| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$15,000.00 |
$12,600.00 |
$15,000.00 |
$20,000.00 |
$20,000.00 |
| 2 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$62,000.00 |
$73,500.00 |
$88,750.00 |
$90,000.00 |
$100,000.00 |
| 3 | 221(C) 2801 |
TEMPORARY SILT FENCE | 4,000 | LF |
$2.50 |
$1.42 |
$1.56 |
$1.70 |
$2.50 |
| 4 | 221(F) 0100 |
TEMPORARY SILT DIKE | 250 | LF |
$6.00 |
$8.35 |
$9.14 |
$8.00 |
$10.00 |
| 5 | 221(G) 0151 |
TEMPORARY ROCK FILTER DAM TYPE 2 | 15 | CY |
$70.00 |
$73.50 |
$74.43 |
$90.00 |
$150.00 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 14,000 | SY |
$2.50 |
$1.58 |
$1.73 |
$1.80 |
$1.80 |
| 7 | 233(A) 2817 |
VEGETATIVE MULCHING | 5.8 | AC |
$500.00 |
$630.00 |
$500.00 |
$400.00 |
$400.00 |
| 8 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 1,904 | TON |
$30.00 |
$22.21 |
$21.00 |
$35.00 |
$25.00 |
| 9 | 408 5774 |
PRIME COAT | 1,287 | GAL |
$4.50 |
$7.88 |
$10.35 |
$6.00 |
$6.00 |
| 10 | 509(D) 0325 |
CLASS C CONCRETE | 15 | CY |
$300.00 |
$255.71 |
$267.50 |
$320.00 |
$750.00 |
| 11 | 613(A) 0496 |
48" R.C.PIPE CLASS III | 46 | LF |
$70.00 |
$156.93 |
$156.50 |
$150.00 |
$160.00 |
| 12 | 613(B) 0690 |
24" CORR. GALV. STEEL PIPE | 50 | LF |
$50.00 |
$28.08 |
$55.00 |
$65.00 |
$70.00 |
| 13 | 613(L) 5730 |
24" PREFAB. CULVERT END SECTION, ROUND | 2 | EA |
$300.00 |
$203.46 |
$325.00 |
$1,000.00 |
$700.00 |
| 14 | 613(O) 4383 |
SPECIAL END SECTION OF 48" RCP ROUND | 2 | EA |
$600.00 |
$1,988.96 |
$1,895.72 |
$3,500.00 |
$2,500.00 |
| 15 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 180 | CY |
$15.00 |
$25.30 |
$8.50 |
$12.00 |
$30.00 |
| 16 | 501(F) 6352 |
GRANULAR BACKFILL | 66 | CY |
$50.00 |
$69.06 |
$68.75 |
$55.00 |
$95.00 |
| 17 | 503(A) 1311 |
PRESTRESSED CONCRETE BEAMS (TYPE II) | 179 | LF |
$185.00 |
$165.65 |
$187.00 |
$175.00 |
$220.00 |
| 18 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 176 | LF |
$60.00 |
$90.97 |
$75.50 |
$75.00 |
$80.00 |
| 19 | 506(A) 1322 |
STRUCTURAL STEEL | 500 | LB |
$3.00 |
$3.94 |
$3.00 |
$4.00 |
$5.50 |
| 20 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 3 | EA |
$750.00 |
$1,269.87 |
$775.00 |
$1,000.00 |
$700.00 |
| 21 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 3 | EA |
$800.00 |
$1,269.87 |
$775.00 |
$1,000.00 |
$750.00 |
| 22 | 509(A) 1326 |
CLASS AA CONCRETE | 48.5 | CY |
$550.00 |
$727.65 |
$622.50 |
$550.00 |
$800.00 |
| 23 | 509(B) 1328 |
CLASS A CONCRETE | 60.4 | CY |
$450.00 |
$689.15 |
$650.00 |
$500.00 |
$400.00 |
| 24 | 511(A) 1332 |
REINFORCING STEEL | 20,160 | LB |
$1.00 |
$1.00 |
$0.9300 |
$1.00 |
$0.8000 |
| 25 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 160 | LF |
$30.00 |
$31.77 |
$25.84 |
$29.00 |
$35.00 |
| 26 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 731 | LF |
$35.00 |
$36.52 |
$32.20 |
$35.00 |
$38.00 |
| 27 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 160 | LF |
$12.00 |
$11.00 |
$11.08 |
$28.00 |
$50.00 |
| 28 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 731 | LF |
$14.00 |
$11.00 |
$13.80 |
$28.00 |
$50.00 |
| 29 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 777 | TON |
$35.00 |
$37.96 |
$35.13 |
$42.00 |
$50.00 |
| 30 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 184 | TON |
$30.00 |
$30.24 |
$26.98 |
$35.00 |
$50.00 |
| 31 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 52 | LF |
$20.00 |
$42.79 |
$32.50 |
$18.00 |
$20.00 |
| 32 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 150 | LF |
$20.00 |
$8.18 |
$29.00 |
$18.00 |
$20.00 |
| 33 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$1,000.00 |
$6,325.00 |
$5,125.00 |
$25,000.00 |
$25,000.00 |
| 34 | 623(A) 1418 |
BEAM GUARDRAIL W-BEAM SINGLE | 200 | LF |
$20.00 |
$13.75 |
$14.66 |
$18.00 |
