| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$17,624.35 |
$12,000.00 |
$15,000.00 |
| 2 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$45,000.00 |
$40,000.00 |
$50,000.00 |
| 3 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,040 | LF |
$1.92 |
$3.64 |
$2.71 |
| 4 | 221(F) 0100 |
TEMPORARY SILT DIKE | 28 | LF |
$9.91 |
$16.50 |
$15.80 |
| 5 | 230(A) 2806 |
SOLID SLAB SODDING | 723 | SY |
$3.40 |
$11.44 |
$3.80 |
| 6 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 395 | CY |
$58.38 |
$65.00 |
$60.00 |
| 7 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 143 | TON |
$38.37 |
$22.00 |
$40.00 |
| 8 | 407(B) 0250 |
TACK COAT | 151 | GAL |
$5.27 |
$4.90 |
$6.00 |
| 9 | 408 5774 |
PRIME COAT | 936 | GAL |
$5.49 |
$4.10 |
$6.00 |
| 10 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 449 | TON |
$119.53 |
$92.50 |
$100.00 |
| 11 | 411(D) 5975 |
SUPERPAVE, TYPE S5(PG 64-22 OK) | 337 | TON |
$81.64 |
$102.15 |
$105.00 |
| 12 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 100 | LF |
$21.90 |
$16.00 |
$21.00 |
| 13 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$1,778.90 |
$1,415.00 |
$1,765.00 |
| 14 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 4 | EA |
$2,295.56 |
$1,830.00 |
$2,356.00 |
| 15 | 624(E) 4294 |
FENCE-STYLE CLF (8'HIGH, CLASS A) | 347.02 | LF |
$92.82 |
$55.00 |
$50.00 |
| 16 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 210 | CY |
$17.14 |
$10.00 |
$33.00 |
| 17 | 501(G) 6309 |
CLSM BACKFILL | 120 | CY |
$151.44 |
$150.00 |
$188.51 |
| 18 | 503(A) 6290 |
PRESTRESSED CONCRETE BEAMS (TYPE J BT) | 404 | LF |
$246.24 |
$450.00 |
$700.00 |
| 19 | 504(A) 1304 |
APPROACH SLAB | 114.8 | SY |
$183.94 |
$180.00 |
$200.00 |
| 20 | 504(B) 1305 |
SAW-CUT GROOVING | 423.26 | SY |
$7.18 |
$6.10 |
$8.31 |
| 21 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 347.2 | LF |
$80.40 |
$80.00 |
$100.00 |
| 22 | 506(A) 1322 |
STRUCTURAL STEEL | 970 | LB |
$2.51 |
$2.00 |
$4.00 |
| 23 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 3 | EA |
$980.89 |
$1,000.00 |
$803.00 |
| 24 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 3 | EA |
$970.64 |
$1,000.00 |
$803.00 |
| 25 | 509(A) 1326 |
CLASS AA CONCRETE | 117.2 | CY |
$687.86 |
$900.00 |
$900.00 |
| 26 | 509(B) 1328 |
CLASS A CONCRETE | 147.5 | CY |
$720.64 |
$900.00 |
$600.00 |
| 27 | 510(A) 6334 |
RETAINING WALL | 187.1 | SY |
$425.00 |
$500.00 |
$475.00 |
| 28 | 511(A) 1332 |
REINFORCING STEEL | 37,300 | LB |
$0.9900 |
$0.9500 |
$1.20 |
| 29 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 9,860 | LB |
$1.17 |
$1.00 |
$1.22 |
| 30 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 317.46 | LF |
$37.56 |
$24.00 |
$32.00 |
| 31 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 1,064.41 | LF |
$36.78 |
$30.00 |
$32.00 |
| 32 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 317.46 | LF |
$13.34 |
$10.00 |
$15.00 |
| 33 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 1,064.41 | LF |
$14.62 |
$12.50 |
$15.00 |
| 34 | 514(K) 6260 |
(PL)PILOT HOLES | 526.91 | LF |
$125.04 |
$60.00 |
$200.00 |
| 35 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
| 36 | 516(A) 6094 |
DRILLED SHAFTS 48" DIAMETER | 176 | LF |
$704.87 |
$950.00 |
$1,400.00 |
| 37 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 473.67 | TON |
$45.91 |
$35.00 |
$48.40 |
| 38 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 157.89 | TON |
$39.34 |
$25.00 |
$37.00 |
| 39 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$25,000.00 |
$40,000.00 |
$75,000.00 |
| 40 | 622(A) 4445 |
2" PIPE RAILING | 96 | LF |
$125.00 |
$125.00 |
$120.00 |
| 41 | 104 0955 |
(SP) RAILROAD FLAGGING(NON-BIDDABLE) | 30 | DAY |
$490.00 |
$490.00 |
$490.00 |
| 42 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$3,314.86 |
$2,740.00 |
$10,000.00 |
| 43 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$15,000.00 |
$5,000.00 |
$6,000.00 |
| 44 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$57,080.47 |
$85,000.00 |
$85,000.00 |