| 1 | 202(D) 0184 |
UNCLASSIFIED BORROW | 2,237 | CY |
$8.00 |
$6.45 |
$10.00 |
$6.00 |
$10.00 |
| 2 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,500 | LF |
$2.00 |
$1.45 |
$1.40 |
$1.60 |
$1.40 |
| 3 | 221(F) 0100 |
TEMPORARY SILT DIKE | 1,162 | LF |
$8.25 |
$7.70 |
$8.00 |
$10.00 |
$8.00 |
| 4 | 230(A) 2806 |
SOLID SLAB SODDING | 27,488 | SY |
$2.00 |
$1.70 |
$1.60 |
$2.00 |
$1.60 |
| 5 | 233(A) 2817 |
VEGETATIVE MULCHING | 5.68 | AC |
$850.00 |
$588.00 |
$300.00 |
$1,000.00 |
$850.00 |
| 6 | 310(B) 0149 |
SUBGRADE, METHOD B | 94,242 | SY |
$1.90 |
$2.15 |
$2.75 |
$2.50 |
$2.00 |
| 7 | 311(D) 0154 |
PROCESSING EXISTING BASE & SURFACE, METHOD D | 35,340.57 | LF |
$7.00 |
$6.10 |
$6.26 |
$1.00 |
$7.80 |
| 8 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 539 | TON |
$55.00 |
$46.20 |
$47.74 |
$75.00 |
$47.00 |
| 9 | 407(B) 0250 |
TACK COAT | 4,463 | GAL |
$3.50 |
$5.70 |
$2.98 |
$2.50 |
$2.45 |
| 10 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 20,434 | TON |
$85.00 |
$78.10 |
$83.48 |
$97.50 |
$87.00 |
| 11 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 9,974 | TON |
$92.00 |
$93.50 |
$87.27 |
$95.00 |
$94.00 |
| 12 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$325.00 |
$340.00 |
$380.00 |
$500.00 |
$325.00 |
| 13 | 613(A) 0493 |
30" R.C.PIPE CLASS III | 88 | LF |
$90.00 |
$94.05 |
$127.22 |
$125.00 |
$88.00 |
| 14 | 613(L) 5732 |
30" PREFAB. CULVERT END SECTION, ROUND | 4 | EA |
$1,000.00 |
$784.00 |
$1,504.49 |
$2,500.00 |
$1,035.00 |
| 15 | 619(C) 0924 |
SAWING PAVEMENT | 132 | LF |
$3.00 |
$5.25 |
$4.55 |
$15.00 |
$2.50 |
| 16 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 193.97 | SF |
$27.00 |
$25.00 |
$25.00 |
$50.00 |
$25.00 |
| 17 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 42,418 | LF |
$0.6500 |
$0.4500 |
$0.4400 |
$0.5200 |
$0.4400 |
| 18 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$30,000.00 |
$7,500.00 |
$13,718.96 |
$10,000.00 |
$7,500.00 |
| 19 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$20,000.00 |
$20,900.00 |
$9,749.95 |
$10,000.00 |
$37,200.00 |
| 20 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$25,000.00 |
$26,125.00 |
$1,213.61 |
$1,000.00 |
$12,000.00 |
| 21 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$150,000.00 |
$105,000.00 |
$141,951.47 |
$130,000.00 |
$200,000.00 |