| 1 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$12,000.00 |
$21,300.00 |
$17,000.00 |
$38,150.00 |
$24,300.64 |
$45,000.00 |
| 2 | 221(C) 2801 |
TEMPORARY SILT FENCE | 200 | LF |
$4.00 |
$2.50 |
$4.00 |
$2.50 |
$2.50 |
$3.00 |
| 3 | 221(F) 0100 |
TEMPORARY SILT DIKE | 100 | LF |
$3.00 |
$11.00 |
$10.00 |
$7.07 |
$8.00 |
$10.00 |
| 4 | 230(A) 2806 |
SOLID SLAB SODDING | 3,500 | SY |
$2.50 |
$3.00 |
$4.00 |
$2.10 |
$3.80 |
$5.00 |
| 5 | 232(A) 2813 |
SEEDING METHOD A | 0.1 | AC |
$500.00 |
$1,965.00 |
$6,700.00 |
$1,500.00 |
$8,800.00 |
$600.00 |
| 6 | 233(A) 2817 |
VEGETATIVE MULCHING | 0.1 | AC |
$450.00 |
$1,965.00 |
$6,700.00 |
$1,500.00 |
$5,750.00 |
$600.00 |
| 7 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 313.7 | CY |
$45.00 |
$49.75 |
$40.00 |
$55.00 |
$74.00 |
$49.50 |
| 8 | 325 5271 |
SEPARATOR FABRIC | 1,882.3 | SY |
$2.00 |
$1.50 |
$0.9500 |
$1.25 |
$1.35 |
$1.10 |
| 9 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 473.6 | TON |
$80.00 |
$105.00 |
$75.00 |
$70.00 |
$75.00 |
$80.00 |
| 10 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 220.8 | TON |
$100.00 |
$111.00 |
$80.00 |
$95.00 |
$100.00 |
$120.00 |
| 11 | 613(A) 0492 |
24" R.C.PIPE CLASS III | 7.5 | LF |
$80.00 |
$78.50 |
$60.00 |
$125.00 |
$141.00 |
$85.00 |
| 12 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 1,100 | SY |
$5.00 |
$5.00 |
$30.00 |
$5.00 |
$11.85 |
$7.50 |
| 13 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 1,969 | LF |
$1.00 |
$1.25 |
$5.00 |
$1.90 |
$1.25 |
$1.50 |
| 14 | 202(A) 1301 |
UNCLASSIFIED EXCAVATION | 428.5 | CY |
$10.00 |
$10.00 |
$25.00 |
$30.00 |
$48.00 |
$15.00 |
| 15 | 501(A) 1306 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 153.3 | CY |
$30.00 |
$23.50 |
$25.00 |
$75.00 |
$34.00 |
$20.00 |
| 16 | 501(G) 6309 |
CLSM BACKFILL | 37 | CY |
$105.00 |
$104.75 |
$130.00 |
$135.00 |
$114.00 |
$105.00 |
| 17 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 64 | LF |
$70.00 |
$80.00 |
$100.00 |
$90.00 |
$170.00 |
$250.00 |
| 18 | 509(B) 1328 |
CLASS A CONCRETE | 258.7 | CY |
$500.00 |
$450.00 |
$480.00 |
$585.00 |
$600.00 |
$755.00 |
| 19 | 511(A) 1332 |
REINFORCING STEEL | 40,098.6 | LB |
$1.20 |
$1.00 |
$0.9000 |
$0.9500 |
$0.7500 |
$1.10 |
| 20 | 525(C) 1000 |
(SP)NEST PREVENTION | 1 | LSUM |
$400.00 |
$750.00 |
$2,500.00 |
$1,250.00 |
$2,500.00 |
$500.00 |
| 21 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 56.2 | TON |
$35.00 |
$54.75 |
$85.00 |
$42.00 |
$80.00 |
$55.00 |
| 22 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 18.7 | TON |
$30.00 |
$37.50 |
$60.00 |
$40.00 |
$73.00 |
$35.00 |
| 23 | 601(I) 6312 |
FILTER FABRIC (RIPRAP) | 60 | SY |
$3.00 |
$37.50 |
$2.00 |
$12.50 |
$4.25 |
$1.50 |
| 24 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$10,000.00 |
$13,400.00 |
$23,000.00 |
$8,000.00 |
$20,000.00 |
$15,000.00 |
| 25 | 623(A) 1418 |
BEAM GUARDRAIL W-BEAM SINGLE | 187.5 | LF |
$22.00 |
$23.00 |
$100.00 |
$19.00 |
$21.50 |
$20.00 |
| 26 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 2 | EA |
$2,000.00 |
$1,637.50 |
$2,100.00 |
$1,500.00 |
$1,550.00 |
$2,000.00 |
| 27 | 623(F) 6033 |
GUARDRAIL ANCHOR UNIT (TYPE II) | 2 | EA |
$1,500.00 |
$2,815.50 |
$75.00 |
$2,300.00 |
$2,675.00 |
$2,500.00 |
| 28 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$2,500.00 |
$3,600.00 |
$4,100.00 |
$1,500.00 |
$3,400.00 |
$5,000.00 |
| 29 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$2,000.00 |
$3,471.00 |
$10,000.00 |
$3,652.00 |
$4,500.00 |
$5,000.00 |
| 30 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$1,310.00 |
$3,000.00 |
$500.00 |
$1,000.00 |
$3,500.00 |
| 31 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$30,000.00 |
$18,200.00 |
$20,000.00 |
$42,000.00 |
$20,500.20 |
$25,000.00 |