16-00103-00-RS
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Iroquois Paving Corporation Low bidder | $1,016,064 | ||
| 2 | Gallagher Asphalt Corporation | $1,027,346 | +1.1% | |
| 3 | D. Construction, Inc. | $1,053,757 | +3.7% | |
| 4 | P. T. Ferro Construction Co. | $1,081,166 | +6.4% | |
| 5 | K-Five Construction Corporation | $1,098,138 | +8.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Iroquois Paving… | #2 Gallagher Aspha… | #3 D. Construction… | #4 P. T. Ferro Con… | #5 K-Five Construc… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | XX006821 | CONC TRUCK WASHOUT | 1 | L SUM | $2,000.00 | $1,015.00 | $1,100.00 | $500.00 | $500.00 | |
| 2 | XX007278 | PARKWAY RESTORATION | 4,775 | SQ YD | $0.0100 | $13.00 | $12.76 | $15.00 | $14.25 | |
| 3 | X0327980 | PAVMT MRKG REM WTR BL | 61 | SQ FT | $40.00 | $40.00 | $44.00 | $40.00 | $10.00 | |
| 4 | X2800510 | INLET FILTER CLEANING | 56 | EACH | $40.00 | $85.00 | $50.00 | $0.0100 | $20.00 | |
| 5 | X4021000 | TEMP ACCESS- PRIV ENT | 57 | EACH | $70.00 | $0.0100 | $22.00 | $0.0100 | $95.00 | |
| 6 | X4022000 | TEMP ACCESS- COM ENT | 6 | EACH | $224.00 | $0.0100 | $22.00 | $0.0100 | $250.00 | |
| 7 | X4023000 | TEMP ACCESS- ROAD | 11 | EACH | $140.00 | $0.0100 | $44.00 | $0.0100 | $250.00 | |
| 8 | X6026056 | SAN MH ADJ NEW T1F CL | 14 | EACH | $925.00 | $865.00 | $900.00 | $1,500.00 | $1,360.00 | |
| 9 | X6026057 | SAN MH REC NEW T1F CL | 2 | EACH | $1,385.00 | $2,020.00 | $1,500.00 | $2,000.00 | $1,625.00 | |
| 10 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $13,400.00 | $9,700.00 | $12,000.00 | $15,000.00 | $8,000.00 | |
| 11 | Z0019600 | DUST CONTROL WATERING | 20 | UNIT | $50.00 | $50.00 | $50.00 | $0.0100 | $88.70 | |
| 12 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $18.00 | $18.00 | $25.00 | $18.00 | $18.00 | |
| 13 | 20101100 | TREE TRUNK PROTECTION | 72 | EACH | $100.00 | $100.00 | $110.00 | $100.00 | $100.00 | |
| 14 | 20101200 | TREE ROOT PRUNING | 72 | EACH | $110.00 | $110.00 | $121.00 | $110.00 | $110.00 | |
| 15 | 20101300 | TREE PRUN 1-10 | 5 | EACH | $10.00 | $100.00 | $110.00 | $100.00 | $100.00 | |
| 16 | 20101350 | TREE PRUN OVER 10 | 5 | EACH | $125.00 | $125.00 | $137.50 | $125.00 | $125.00 | |
| 17 | 20200100 | EARTH EXCAVATION | 293 | CU YD | $50.00 | $55.85 | $55.00 | $50.00 | $35.00 | |
| 18 | 20201200 | REM & DISP UNS MATL | 1,425 | CU YD | $25.00 | $1.00 | $32.00 | $25.00 | $39.00 | |
| 19 | 21001000 | GEOTECH FAB F/GR STAB | 4,389 | SQ YD | $1.15 | $0.0100 | $2.00 | $2.00 | $1.35 | |
| 20 | 25200200 | SUPPLE WATERING | 73 | UNIT | $0.0100 | $50.00 | $0.0100 | $0.0100 | $10.00 | |
| 21 | 28000510 | INLET FILTERS | 28 | EACH | $175.00 | $200.00 | $125.00 | $0.0100 | $150.00 | |
| 22 | 30300001 | AGG SUBGRADE IMPROVE | 1,393 | CU YD | $39.50 | $1.00 | $40.00 | $35.00 | $32.00 | |
| 23 | 35101600 | AGG BASE CSE B 4 | 2,100 | SQ YD | $7.00 | $4.60 | $4.95 | $6.00 | $5.00 | |
| 24 | 35800100 | PREPARATION OF BASE | 13,925 | SQ YD | $0.0100 | $1.40 | $1.00 | $1.50 | $1.30 | |
| 25 | 35800200 | AGG BASE REPAIR | 1,129 | TON | $0.0100 | $8.00 | $20.00 | $14.00 | $12.75 | |
| 26 | 40600290 | BIT MATLS TACK CT | 3,150 | POUND | $0.0100 | $0.9000 | $0.0100 | $0.0100 | $0.0100 | |
| 27 | 40603080 | HMA BC IL-19.0 N50 | 1,950 | TON | $67.00 | $70.00 | $62.00 | $66.00 | $69.00 | |
