| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$15,000.00 |
$7,150.00 |
$8,494.00 |
$12,250.00 |
$13,000.00 |
$20,000.00 |
$30,400.00 |
| 2 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$30,000.00 |
$26,400.00 |
$36,687.00 |
$33,856.00 |
$35,000.00 |
$35,000.00 |
$27,500.00 |
| 3 | 221(C) 2801 |
TEMPORARY SILT FENCE | 2,000 | LF |
$2.50 |
$1.34 |
$1.22 |
$1.53 |
$1.40 |
$2.00 |
$2.50 |
| 4 | 221(F) 0100 |
TEMPORARY SILT DIKE | 300 | LF |
$6.00 |
$7.08 |
$6.44 |
$8.05 |
$7.50 |
$8.00 |
$21.50 |
| 5 | 221(G) 0151 |
TEMPORARY ROCK FILTER DAM TYPE 2 | 30 | CY |
$80.00 |
$137.50 |
$60.00 |
$150.00 |
$110.00 |
$70.00 |
$178.00 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 11,280 | SY |
$2.50 |
$1.47 |
$1.34 |
$1.68 |
$1.40 |
$2.50 |
$3.00 |
| 7 | 233(A) 2817 |
VEGETATIVE MULCHING | 4.6 | AC |
$500.00 |
$453.20 |
$412.00 |
$300.00 |
$675.00 |
$800.00 |
$930.00 |
| 8 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 1,344 | TON |
$30.00 |
$30.73 |
$31.05 |
$34.94 |
$40.00 |
$45.00 |
$46.00 |
| 9 | 408 5774 |
PRIME COAT | 1,133 | GAL |
$4.50 |
$11.00 |
$12.00 |
$12.50 |
$5.00 |
$10.00 |
$8.00 |
| 10 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$300.00 |
$431.37 |
$350.00 |
$300.00 |
$200.00 |
$400.00 |
$536.00 |
| 11 | 613(B) 4530 |
42" X 29" CORR. GALV. STEEL PIPE ARCH | 174 | LF |
$50.00 |
$51.50 |
$51.08 |
$49.00 |
$75.00 |
$65.00 |
$73.00 |
| 12 | 624(C) 4459 |
FENCE-STYLE SWF (5 BARBED WIRE) | 1,877 | LF |
$5.00 |
$9.57 |
$8.70 |
$10.88 |
$9.00 |
$10.00 |
$15.75 |
| 13 | 202(A) 1301 |
UNCLASSIFIED EXCAVATION | 622 | CY |
$5.58 |
$8.80 |
$7.22 |
$8.80 |
$20.00 |
$20.00 |
$32.00 |
| 14 | 501(A) 1306 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 90 | CY |
$11.66 |
$22.00 |
$5.00 |
$13.50 |
$20.00 |
$20.00 |
$96.00 |
| 15 | 509(A) 1326 |
CLASS AA CONCRETE | 189.8 | CY |
$550.00 |
$441.45 |
$515.76 |
$546.25 |
$600.00 |
$550.00 |
$621.00 |
| 16 | 511(A) 1332 |
REINFORCING STEEL | 27,644 | LB |
$1.00 |
$1.31 |
$0.9000 |
$0.9600 |
$1.10 |
$1.50 |
$1.00 |
| 17 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$1,000.00 |
$5,500.00 |
$4,800.00 |
$4,325.00 |
$4,000.00 |
$18,000.00 |
$19,000.00 |
| 18 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$5,000.00 |
$4,400.00 |
$4,000.00 |
$4,500.00 |
$4,000.00 |
$5,000.00 |
$9,500.00 |
| 19 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$10,000.00 |
$12,870.00 |
$11,700.00 |
$13,500.00 |
$4,200.00 |
$8,500.00 |
$6,300.00 |
| 20 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$1,650.00 |
$2,500.00 |
$3,800.00 |
$2,500.00 |
$3,500.00 |
$3,600.00 |
| 21 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$30,000.00 |
$29,657.23 |
$28,844.57 |
$27,850.00 |
$35,000.00 |
$35,000.00 |
$42,200.00 |