Bid tab 150004

Let Jan 22, 2015 · Division 5 · Beckham Sign up free

‹ Jan 2015 results

BRIDGE REHABILITATION SH -152: OVER I-40, 1.5 MILE EAST OF US -283. PROJECT LENGTH =0.084 MILES

Let date
Thursday, January 22, 2015
Contract
150004
J/P numbers
29275(04)
District
Division 5
County
Beckham
Highway
Limits
BRIDGE REHABILITATION SH -152: OVER I-40, 1.5 MILE EAST OF US -283. PROJECT LENGTH =0.084 MILES
Project number
NHPP-205N(028)SS

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,271,723
1 M.J. HUGHES CONSTRUCTION, INC. Low bidder $1,696,816 -25.3%
2 SEWELL BROS., INC / FRONTIER BRIDGE, INC $2,051,292 -9.7% +20.9%
3 K & R BUILDERS, INC. $2,199,972 -3.2% +29.7%
4 OBC, INC. $2,420,115 +6.5% +42.6%
5 WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES $2,637,575 +16.1% +55.4%
6 PBX Corporation $2,671,201 +17.6% +57.4%

Bid tab: unit prices 53 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 M.J. HUGHES CON…#2 SEWELL BROS., I…#3 K & R BUILDERS,…#4 OBC, INC.#5 WILDCAT CONSTRU…#6 PBX Corporation
1202(A) 0183 UNCLASSIFIED EXCAVATION12,000CY $15.00 $10.00 $12.10 $10.00 $21.74 $6.00 $12.00
2221(D) 2803 TEMPORARY SEDIMENT FILTER3EA $300.00 $350.00 $345.00 $450.00 $299.25 $289.49 $313.00
3221(F) 0100 TEMPORARY SILT DIKE700LF $15.00 $7.50 $8.35 $10.00 $7.24 $7.00 $8.00
4230(A) 2806 SOLID SLAB SODDING14,400SY $2.00 $1.50 $1.41 $1.50 $1.21 $1.17 $1.30
5411(C) 5950 SUPERPAVE, TYPE S4(PG 76-28 OK)500TON $200.00 $175.00 $208.45 $210.00 $180.89 $172.28 $200.00
6412 5267 COLD MILLING PAVEMENT1,000SY $15.00 $22.00 $27.50 $26.20 $22.92 $21.83 $25.00
7619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $8,000.00 $15,000.00 $6,655.00 $6,500.00 $25,200.00 $10,000.00 $15,000.00
8619(B) 4728 REMOVAL OF ASPHALT PAVEMENT6,360SY $15.00 $10.00 $8.14 $8.07 $7.06 $8.00 $10.00
9619(B) 4780 REMOVAL OF GUARDRAIL837LF $5.00 $4.00 $4.84 $5.10 $3.68 $5.00 $4.00
10623(A) 1418 BEAM GUARDRAIL W-BEAM SINGLE537.5LF $25.00 $25.00 $20.99 $19.38 $18.22 $15.50 $20.00
11623(F) 8300 GUARDRAIL TRAIL END TURNDOWN (31")2EA $1,200.00 $2,300.00 $1,083.00 $1,629.38 $939.75 $1,303.50 $1,200.00
12623(G) 8590 GUARDRAIL END TREATMENT (31")2EA $3,000.00 $2,500.00 $2,450.00 $2,695.00 $2,126.25 $2,447.50 $2,500.00
13623(I) 8700 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")4EA $3,000.00 $2,500.00 $1,875.00 $2,750.00 $1,627.50 $2,049.00 $2,000.00
14625(D) 1254 REMOVE AND RECONSTRUCT GUARDRAIL461LF $20.00 $16.00 $18.75 $17.00 $16.28 $14.98 $18.00
15501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON110CY $25.00 $15.00 $18.15 $24.00 $37.50 $40.00 $90.00
16501(G) 6309 CLSM BACKFILL110CY $200.00 $150.00 $220.00 $185.00 $222.40 $350.00 $325.00
17504(A) 1304 APPROACH SLAB317.7SY $300.00 $250.00 $239.80 $265.00 $248.59 $275.00 $300.00
18504(B) 1305 SAW-CUT GROOVING1,560.6SY $5.00 $6.00 $3.80 $4.80 $3.94 $3.15 $4.00
19504(C) 6250 SEALED EXPANSION JOINT83LF $350.00 $275.00 $377.00 $310.00 $375.85 $450.00 $450.00
20504(E) 6190 42" F-SHAPED PARAPET702.3LF $135.00 $120.00 $114.00 $138.00 $144.05 $160.00 $250.00
21506(A) 1322 STRUCTURAL STEEL680LB $15.00 $9.50 $13.83 $10.00 $7.75 $8.00 $15.00
22509 6153 SPECIAL CONCRETE FINISH1LSUM $25,000.00 $18,000.00 $18,150.00 $24,000.00 $55,418.75 $50,000.00 $100,000.00
23509(A) 1326 CLASS AA CONCRETE325.7CY $1,200.00 $740.00 $935.00 $1,060.00 $1,188.72 $1,200.00 $1,350.00
