35Let jobs
$112,548,047Total low bids
$103,430,449Total estimates
+8.8%Low bids vs estimates
Jan 2021 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Jan 21, 2021 | 200340BSAP-207N(012)FM | Bsap-207c(102)fm |
34764(04) SSP-013N(182)PM BRYAN PORT OF ENTRY , GRADE, DRAIN, SURFACE AND RESURFACE US-69: FROM 0.2 MILES SOUTH OF THE SH -91 INTERCHANGE, EXTEND NORTH IN COLBERT . PROJECT LENGTH = 2.496 MILES · | $16,511,062 | $17,981,742 | OVERLAND CORPORATION | +8.9% | 1 |
| Jan 21, 2021 | 210025STP-237C(034)PM | Kingfisher Division 4 |
GRADE, DRAIN, SURFACE , AND BRIDGE SH-51: FROM THE US -81 JUNCTION, EXTEND EAST NEAR HENNESSEY . PROJECT LENGTH = 6.984 MILES · | — | $12,515,005 | THE CUMMINS CONSTRUCTION CO., INC. | 3 | |
| Jan 21, 2021 | 210030NHPPI-3500(094)PM | Mcclain Division 3 |
PAVEMENT REHABILITATION (A.C. AND P.C.) I-35: FROM 1.1 MILES SOUTH OF THE SH -59 JUNCTION, EXTEND NORTH NEAR WAYNE . PROJECT LENGTH = 2.102 MILES · | $15,424,461 | $12,287,440 | IHC Scott, INC. | -20.3% | 4 |
| Jan 21, 2021 | 210035NHPP-262N(061)PM | Pontotoc |
GRADE, DRAIN, AND SURFACE SH-1: FROM 1.3 MILES SOUTH OF THE SH -3 INTERCHANGE, EXTEND NORTH NEAR ADA . PROJECT LENGTH = 1.483 MILES · | $9,641,528 | $9,022,083 | THE CUMMINS CONSTRUCTION CO., INC. | -6.4% | 3 |
| Jan 21, 2021 | 210018STP-130C(149)PM | Harper Division 6 |
WIDEN AND RESURFACE US-183: FROM THE WOODWARD COUNTY LINE , EXTEND NORTH NEAR FORT SUPPLY . PROJECT LENGTH = 4.583 MILES · | $8,031,100 | $7,488,386 | THE CUMMINS CONSTRUCTION CO., INC. | -6.8% | 2 |
| Jan 21, 2021 | 210007NHPPI-4000-(098)PM | Beckham Division 5 |
BRIDGE REHABILITATION I-40: OVER NORTH FORK OF RED RIVER , 0.5 MILES SOUTH OF THE SH -152 INTERCHANGE IN SAYRE . PROJECT LENGTH = 0.247 MILE · | $8,022,197 | $7,458,048 | C3 Construction, Inc. | -7.0% | 6 |
| Jan 21, 2021 | 210031STP-155A(196)AG | Oklahoma Division 4 |
GRADE, DRAIN, WIDEN, RESURFACE , AND TRAFFIC SIGNALS CITY STREET (MACARTHUR BOULEVARD ): FROM NW 34TH STREET, EXTEND NORTH IN THE CITY OF WARR ACRES. PROJECT LENGTH = 0.927 MILES · | $5,913,578 | $6,207,409 | SCHWARZ PAVING CO., INC. | +5.0% | 5 |
| Jan 21, 2021 | 210010CIRB-214C(105)RB | Cleveland Division 3 |
GRADE, DRAIN, AND SURFACE COUNTY ROAD (156TH AVENUE S .E./NS-325): FROM MAGUIRE ROAD, EXTEND NORTH NEAR ETOWAH . PROJECT LENGTH = 3.742 MILES · | $5,117,975 | $4,208,830 | T.J. CAMPBELL CONSTRUCTION COMPANY | -17.8% | 4 |
| Jan 21, 2021 | 210027SSR-240N(084)SR | Leflore |
RESURFACE (ASPHALT ) US-259: FROM 4.2 MILES NORTH OF THE SH -144 JUNCTION, EXTEND NORTH NEAR BIG CEDAR . PROJECT LENGTH = 10.000 MILES · | $2,539,879 | $3,259,936 | Rosscon, LLC | +28.4% | 2 |
| Jan 21, 2021 | 210024SSR-236C(075)SR | Kay Division 4 |
RESURFACE (ASPHALT ) US-177: FROM CHRYSLER AVENUE , EXTEND NORTH IN BLACKWELL . PROJECT LENGTH = 3.00 MILES · | $1,982,320 | $2,478,797 | Evans & Associates Construction Co., Inc. | +25.0% | 1 |
| Jan 21, 2021 | 210022SSR-235C(059)SR | Ssr-235c(058)sr |
JOHNSTON RESURFACE (ASPHALT ) SH-22/SH-78: SH-78, FROM THE BRYAN COUNTY LINE , EXTEND NORTH THEN WEST NEAR MILBURN . SH-22, FROM THE SH -78 JUNCTION, EXTEND WEST NEAR TISHOMINGO . PROJECT LENGTH = 15.95 MILES · | $2,752,899 | $2,435,260 | OVERLAND CORPORATION | -11.5% | 3 |
