| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$20,000.00 |
$15,000.00 |
$10,000.00 |
$28,750.00 |
$15,000.00 |
| 2 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$30,000.00 |
$27,000.00 |
$25,000.00 |
$57,500.00 |
$18,000.00 |
| 3 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,000 | LF |
$2.25 |
$2.00 |
$4.00 |
$2.58 |
$3.85 |
| 4 | 221(F) 0100 |
TEMPORARY SILT DIKE | 200 | LF |
$6.00 |
$8.00 |
$8.00 |
$7.12 |
$10.30 |
| 5 | 230(A) 2806 |
SOLID SLAB SODDING | 1,500 | SY |
$2.85 |
$3.00 |
$3.00 |
$3.39 |
$5.05 |
| 6 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 400 | CY |
$50.00 |
$60.00 |
$65.00 |
$63.82 |
$142.00 |
| 7 | 408 5774 |
PRIME COAT | 800 | GAL |
$6.50 |
$5.00 |
$6.00 |
$6.22 |
$9.35 |
| 8 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 436 | TON |
$100.00 |
$101.00 |
$115.00 |
$117.15 |
$176.00 |
| 9 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 322 | TON |
$110.00 |
$110.00 |
$120.00 |
$128.13 |
$192.50 |
| 10 | 601(B) 0536 |
TYPE I-A PLAIN RIPRAP | 1,800 | TON |
$30.00 |
$50.00 |
$35.00 |
$48.20 |
$79.70 |
| 11 | 601(I) 6312 |
FILTER FABRIC (RIPRAP) | 1,500 | SY |
$2.25 |
$1.25 |
$2.00 |
$1.66 |
$2.55 |
| 12 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 50 | LF |
$18.00 |
$16.50 |
$30.00 |
$37.38 |
$34.80 |
| 13 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$1,400.00 |
$1,500.00 |
$2,400.00 |
$2,173.50 |
$2,440.00 |
| 14 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 4 | EA |
$2,200.00 |
$2,250.00 |
$2,500.00 |
$2,616.25 |
$3,830.00 |
| 15 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 2,908 | LF |
$1.05 |
$0.8800 |
$1.00 |
$0.9800 |
$1.45 |
| 16 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 168 | CY |
$15.00 |
$22.50 |
$15.00 |
$27.50 |
$30.70 |
| 17 | 501(G) 6309 |
CLSM BACKFILL | 90 | CY |
$170.00 |
$160.00 |
$150.00 |
$161.55 |
$215.00 |
| 18 | 504(A) 1304 |
APPROACH SLAB | 114.8 | SY |
$175.00 |
$185.00 |
$180.00 |
$158.59 |
$90.00 |
| 19 | 504(B) 1305 |
SAW-CUT GROOVING | 271.8 | SY |
$7.75 |
$17.00 |
$15.00 |
$11.00 |
$20.80 |
| 20 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 278.4 | LF |
$80.00 |
$65.00 |
$75.00 |
$80.02 |
$117.00 |
| 21 | 506(A) 1322 |
STRUCTURAL STEEL | 19,720 | LB |
$2.00 |
$2.50 |
$5.30 |
$6.01 |
$3.50 |
| 22 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 12 | EA |
$800.00 |
$900.00 |
$550.00 |
$1,542.09 |
$1,210.00 |
| 23 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 4 | EA |
$945.00 |
$900.00 |
$550.00 |
$1,542.09 |
$1,250.00 |
| 24 | 509(A) 1326 |
CLASS AA CONCRETE | 82 | CY |
$700.00 |
$600.00 |
$650.00 |
$710.44 |
$856.00 |
| 25 | 509(B) 1328 |
CLASS A CONCRETE | 84.1 | CY |
$700.00 |
$635.00 |
$600.00 |
$739.79 |
$774.00 |
| 26 | 511(A) 1332 |
REINFORCING STEEL | 31,573 | LB |
$1.25 |
$1.10 |
$0.9800 |
$1.11 |
$1.35 |
| 27 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 118.08 | LF |
$32.00 |
$39.00 |
$40.00 |
$39.31 |
$52.70 |
| 28 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 262.93 | LF |
$42.00 |
$48.00 |
$50.00 |
$47.17 |
$74.80 |
| 29 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 118.08 | LF |
$13.50 |
$11.00 |
$15.00 |
$8.80 |
$39.60 |
| 30 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 262.93 | LF |
$14.50 |
$11.00 |
$15.00 |
$8.80 |
$48.40 |
| 31 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 32 | 516(A) 6094 |
DRILLED SHAFTS 48" DIAMETER | 39.17 | LF |
$550.00 |
$2,400.00 |
$1,250.00 |
$1,322.18 |
$3,240.00 |
| 33 | 535 6225 |
HAUL AND ERECT STEEL BEAMS | 1 | LSUM |
$60,000.00 |
$55,000.00 |
$87,500.00 |
$138,009.30 |
$56,300.00 |
| 34 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 300 | TON |
$45.00 |
$50.00 |
$50.00 |
$46.10 |
$81.50 |
| 35 | 601(I) 6312 |
FILTER FABRIC (RIPRAP) | 350 | SY |
$3.25 |
$1.25 |
$2.00 |
$11.92 |
$2.55 |
| 36 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$25,000.00 |
$11,500.00 |
$10,000.00 |
$41,250.00 |
$19,000.00 |
| 37 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$4,000.00 |
$3,500.00 |
$50,000.00 |
$3,740.00 |
$7,000.00 |
| 38 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$15,000.00 |
$6,000.00 |
$5,000.00 |
$14,025.00 |
$26,000.00 |
| 39 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$3,500.00 |
$2,500.00 |
$3,000.00 |
$2,750.00 |
$17,000.00 |
| 40 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$30,000.00 |
$53,000.00 |
$20,000.00 |
$50,684.47 |
$50,000.00 |