24509(D) 1331 CLASS C CONCRETE5CY $500.00 $485.00 $704.00 $900.00 $875.62 $1,200.00 $2,500.00
25511(B) 6010 EPOXY COATED REINFORCING STEEL109,130LB $1.20 $1.15 $1.54 $1.21 $1.23 $2.00 $1.60
26512(A) 1323 PAINTING EXISTING STRUCTURES1LSUM $40,000.00 $25,000.00 $28,600.00 $31,000.00 $28,850.00 $50,000.00 $125,000.00
27512(B) 6303 COLLECTION AND HANDLING OF WASTE1LSUM $20,000.00 $12,000.00 $3,570.00 $5,000.00 $3,625.00 $10,000.00 $2,500.00
28515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)631.2SY $5.00 $4.50 $3.94 $4.80 $4.38 $3.50 $5.00
29520(A) 6058 PREPARATION OF CRACKS, ABOVE WATER200LF $50.00 $50.00 $48.40 $50.00 $50.00 $35.00 $32.00
30520(C) 6060 EPOXY RESIN, ABOVE WATER16GAL $150.00 $125.00 $72.60 $72.00 $75.00 $104.00 $85.00
31521(A) 6210 PNEUMATICALLY PLACED MORTAR100SY $950.00 $350.00 $954.00 $900.00 $966.25 $518.00 $475.00
32523(A) 6550 SEALER CRACK PREPARATION81LF $5.00 $7.50 $5.33 $3.75 $5.00 $4.00 $8.00
33523(B) 6560 SEALER RESIN1GAL $150.00 $315.00 $242.00 $120.00 $125.00 $100.00 $90.00
34619(B) 2510 REMOVAL OF BRIDGE ITEM (TYPE A)1LSUM $10,000.00 $15,000.00 $35,250.00 $25,000.00 $50,612.50 $15,000.00 $30,000.00
35619(B) 2520 REMOVAL OF BRIDGE ITEM (TYPE B)1LSUM $180,000.00 $70,000.00 $230,000.00 $206,000.00 $257,475.00 $280,000.00 $263,000.00
36619(B) 2530 REMOVAL OF BRIDGE ITEM (TYPE C)1LSUM $10,000.00 $10,000.00 $29,500.00 $29,500.00 $50,612.50 $30,000.00 $75,000.00
37856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)3,251LF $2.00 $2.90 $1.21 $1.30 $2.58 $1.00 $2.75
38857(E) 8887 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-112,420EA $0.7000 $0.4500 $0.5200 $0.5500 $0.4100 $0.4200 $0.4400
39857(F) 8006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE)1,445LF $1.30 $1.15 $1.21 $1.20 $1.03 $1.00 $1.10
40877(B) 8484 DELIVER PORTABLE LONGITUDINAL BARRIER8,625LF $33.00 $32.00 $24.20 $42.75 $32.96 $73.00 $35.00
41877(C) 8486 RELOCATION OF PORTABLE LONGITUDINAL BARRIER8,625LF $7.00 $3.50 $8.47 $8.75 $8.24 $5.00 $5.00
42880(A) 8812 ARROW DISPLAY(TYPE C)240SD $10.00 $6.00 $18.15 $17.00 $5.15 $15.00 $6.00
43880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF21,440SD $0.5000 $0.3000 $0.1900 $0.2000 $0.2600 $0.1500 $0.2700
44880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF15,440SD $1.00 $0.3000 $0.1900 $0.2200 $0.2600 $0.1500 $0.2700
45880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF7,220SD $1.50 $1.15 $2.42 $2.40 $1.03 $2.00 $1.10
46880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)5,040SD $2.00 $0.9000 $0.7200 $0.7500 $0.7700 $0.6000 $0.8500
47880(C) 8848 WING BARRICADES480SD $1.50 $2.50 $0.3600 $0.4000 $0.0300 $0.3000 $2.20
48880(E) 8860 WARNING LIGHTS(TYPE A)13,380SD $0.5000 $0.3000 $0.3600 $0.3900 $0.2600 $0.3000 $0.2700
49880(F) 8878 DRUMS30,180SD $0.7500 $0.9000 $0.3600 $0.4100 $0.8200 $0.3000 $0.8800
50882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN348SD $20.00 $18.00 $12.00 $12.00 $15.45 $10.00 $17.00
51642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $15,000.00 $12,000.00 $11,000.00 $16,000.00 $9,862.25 $5,000.00 $15,000.00
52220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $3,000.00 $5,500.00 $6,000.00 $5,000.00 $2,000.00 $15,000.00
53641 1399 MOBILIZATION1LSUM $135,000.00 $125,000.00 $127,650.00 $134,000.00 $143,584.09 $202,500.00 $157,000.00