 MOBILIZATION | 1 LS | $80,000.00 | $523,850.32 | 0.15x | -$443,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $1,632.52 | $11,585.04 | 0.14x | -$69,668 |
| 100-7002 PREPARING ROW | 7.1 STA | $1,500.00 | $6,072.92 | 0.25x | -$32,468 |
PMCO CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 425-7028 PRESTR CONC BOX BEAM (4B28) | 595.74 LF | $350.00 | $189.02 | 1.85x | $95,904 |
| 400-7010 CEM STABIL BKFL | 156 CY | $250.00 | $138.14 | 1.81x | $17,450 |
| 500-7001 MOBILIZATION | 1 LS | $115,000.00 | $523,850.32 | 0.22x | -$408,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $3,000.00 | $11,585.04 | 0.26x | -$60,095 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $10,000.00 | $28,021.15 | 0.36x | -$36,042 |
| 100-7002 PREPARING ROW | 7.1 STA | $2,000.00 | $6,072.92 | 0.33x | -$28,918 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 645 CY | $50.00 | $16.69 | 3.00x | $21,482 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 436 CY | $55.00 | $13.19 | 4.17x | $18,228 |
| 500-7001 MOBILIZATION | 1 LS | $120,000.00 | $523,850.32 | 0.23x | -$403,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $5,000.00 | $11,585.04 | 0.43x | -$46,095 |