| Jan 21, 2021 | 210039SSR-268C(073)SR | Sequoyah Division 1 |
RESURFACE (ASPHALT ) US-64: FROM 2.1 MILES EAST OF US -59 JUNCTION, EXTEND SOUTHEAST NEAR SALLISAW . PROJECT LENGTH = 5.880 MILES · | $2,320,119 | $2,358,843 | Rosscon, LLC | +1.7% | 2 |
| Jan 21, 2021 | 210006SSR-202C(058)SR | Ssr-202c(057)sr |
32753(04) SSR-202B(059)SR ALFALFA RESURFACE (ASPHALT ) SH-45: FROM THE WOODS COUNTY LINE , EXTEND EAST NEAR CARMEN , HELENA, AND GOLTRY . PROJECT LENGTH = 13.12 MILES · | $2,026,355 | $2,298,713 | THE CUMMINS CONSTRUCTION CO., INC. | +13.4% | 1 |
| Jan 21, 2021 | 210017STP-226C(083)CI | Grady Division 7 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-2958): OVER RUSH CREEK, 5.4 MILES NORTH OF THE SH -29 JUNCTION NEAR COX CITY. PROJECT LENGTH = 0.464 MILE · | $2,223,351 | $2,069,514 | Treas Construction Inc | -6.9% | 6 |
| Jan 21, 2021 | 210009SSR-208B(098)SR | Caddo Division 7 |
RESURFACE (ASPHALT ) AND BRIDGE REPAIR US-62: FROM 0.58 MILES EAST OF THE SH -8 SOUTH JUNCTION, EXTEND EAST IN ANADARKO . PROJECT LENGTH = 7.580 MILES · | $2,128,343 | $1,857,904 | T & G CONSTRUCTION, INC. | -12.7% | 5 |
| Jan 21, 2021 | 210037SBR-264N(073)SB | Pushmataha Division 2 |
BRIDGE REHABILITATION SH-3: OVER FRAZIER CREEK, 0.4 MILES WEST OF THE SH -147 JUNCTION NEAR RATTAN . PROJECT LENGTH = 0.211 MILE · | $2,153,066 | $1,831,737 | B & B CONSTRUCTION SERVICE J.T., INC. | -14.9% | 8 |
| Jan 21, 2021 | 210029SSR-249C(063)SR | Mayes Division 8 |
RESURFACE (ASPHALT ) SH-82: FROM THE US -412 JUNCTION, EXTEND NORTH NEAR LOCUST GROVE . PROJECT LENGTH = 6.980 MILES · | $1,704,583 | $1,523,000 | BECCO CONTRACTORS, INC. | -10.7% | 5 |
| Jan 21, 2021 | 210026SSR-240B(083)SR | Leflore |
RESURFACE (ASPHALT ) SH-112: FROM THE SH -112 JUNCTION, EXTEND NORTH NEAR ARKOMA . PROJECT LENGTH = 5.090 MILES · | $1,365,037 | $1,279,941 | JOB CONSTRUCTION CO., INC. | -6.2% | 3 |
| Jan 21, 2021 | 210008STP-208B(089)CI | Caddo Division 7 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-134): OVER FORMER WASHITA RIVER , 0.6 MILES WEST OF THE SH -9 JUNCTION IN ANADARKO . PROJECT LENGTH = 0.321 MILE · | $1,651,158 | $1,267,273 | Treas Construction Inc | -23.2% | 10 |
| Jan 21, 2021 | 210034SSR-258C(078)SR | Ottawa Division 8 |
RESURFACE (ASPHALT ) SH-137: FROM THE US -60 JUNCTION, EXTEND NORTH NEAR WYANDOTTE . PROJECT LENGTH = 6.29 MILES · | — | $1,264,262 | EMERY SAPP & SONS, INC. | 4 | |
| Jan 21, 2021 | 210012NHPP-215N(039)PM | Coal Division 3 |
BRIDGE AND APPROACHES US-75: OVER CANEY CREEK , 0.8 MILES NORTHWEST OF THE SH -31 JUNCTION NEAR COALGATE . PROJECT LENGTH = 0.056 MILE · | $1,681,336 | $1,241,460 | Treas Construction Inc | -26.2% | 8 |
| Jan 21, 2021 | 210028SSR-243C(040)SR | Love Division 7 |
RESURFACE (ASPHALT ) US-77: FROM I-35, EXTEND NORTH NEAR MARIETTA . PROJECT LENGTH = 2.250 MILES · | $1,401,036 | $1,195,668 | OVERLAND CORPORATION | -14.7% | 2 |
| Jan 21, 2021 | 210019STP-235C(053)PM | Johnston Division 3 |
BRIDGE REHABILITATION SH-7: OVER KEEL CREEK , 3.8 MILES WEST OF THE US-377 JUNCTION NEAR WAPANUCKA . PROJECT LENGTH = 0.198 MILE · | $1,324,176 | $1,181,139 | C3 Construction, Inc. | -10.8% | 8 |
