| 1 | 202(D) 0184 |
UNCLASSIFIED BORROW | 21,787 | CY |
$8.00 |
$6.00 |
$15.50 |
$15.28 |
| 2 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$75,000.00 |
$35,000.00 |
$21,000.00 |
$20,505.39 |
| 3 | 210 0121 |
OBLITERATING ABANDONED ROAD | 2,550 | LF |
$5.00 |
$4.00 |
$6.50 |
$6.28 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,910 | LF |
$1.50 |
$1.50 |
$1.25 |
$2.00 |
| 5 | 221(F) 0100 |
TEMPORARY SILT DIKE | 520 | LF |
$7.00 |
$8.50 |
$8.00 |
$9.00 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 38,000 | SY |
$1.70 |
$1.35 |
$1.25 |
$2.25 |
| 7 | 233(A) 2817 |
VEGETATIVE MULCHING | 7.85 | AC |
$500.00 |
$515.00 |
$475.00 |
$400.00 |
| 8 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 1,347 | CY |
$45.00 |
$84.00 |
$60.00 |
$14.00 |
| 9 | 311(A) 0151 |
PROCESSING EXISTING BASE & SURFACE, METHOD A | 2,550 | LF |
$2.00 |
$4.00 |
$6.50 |
$15.00 |
| 10 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 867 | TON |
$100.00 |
$126.00 |
$98.00 |
$98.00 |
| 11 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 857 | TON |
$100.00 |
$129.00 |
$100.00 |
$100.00 |
| 12 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$300.00 |
$300.00 |
$450.00 |
$350.00 |
| 13 | 601(B) 0536 |
TYPE I-A PLAIN RIPRAP | 564 | TON |
$49.00 |
$47.00 |
$55.00 |
$47.50 |
| 14 | 601(C) 0538 |
TYPE I-A FILTER BLANKET | 282 | TON |
$40.00 |
$40.00 |
$45.00 |
$42.00 |
| 15 | 619(C) 0924 |
SAWING PAVEMENT | 44 | LF |
$6.50 |
$6.00 |
$15.00 |
$8.00 |
| 16 | 854(A) 8800 |
TRAFFIC STRIPE(PAINT)(4" WIDE) | 6,300 | LF |
$0.5000 |
$0.3000 |
$0.2800 |
$0.2800 |
| 17 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 210 | CY |
$20.00 |
$15.00 |
$15.00 |
$12.50 |
| 18 | 501(G) 6315 |
CLSM BACKFILL | 108 | CY |
$125.00 |
$120.00 |
$75.00 |
$133.24 |
| 19 | 503(A) 1313 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 3,189.36 | LF |
$225.00 |
$195.00 |
$235.00 |
$225.00 |
| 20 | 504(B) 1305 |
SAW-CUT GROOVING | 2,447 | SY |
$3.50 |
$4.00 |
$5.00 |
$3.60 |
| 21 | 504(C) 6250 |
SEALED EXPANSION JOINT | 140.68 | LF |
$250.00 |
$260.00 |
$275.00 |
$195.00 |
| 22 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 1,666.4 | LF |
$70.00 |
$65.00 |
$65.00 |
$65.00 |
| 23 | 506(A) 1322 |
STRUCTURAL STEEL | 3,220 | LB |
$2.50 |
$4.00 |
$3.50 |
$2.65 |
| 24 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 32 | EA |
$900.00 |
$500.00 |
$600.00 |
$850.00 |
| 25 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 32 | EA |
$900.00 |
$500.00 |
$650.00 |
$850.00 |
| 26 | 509(A) 1326 |
CLASS AA CONCRETE | 781 | CY |
$500.00 |
$500.00 |
$375.00 |
$525.00 |
| 27 | 509(B) 1328 |
CLASS A CONCRETE | 238 | CY |
$525.00 |
$600.00 |
$500.00 |
$485.00 |
| 28 | 511(A) 1332 |
REINFORCING STEEL | 202,260 | LB |
$0.9000 |
$0.9000 |
$0.9500 |
$0.8000 |
| 29 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 280 | LF |
$30.00 |
$30.00 |
$30.00 |
$25.30 |
| 30 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 1,120 | LF |
$35.00 |
$35.00 |
$37.00 |
$32.40 |
| 31 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 280 | LF |
$10.00 |
$15.00 |
$12.50 |
$8.00 |
| 32 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 1,120 | LF |
$10.00 |
$20.35 |
$12.50 |
$10.00 |
| 33 | 516(A) 6096 |
DRILLED SHAFTS 60" DIAMETER | 1,036 | LF |
$800.00 |
$630.00 |
$600.00 |
$610.00 |
| 34 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 1,612 | TON |
$49.00 |
$47.00 |
$55.00 |
$45.00 |
| 35 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 505 | TON |
$40.00 |
$40.00 |
$45.00 |
$42.00 |
| 36 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 64 | LF |
$30.00 |
$25.00 |
$15.00 |
$20.60 |
| 37 | 613(I) 1096 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 22 | LF |
$25.00 |
$25.00 |
$15.00 |
$29.40 |
| 38 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$15,000.00 |
$20,000.00 |
$40,000.00 |
$38,560.02 |
| 39 | 623(F) 6033 |
GUARDRAIL ANCHOR UNIT (TYPE II) | 4 | EA |
$2,200.00 |
$2,195.00 |
$1,995.00 |
$1,995.00 |
| 40 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$5,000.00 |
$5,150.00 |
$4,375.00 |
$5,500.00 |
| 41 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$25,000.00 |
$17,000.00 |
$15,250.00 |
$18,000.00 |
| 42 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$7,500.00 |
$3,000.00 |
$2,800.00 |
$10,000.00 |
| 43 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$95,000.00 |
$90,000.00 |
$175,000.00 |
$150,000.00 |