| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$13,274.72 |
$7,250.00 |
$5,200.00 |
$8,000.00 |
$10,000.00 |
$8,500.00 |
$4,948.95 |
| 2 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$42,188.64 |
$25,500.00 |
$32,500.00 |
$18,000.00 |
$21,000.00 |
$30,000.00 |
$10,604.89 |
| 3 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,062 | LF |
$1.87 |
$2.45 |
$4.00 |
$2.00 |
$1.70 |
$2.28 |
$3.22 |
| 4 | 221(F) 0100 |
TEMPORARY SILT DIKE | 48 | LF |
$11.18 |
$13.90 |
$10.00 |
$4.00 |
$11.00 |
$13.44 |
$19.00 |
| 5 | 230(A) 2806 |
SOLID SLAB SODDING | 728.9 | SY |
$3.85 |
$9.50 |
$3.00 |
$3.50 |
$11.00 |
$8.22 |
$11.62 |
| 6 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 330.3 | CY |
$57.40 |
$50.90 |
$60.56 |
$55.00 |
$60.00 |
$65.00 |
$21.42 |
| 7 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 100 | TON |
$39.38 |
$29.75 |
$38.00 |
$22.00 |
$30.50 |
$42.00 |
$21.42 |
| 8 | 407(B) 0250 |
TACK COAT | 176.5 | GAL |
$5.39 |
$3.95 |
$4.38 |
$3.65 |
$4.00 |
$3.50 |
$5.16 |
| 9 | 408 5774 |
PRIME COAT | 741.1 | GAL |
$6.36 |
$5.15 |
$5.88 |
$4.90 |
$5.50 |
$6.00 |
$6.93 |
| 10 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 296.5 | TON |
$108.73 |
$98.65 |
$100.00 |
$89.40 |
$104.50 |
$84.00 |
$126.41 |
| 11 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 197.7 | TON |
$133.18 |
$112.10 |
$115.00 |
$102.10 |
$119.00 |
$100.00 |
$144.37 |
| 12 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 100 | LF |
$20.77 |
$22.80 |
$22.00 |
$20.00 |
$18.00 |
$20.00 |
$23.19 |
| 13 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$1,777.78 |
$1,500.00 |
$1,320.00 |
$1,100.00 |
$1,860.00 |
$1,100.00 |
$2,403.78 |
| 14 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 4 | EA |
$2,403.99 |
$2,950.00 |
$2,500.00 |
$2,500.00 |
$1,930.00 |
$2,500.00 |
$2,474.48 |
| 15 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 180 | CY |
$22.38 |
$12.00 |
$14.70 |
$10.00 |
$12.50 |
$25.00 |
$11.31 |
| 16 | 501(G) 6309 |
CLSM BACKFILL | 93.5 | CY |
$164.56 |
$152.82 |
$141.00 |
$150.00 |
$167.50 |
$165.00 |
$295.52 |
| 17 | 503(A) 1311 |
PRESTRESSED CONCRETE BEAMS (TYPE II) | 179 | LF |
$210.43 |
$215.23 |
$220.00 |
$285.00 |
$215.00 |
$240.00 |
$244.62 |
| 18 | 504(A) 1304 |
APPROACH SLAB | 114.8 | SY |
$198.59 |
$197.29 |
$183.00 |
$200.00 |
$205.00 |
$200.00 |
$287.39 |
| 19 | 504(B) 1305 |
SAW-CUT GROOVING | 239.96 | SY |
$7.69 |
$12.27 |
$12.00 |
$11.80 |
$16.50 |
$15.00 |
$21.21 |
| 20 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 176 | LF |
$96.62 |
$78.00 |
$90.00 |
$85.00 |
$94.00 |
$110.00 |
$102.73 |
| 21 | 506(A) 1322 |
STRUCTURAL STEEL | 1,400 | LB |
$2.45 |
$2.90 |
$1.50 |
$2.00 |
$1.65 |
$2.50 |
$3.39 |
| 22 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 3 | EA |
$983.10 |
$600.00 |
$550.00 |
$500.00 |
$750.00 |
$900.00 |
$661.35 |
| 23 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 3 | EA |
$1,061.20 |
$600.00 |
$550.00 |
$500.00 |
$750.00 |
$900.00 |
$661.35 |
| 24 | 509(A) 1326 |
CLASS AA CONCRETE | 48.5 | CY |
$893.73 |
$525.00 |
$580.00 |
$850.00 |
$742.50 |
$1,050.00 |
$1,040.69 |
| 25 | 509(B) 1328 |
CLASS A CONCRETE | 60.4 | CY |
$710.76 |
$550.00 |
$525.00 |
$800.00 |
$720.00 |
$800.00 |
$463.79 |
| 26 | 509(D) 1331 |
CLASS C CONCRETE | 20 | CY |
$515.54 |
$350.00 |
$195.00 |
$225.00 |
$300.00 |
$375.00 |
$281.38 |
| 27 | 511(A) 1332 |
REINFORCING STEEL | 20,160 | LB |
$1.03 |
$1.10 |
$1.00 |
$0.7500 |
$0.8600 |
$1.05 |
$1.19 |
| 28 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 106.96 | LF |
$38.17 |
$28.12 |
$34.45 |
$30.00 |
$35.00 |
$40.00 |
$28.28 |
| 29 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 234.64 | LF |
$41.94 |
$30.41 |
$42.14 |
$35.00 |
$45.50 |
$50.00 |
$35.35 |
| 30 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 106.96 | LF |
$14.23 |
$15.00 |
$14.96 |
$13.00 |
$15.00 |
$20.00 |
$39.59 |
| 31 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 234.64 | LF |
$12.67 |
$12.00 |
$14.70 |
$15.00 |
$19.50 |
$20.00 |
$39.59 |
| 32 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 33 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 374 | TON |
$46.40 |
$45.60 |
$38.47 |
$32.00 |
$46.50 |
$60.00 |
$43.48 |
| 34 | 601(I) 6312 |
FILTER FABRIC (RIPRAP) | 461 | SY |
$2.64 |
$2.75 |
$3.00 |
$1.05 |
$5.90 |
$1.50 |
$42.07 |
| 35 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$20,412.42 |
$7,500.00 |
$6,800.00 |
$8,500.00 |
$11,000.00 |
$10,000.00 |
$21,916.78 |
| 36 | 854(A) 8800 |
TRAFFIC STRIPE(PAINT)(4" WIDE) | 2,776.2 | LF |
$0.5300 |
$0.7100 |
$0.6600 |
$0.5500 |
$0.6700 |
$0.5500 |
$0.8500 |
| 37 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$3,350.19 |
$3,750.00 |
$3,900.00 |
$3,250.00 |
$4,600.00 |
$3,250.00 |
$4,185.40 |
| 38 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$11,529.91 |
$7,250.00 |
$8,000.00 |
$4,000.00 |
$8,400.00 |
$6,500.00 |
$10,746.29 |
| 39 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$65,124.58 |
$32,000.00 |
$34,000.00 |
$40,000.00 |
$37,000.00 |
$50,000.00 |
$46,223.19 |