$227.72Avg low bid / LF
$245.18Avg of all bids
$212.78Avg engineer's estimate
23Jobs · 2,997 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 4 | 1,027 | $229.33 | $260.84 |
| 2020 | 10 | 923 | $227.36 | $238.29 |
| 2019 | 6 | 825 | $233.30 | $245.78 |
| 2018 | 3 | 222 | $200.99 | $211.46 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 19, 2021 | 210149 | Nhpp-260n(054)pm | 306 LF | $315.37 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 368 LF | $193.65 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210127 | BlaineDivision 5 | 115 LF | $164.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210136 | HughesDivision 3 | 162 LF | $181.00 | C-GAWF CONSTRUCTION, INC. |
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 76 LF | $257.50 | THE CUMMINS CONSTRUCTION CO., INC. |
| Nov 19, 2020 | 200355 | RogersDivision 8 | 136 LF | $326.00 | EMERY SAPP & SONS, INC. |
| Oct 15, 2020 | 200309 | GarfieldDivision 4 | 184 LF | $214.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Aug 20, 2020 | 200225 | GradyDivision 7 | 90 LF | $190.00 | SEWELL BROS., INC. |
| Jul 23, 2020 | 200251 | HarmonDivision 5 | 55 LF | $262.50 | Frontier Bridge, Inc. |
| Apr 16, 2020 | 200028 | Cirb-264d(069)rb | 168 LF | $151.55 | THE CUMMINS CONSTRUCTION CO., INC. |
| Mar 19, 2020 | 200110 | McintoshDivision 1 | 116 LF | $215.00 | Robinson Construction, LLC |
| Mar 19, 2020 | 200133 | HaskellDivision 1 | 39 LF | $227.26 | C3 Construction, Inc. |
| Jan 16, 2020 | 200092 | TulsaDivision 8 | 16 LF | $265.00 | APAC-CENTRAL, INC. |
| Jan 16, 2020 | 200001 | AlfalfaDivision 6 | 73 LF | $288.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 16, 2020 | 200020 | NobleDivision 4 | 46 LF | $219.05 | Evans & Associates Construction Co., Inc. |
| Oct 17, 2019 | 190335 | TulsaDivision 8 | 24 LF | $247.50 | Tri Star Construction Arkansas, LLC |
| Jul 25, 2019 | 190145 | BryanDivision 2 | 331 LF | $207.92 | DUIT CONSTRUCTION COMPANY, INC. |
| May 16, 2019 | 180277 | BlaineDivision 5 | 128 LF | $186.00 | HASKELL LEMON CONSTRUCTION CO. |
| Feb 14, 2019 | 190097 | Nhpp-008n(090)fp | 100 LF | $150.00 | J & R SAND COMPANY, INC. |
| Jan 17, 2019 | 190001 | AtokaDivision 2 | 42 LF | $212.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 17, 2019 | 190034 | CimarronDivision 6 | 200 LF | $350.00 | J & R SAND COMPANY, INC. |
| Jun 14, 2018 | 180225 | Stp-231c(033)ci | 100 LF | $210.00 | T. McDonald Construction, Inc. |
| Apr 19, 2018 | 180168 | LoganDivision 4 | 72 LF | $210.00 | K & R BUILDERS, INC. |
| Jan 18, 2018 | 180030 | RogersDivision 8 | 50 LF | $170.00 | BECCO CONTRACTORS, INC. |