Bid tab 120253

Let Jul 19, 2012 · Division 5 · Harmon Sign up free

‹ Jul 2012 results

BRIDGE AND APPROACHES COUNTY ROAD : OVER THE RED RIVER 8.0 MILES SOUTH AND 3.0 MILES WEST OF HOLLIS . PROJECT LENGTH = 0.937 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .

Let date
Thursday, July 19, 2012
Contract
120253
J/P numbers
24949(04)
District
Division 5
County
Harmon
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD : OVER THE RED RIVER 8.0 MILES SOUTH AND 3.0 MILES WEST OF HOLLIS . PROJECT LENGTH = 0.937 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .
Project number
CIRB-129C(039)RB

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$5,967,102
1 EARTH BUILDERS, L.P. Low bidder $7,176,530 +20.3%
2 JENSEN CONSTRUCTION COMPANY $7,306,725 +22.5% +1.8%
3 A. M. COHRON & SON, INC. $7,511,165 +25.9% +4.7%
4 OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV) $9,545,113 +60.0% +33.0%

Bid tab: unit prices 53 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 EARTH BUILDERS,…#2 JENSEN CONSTRUC…#3 A. M. COHRON & …#4 OBC, INC./PLAIN…
1202(A) 0183 UNCLASSIFIED EXCAVATION1,572CY $8.00 $10.00 $13.85 $10.00 $12.50
2202(D) 0184 UNCLASSIFIED BORROW1,000CY $8.00 $10.00 $11.90 $14.00 $15.16
3202(H) 0185 EARTHWORK1LSUM $75,000.00 $350,000.00 $274,000.00 $358,122.00 $712,500.00
4221(C) 2801 TEMPORARY SILT FENCE4,450LF $1.75 $2.00 $1.78 $2.00 $3.48
5232(B) 2814 SEEDING METHOD B9.9AC $700.00 $1,000.00 $788.00 $788.00 $2,000.00
6233(A) 2817 VEGETATIVE MULCHING9.9AC $600.00 $1,000.00 $788.00 $788.00 $2,000.00
7303(A) 2100 AGGREGATE BASE TYPE A1,750CY $40.00 $65.00 $67.00 $39.27 $51.62
8311(A) 0151 PROCESSING EXISTING BASE & SURFACE, METHOD A1,146.84LF $5.00 $20.00 $13.00 $5.77 $10.94
9402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E104TON $26.00 $40.00 $32.60 $38.50 $35.00
10411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)1,100TON $80.00 $110.00 $97.01 $85.00 $121.26
11411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)1,100TON $80.00 $110.00 $96.81 $99.00 $121.01
12509(D) 0325 CLASS C CONCRETE10CY $350.00 $350.00 $500.00 $325.00 $645.91
13613(B) 0689 18" CORR. GALV. STEEL PIPE85LF $25.00 $65.00 $29.50 $28.50 $15.31
14624(B) 4466 GATES-STYLE WWF (4.5'HIGH X 16'LONG)4EA $100.00 $750.00 $150.00 $690.00 $862.50
15624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)7,244LF $3.50 $5.00 $4.00 $3.52 $4.40
16877(A) 8483 PORTABLE LONGITUDINAL BARRIER212.5LF $35.00 $45.00 $44.00 $52.00 $35.00
17202(D) 0184 UNCLASSIFIED BORROW5,982CY $20.00 $10.00 $20.00 $17.38 $38.27
18601(A) 1351 TYPE I PLAIN RIPRAP1,197TON $35.00 $45.00 $30.00 $45.00 $81.85
19613(B) 4534 71" X 47" CORR. GALV. STEEL PIPE ARCH308LF $50.00 $100.00 $80.00 $95.75 $236.17
20501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON240CY $10.00 $12.00 $15.00 $17.54 $26.00
21501(F) 6352 GRANULAR BACKFILL148CY $55.00 $70.00 $50.00 $54.25 $125.44
