$6,027.62Avg low bid / EACH
$6,657.89Avg of all bids
—Avg engineer's estimate
5Jobs · 21 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 1 | 2 | $4,500.00 | $4,855.00 |
| 2025 | 4 | 19 | $6,188.42 | $6,772.97 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 16, 2026 | 61M01 | WillDistrict 1 | 2 EACH | $4,500.00 | Austin Tyler Construction, Inc. |
| Sep 19, 2025 | 62R22 | WillDistrict 1 | 5 EACH | $5,300.00 | D. Construction, Inc. |
| Aug 1, 2025 | 61L38 | CookDistrict 1 | 3 EACH | $5,000.00 | Plote Construction, Inc. |
| Aug 1, 2025 | 64C24 | WinnebagoDistrict 2 | 10 EACH | $7,200.00 | OHLA Central, Inc. |
| Mar 7, 2025 | 61J84 | KaneDistrict 1 | 1 EACH | $4,080.00 | R. W. Dunteman Company |