BRIDGE AND APPROACHES US -183: OVER GYP CREEK , 9.8 MILES NORTH OF THE WOODWARD COUNTY LINE . PROJECT LENGTH = 0.052 MILE
- Let date
- Thursday, September 18, 2014
- Contract
- 140294
- J/P numbers
- 27008(04)
- District
- Division 6
- County
- Harper
- Highway
- Limits
- BRIDGE AND APPROACHES US -183: OVER GYP CREEK , 9.8 MILES NORTH OF THE WOODWARD COUNTY LINE . PROJECT LENGTH = 0.052 MILE
- Project number
- SSP-230C(014)SS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $425,348 | ||
| 1 | KLAVER CONSTRUCTION COMPANY, INC. Low bidder | $410,755 | -3.4% | |
| 2 | Reece Construction Co, Inc. | $459,495 | +8.0% | +11.9% |
| 3 | Frontier Bridge, Inc. | $494,797 | +16.3% | +20.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 KLAVER CONSTRUC… | #2 Reece Construct… | #3 Frontier Bridge… |
|---|---|---|---|---|---|---|---|---|
| 1 | 201(A) 0102 | CLEARING AND GRUBBING | 1 | LSUM | $2,500.00 | $6,444.80 | $6,444.80 | $19,800.00 |
| 2 | 202(A) 0183 | UNCLASSIFIED EXCAVATION | 2,271 | CY | $10.00 | $11.06 | $11.06 | $8.80 |
| 3 | 202(D) 0184 | UNCLASSIFIED BORROW | 940 | CY | $15.00 | $17.99 | $17.99 | $17.60 |
| 4 | 205(A) 4229 | TYPE A-SALVAGED TOPSOIL | 1 | LSUM | $10,000.00 | $2,685.33 | $2,685.33 | $3,850.00 |
| 5 | 221(C) 2801 | TEMPORARY SILT FENCE | 600 | LF | $3.00 | $2.50 | $2.00 | $2.75 |
| 6 | 221(F) 0100 | TEMPORARY SILT DIKE | 70 | LF | $10.00 | $22.00 | $9.00 | $24.20 |
| 7 | 221(K) 0600 | TEMPORARY FIBER LOG | 1,015 | LF | $4.00 | $4.25 | $2.25 | $4.67 |
| 8 | 230(A) 2806 | SOLID SLAB SODDING | 4,066 | SY | $3.00 | $2.48 | $2.75 | $2.72 |
| 9 | 233(A) 2817 | VEGETATIVE MULCHING | 1.68 | AC | $500.00 | $1,500.00 | $200.00 | $1,650.00 |
| 10 | 501(G) 6315 | CLSM BACKFILL | 246 | CY | $200.00 | $200.46 | $214.00 | $230.00 |
| 11 | 509(A) 0319 | CLASS AA CONCRETE | 125.6 | CY | $600.00 | $653.92 | $684.00 | $700.00 |
| 12 | 511(A) 0332 | REINFORCING STEEL | 13,720 | LB | $1.00 | $0.9000 | $0.8000 | $1.62 |
| 13 | 601(B) 0536 | TYPE I-A PLAIN RIPRAP | 411 | TON | $55.00 | $75.00 | $64.00 | $66.60 |
| 14 | 601(C) 0538 | TYPE I-A FILTER BLANKET | 131 | TON | $45.00 | $65.00 | $53.00 | $58.87 |
| 15 | 613(A) 0500 | 72" R.C.PIPE CLASS III | 360 | LF | $350.00 | $219.89 | $345.00 | $400.00 |
| 16 | 619(A) 0920 | REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM | $12,000.00 | $15,000.00 | $10,100.00 | $3,300.00 |
| 17 | 624(C) 4459 | FENCE-STYLE SWF (5 BARBED WIRE) | 816 | LF | $10.00 | $10.00 | $3.65 | $6.76 |
| 18 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $5,000.00 | $2,750.00 | $2,750.00 | $3,025.00 |
| 19 | 642(B) 0096 | CONSTRUCTION STAKING LEVEL II | 1 | LSUM | $3,500.00 | $10,000.00 | $2,300.00 | $6,050.00 |
| 20 | 641 1552 | MOBILIZATION | 1 | LSUM | $35,000.00 | $41,435.25 | $67,600.00 | $49,000.00 |