22503(A) 6290 PRESTRESSED CONCRETE BEAMS (TYPE J BT)5,786.7LF $275.00 $220.00 $250.00 $262.50 $281.71
23503(C) 6175 PRESTRESSED CONCRETE DECK PANELS28,320SF $9.00 $10.00 $10.00 $16.37 $13.60
24504 6176 INSERTS644EA $35.00 $22.00 $15.00 $17.55 $45.31
25504(B) 1305 SAW-CUT GROOVING4,490SY $5.00 $5.00 $5.00 $4.00 $5.20
26504(C) 6250 SEALED EXPANSION JOINT175.85LF $250.00 $200.00 $200.00 $230.07 $495.37
27504(D) 6239 CONCRETE RAIL (TR3)2,977.2LF $65.00 $70.00 $100.00 $74.15 $94.29
28506(A) 1322 STRUCTURAL STEEL10,060LB $2.50 $3.50 $2.75 $1.60 $4.00
29507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY40EA $850.00 $1,500.00 $2,000.00 $1,262.00 $1,539.13
30507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY40EA $850.00 $1,500.00 $2,000.00 $1,262.00 $1,539.13
31509(A) 1326 CLASS AA CONCRETE1,172CY $500.00 $650.00 $550.00 $685.00 $677.55
32509(B) 1328 CLASS A CONCRETE451.5CY $525.00 $550.00 $750.00 $645.00 $792.47
33511(A) 1332 REINFORCING STEEL290,010LB $0.8500 $1.20 $1.00 $1.06 $1.04
34514(A) 6010 PILES, FURNISHED (HP 10X42)260LF $32.00 $30.00 $23.00 $25.14 $56.77
35514(A) 6011 PILES, FURNISHED (HP 12X53)1,440LF $45.00 $32.00 $25.00 $46.42 $59.89
36514(B) 6292 PILES, DRIVEN (HP 10X42)260LF $12.00 $35.00 $10.00 $4.66 $10.40
37514(B) 6294 PILES, DRIVEN (HP 12X53)1,440LF $12.00 $35.00 $12.00 $6.16 $10.40
38516 6200 (SP)CLASS T CONCRETE350CY $200.00 $500.00 $250.00 $348.82 $397.90
39516(A) 6098 DRILLED SHAFTS 72" DIAMETER1,515LF $1,000.00 $1,100.00 $1,220.00 $1,197.26 $1,578.41
40516(A) 6200 (SP)RE-DRILL GROUTED SHAFTS450LF $200.00 $250.00 $100.00 $399.61 $130.00
41516(C) 6200 CROSSHOLE SONIC LOGGING18EA $1,500.00 $1,000.00 $3,000.00 $471.00 $1,755.00
42516(D) 6400 CSL ACCESS TUBES11,186LF $5.00 $8.00 $10.00 $7.59 $7.36
43601(B) 1353 TYPE I-A PLAIN RIPRAP500TON $35.00 $50.00 $40.00 $45.00 $50.23
44601(C) 1355 TYPE I-A FILTER BLANKET500TON $25.00 $40.00 $30.00 $38.28 $45.81
45613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND64LF $20.00 $15.00 $20.00 $26.19 $60.61
46613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.26LF $20.00 $15.00 $20.00 $39.08 $32.92
47619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $100,000.00 $175,000.00 $75,000.00 $51,028.00 $304,200.00
48623(F) 6033 GUARDRAIL ANCHOR UNIT (TYPE II)4EA $2,000.00 $2,300.00 $2,440.00 $2,600.00 $3,380.00
49880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $10,000.00 $10,000.00 $13,300.00 $5,850.00 $7,605.00
50642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $10,000.00 $35,000.00 $100,000.00 $20,185.61 $35,250.00
51220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $7,500.00 $3,500.00 $10,000.00 $18,750.00 $4,812.50
52640(A) 1398 FIELD OFFICE1EA $10,000.00 $20,000.00 $30,000.00 $9,000.00 $23,125.00
53641 1399 MOBILIZATION1LSUM $50,000.00 $350,000.00 $350,000.00 $328,793.62 $579,250.00