| 28 | 40603335 | HMA SC "D" N50 | 1,561 | TON | $70.00 | $80.00 | $63.00 | $72.00 | $72.00 | |
| 29 | 42001300 | PROTECTIVE COAT | 3,685 | SQ YD | $0.0100 | $1.02 | $1.10 | $0.5000 | $0.0100 | |
| 30 | 42300200 | PCC DRIVEWAY PAVT 6 | 1,500 | SQ YD | $56.00 | $65.00 | $69.30 | $59.00 | $56.00 | |
| 31 | 42300400 | PCC DRIVEWAY PAVT 8 | 267 | SQ YD | $54.00 | $73.10 | $79.20 | $62.00 | $62.00 | |
| 32 | 42400200 | PC CONC SIDEWALK 5 | 2,900 | SQ FT | $6.35 | $6.60 | $7.15 | $7.50 | $6.00 | |
| 33 | 42400800 | DETECTABLE WARNINGS | 430 | SQ FT | $32.00 | $22.35 | $24.20 | $32.00 | $20.00 | |
| 34 | 44000100 | PAVEMENT REM | 13,925 | SQ YD | $4.25 | $4.25 | $3.25 | $4.00 | $3.65 | |
| 35 | 44000200 | DRIVE PAVEMENT REM | 1,495 | SQ YD | $15.00 | $15.25 | $8.00 | $25.00 | $15.00 | |
| 36 | 44000500 | COMB CURB GUTTER REM | 7,176 | FOOT | $7.00 | $7.12 | $7.70 | $7.00 | $8.00 | |
| 37 | 44000600 | SIDEWALK REM | 3,410 | SQ FT | $2.00 | $2.05 | $2.20 | $2.00 | $2.00 | |
| 38 | 60204505 | CB TA 5 DIA T8G | 2 | EACH | $2,000.00 | $3,950.00 | $3,000.00 | $3,500.00 | $3,800.00 | |
| 39 | 60238800 | INLETS TA | 15 | EACH | $725.00 | $1,350.00 | $2,000.00 | $950.00 | $1,880.00 | |
| 40 | 60255500 | MAN ADJUST | 2 | EACH | $350.00 | $465.00 | $600.00 | $400.00 | $780.00 | |
| 41 | 60255800 | MAN ADJ NEW T1F CL | 2 | EACH | $550.00 | $805.00 | $900.00 | $700.00 | $1,100.00 | |
| 42 | 60257900 | MAN RECONST | 2 | EACH | $875.00 | $1,185.00 | $900.00 | $600.00 | $1,350.00 | |
| 43 | 60258200 | MAN RECON NEW T1F CL | 3 | EACH | $1,085.00 | $1,380.00 | $1,100.00 | $800.00 | $1,600.00 | |
| 44 | 60260100 | INLETS ADJUST | 8 | EACH | $350.00 | $365.00 | $600.00 | $500.00 | $685.00 | |
| 45 | 60406400 | FR & LIDS T15 | 5 | EACH | $300.00 | $340.00 | $350.00 | $400.00 | $545.00 | |
| 46 | 60500060 | REMOV INLETS | 15 | EACH | $175.00 | $350.00 | $400.00 | $200.00 | $25.00 | |
| 47 | 60608562 | COMB CC&G TM4.12 | 7,176 | FOOT | $26.50 | $20.30 | $21.45 | $20.00 | $22.50 | |
| 48 | 67100100 | MOBILIZATION | 1 | L SUM | $60,000.00 | $49,000.00 | $25,000.00 | $64,000.00 | $62,100.00 | |
| 49 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $31,100.00 | $45,000.00 | $0.0100 | $9,000.00 | $6,100.00 | |
| 50 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $100.00 | $18,765.00 | $100.00 | $100.00 | |
| 51 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $100.00 | $100.00 | $0.0100 | $100.00 | $100.00 | |
| 52 | 70300100 | SHORT TERM PAVT MKING | 572 | FOOT | $0.6000 | $0.0100 | $0.0100 | $0.0100 | $1.00 | |
| 53 | 70300150 | SHRT TRM PAVT MK REM | 190 | SQ FT | $1.35 | $0.0100 | $0.0100 | $0.0100 | $1.00 | |
| 54 | 72400100 | REMOV SIN PAN ASSY TA | 2 | EACH | $75.00 | $75.00 | $50.00 | $75.00 | $75.00 | |
| 55 | 78000100 | THPL PVT MK LTR & SYM | 33 | SQ FT | $5.00 | $5.00 | $5.50 | $5.00 | $7.00 | |
| 56 | 78000200 | THPL PVT MK LINE 4 | 794 | FOOT | $0.4000 | $0.4000 | $0.4400 | $0.8500 | $1.10 | |
| 57 | 78000400 | THPL PVT MK LINE 6 | 1,402 | FOOT | $1.50 | $1.50 | $1.65 | $1.28 | $1.75 | |
| 58 | 78000600 | THPL PVT MK LINE 12 | 504 | FOOT | $2.25 | $2.25 | $2.48 | $2.70 | $3.50 | |
| 59 | 78000650 | THPL PVT MK LINE 24 | 91 | FOOT | $5.00 | $5.00 | $5.50 | $5.00 | $7.00 | |
| 60 | 88600100 | DET LOOP T1 | 61 | FOOT | $21.00 | $21.00 | $23.10 | $21.00 | $21.00 |