| Jan 21, 2021 | 210016CIRB-226D(084)RB | Grady Division 7 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-137): OVER EAST BITTER CREEK , 1.1 MILES SOUTH OF THE US -277 JUNCTION NEAR CHICKASHA. PROJECT LENGTH = 0.266 MILE · | $1,317,343 | $1,060,215 | K & R BUILDERS, INC. | -19.5% | 8 |
| Jan 21, 2021 | 210004HSIPG-266B(068)PM | Rogers Division 8 |
SAFETY IMPROVEMENT (CABLE BARRIER) SH-20: FROM 3.9 MILES EAST OF I -44 (WILL ROGERS TURNPIKE ), EXTEND EAST NEAR CLAREMORE. PROJECT LENGTH = 3.90 MILES · | $968,805 | $1,009,000 | BECCO CONTRACTORS, INC. | +4.1% | 3 |
| Jan 21, 2021 | 210040TAP-269F(079)TP | Stp-269f(076)ad |
STEPHENS PEDESTRIAN IMPROVEMENTS (SIDEWALKS ) US-81/SH-53/CITY STREET (2ND STREET): US-81, FROM 0.1 MILES SOUTH OF THE SH-53 JUNCTION EXTEND NORTH IN COMANCHE . PROJECT LENGTH = 0.373 MILE · | $898,247 | $991,591 | SCHIRALLI CONSTRUCTION CORP. | +10.4% | 3 |
| Jan 21, 2021 | 210014STP-224C(084)CI | Garfield Division 4 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-296): OVER RED ROCK CREEK, 6.5 MILES NORTH OF THE US -64 JUNCTION NEAR BRECKINRIDGE. PROJECT LENGTH = 0.454 MILE · | $980,768 | $921,008 | K & R BUILDERS, INC. | -6.1% | 6 |
| Jan 21, 2021 | 210032SSR-256B(061)SR | Okmulgee Division 1 |
RESURFACE (ASPHALT ) SH-16: FROM THE SH -52 JUNCTION, EXTEND EAST NEAR BEGGS . PROJECT LENGTH = 4.900 MILES · | — | $888,487 | Rosscon, LLC | 4 | |
| Jan 21, 2021 | 210033SSR-018N(078)SR | Osage Division 8 |
RESURFACE (ASPHALT ) US-60: FROM 1.8 MILES WEST OF THE SH -99 JUNCTION, EXTEND EAST IN PAWHUSKA . PROJECT LENGTH = 1.85 MILES · | $855,733 | $769,000 | BECCO CONTRACTORS, INC. | -10.1% | 3 |
| Jan 21, 2021 | 210005STP-202C(047)CI | Alfalfa Division 6 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-30): OVER EAST CLAY CREEK , 3.3 MILES WEST OF THE SH -58 JUNCTION NEAR HELENA. PROJECT LENGTH = 0.312 MILE · | $860,726 | $742,079 | K & R BUILDERS, INC. | -13.8% | 6 |
| Jan 21, 2021 | 200282NHPP-009N(101) AD | Kiowa Division 5 |
PEDESTRIAN IMPROVEMENTS (SIDEWALKS ) US-183: FROM THE SH -19 JUNCTION, EXTEND SOUTH IN ROOSEVELT . PROJECT LENGTH = 0.372 MILE · | $509,861 | $466,664 | TOM HUDSON PAVING, INC. | -8.5% | 6 |
| Jan 21, 2021 | 210023STP-235C(054)PM | Johnston Division 3 |
BRIDGE AND APPROACHES SH-48: OVER UNNAMED CREEK, 1.5 MILES NORTH OF THE SH -48A JUNCTION NEAR COLEMAN. PROJECT LENGTH = 0.084 MILE · | $573,484 | $423,630 | Treas Construction Inc | -26.1% | 4 |
| Jan 21, 2021 | 210003NHPP-014N(102)PM | Washington Division 8 |
SAFETY IMPROVEMENT (RIGHT TURN LANE ) US-75: FROM 0.3 MILES NORTH OF THE US -60 INTERCHANGE, EXTEND NORTH IN BARTLESVILLE . PROJECT LENGTH = 0.030 MILE · | $212,623 | $219,609 | Tri Star Construction Arkansas, LLC | +3.3% | 3 |
| Jan 21, 2021 | 210038STP-267B(090)RW | Seminole Division 3 |
RIGHT-OF-WAY CLEARANCE US-270: FROM 0.2 MILES WEST OF THE US -270A (NS-357) JUNCTION, EXTEND SOUTHEAST IN SEMINOLE . PROJECT LENGTH = 8.040 MILES · | $205,209 | $177,100 | Robin Hausner Demolition, LLC | -13.7% | 2 |
| Jan 21, 2021 | 210011SAP-3500(109)ES | Cleveland Division 3 |
BRIDGE REPAIR CITY STREET (NW 12TH STREET): REPAIR VEHICLE IMPACT DAMAGE OVER I-35, 1.1 MILES NORTH OF SH -37 IN MOORE. PROJECT LENGTH = 0.000 MILE · | $132,092 | $167,276 | PBX Corporation | +26.6% | 4 |
1–35 of 35
Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.