$15.00 |
| 35 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$2,500.00 |
$1,430.00 |
$1,380.00 |
$1,500.00 |
$1,200.00 |
| 36 | 623(F) 6030 |
GUARDRAIL ANCHOR UNIT (TYPE B) | 3 | EA |
$600.00 |
$445.50 |
$471.50 |
$650.00 |
$900.00 |
| 37 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$5,000.00 |
$3,245.00 |
$3,392.50 |
$4,000.00 |
$2,500.00 |
| 38 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 190 | CY |
$15.00 |
$25.30 |
$8.50 |
$12.00 |
$30.00 |
| 39 | 501(F) 6352 |
GRANULAR BACKFILL | 76 | CY |
$50.00 |
$69.06 |
$69.00 |
$55.00 |
$95.00 |
| 40 | 503(A) 1311 |
PRESTRESSED CONCRETE BEAMS (TYPE II) | 179 | LF |
$185.00 |
$165.65 |
$187.00 |
$175.00 |
$220.00 |
| 41 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 188.1 | LF |
$60.00 |
$90.97 |
$75.50 |
$75.00 |
$80.00 |
| 42 | 506(A) 1322 |
STRUCTURAL STEEL | 580 | LB |
$3.00 |
$3.94 |
$3.00 |
$4.00 |
$5.50 |
| 43 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 3 | EA |
$750.00 |
$1,269.87 |
$775.00 |
$1,000.00 |
$700.00 |
| 44 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 3 | EA |
$800.00 |
$1,269.87 |
$775.00 |
$1,000.00 |
$750.00 |
| 45 | 509(A) 1326 |
CLASS AA CONCRETE | 50.6 | CY |
$550.00 |
$727.65 |
$615.00 |
$550.00 |
$800.00 |
| 46 | 509(B) 1328 |
CLASS A CONCRETE | 68 | CY |
$450.00 |
$689.15 |
$645.00 |
$500.00 |
$400.00 |
| 47 | 511(A) 1332 |
REINFORCING STEEL | 24,120 | LB |
$1.00 |
$1.00 |
$0.9300 |
$1.00 |
$0.8000 |
| 48 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 160 | LF |
$30.00 |
$32.13 |
$25.84 |
$29.00 |
$35.00 |
| 49 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 801 | LF |
$35.00 |
$36.34 |
$32.20 |
$35.00 |
$38.00 |
| 50 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 160 | LF |
$12.00 |
$11.00 |
$11.08 |
$28.00 |
$50.00 |
| 51 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 801 | LF |
$14.00 |
$11.00 |
$13.80 |
$28.00 |
$50.00 |
| 52 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 703 | TON |
$35.00 |
$37.96 |
$35.13 |
$42.00 |
$50.00 |
| 53 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 166 | TON |
$30.00 |
$30.24 |
$26.98 |
$35.00 |
$50.00 |
| 54 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 60 | LF |
$20.00 |
$42.79 |
$32.50 |
$18.00 |
$20.00 |
| 55 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 150 | LF |
$20.00 |
$8.18 |
$29.00 |
$18.00 |
$20.00 |
| 56 | 623(A) 1418 |
BEAM GUARDRAIL W-BEAM SINGLE | 442.37 | LF |
$20.00 |
$13.75 |
$14.66 |
$18.00 |
$15.00 |
| 57 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$2,500.00 |
$1,430.00 |
$1,380.00 |
$1,500.00 |
$1,200.00 |
| 58 | 623(F) 6030 |
GUARDRAIL ANCHOR UNIT (TYPE B) | 1 | EA |
$600.00 |
$445.50 |
$471.50 |
$650.00 |
$900.00 |
| 59 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 180 | CY |
$15.00 |
$25.30 |
$8.50 |
$12.00 |
$30.00 |
| 60 | 501(F) 6352 |
GRANULAR BACKFILL | 66 | CY |
$50.00 |
$69.06 |
$68.75 |
$55.00 |
$95.00 |
| 61 | 503(A) 1311 |
PRESTRESSED CONCRETE BEAMS (TYPE II) | 179 | LF |
$185.00 |
$165.65 |
$187.00 |
$175.00 |
$220.00 |
| 62 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 176 | LF |
$60.00 |
$90.97 |
$75.50 |
$75.00 |
$80.00 |
| 63 | 506(A) 1322 |
STRUCTURAL STEEL | 500 | LB |
$3.00 |
$3.94 |
$3.00 |
$4.00 |
$5.50 |
| 64 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 3 | EA |
$750.00 |
$1,269.87 |
$775.00 |
$1,000.00 |
$700.00 |
| 65 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 3 | EA |
$800.00 |
$1,269.87 |
$775.00 |
$1,000.00 |
$750.00 |
| 66 | 509(A) 1326 |
CLASS AA CONCRETE | 48.5 | CY |
$550.00 |
$727.65 |
$622.50 |
$550.00 |
$700.00 |
| 67 | 509(B) 1328 |
CLASS A CONCRETE | 60.4 | CY |
$450.00 |
$689.15 |
$650.00 |
$500.00 |
$400.00 |
| 68 | 511(A) 1332 |
REINFORCING STEEL | 20,160 | LB |
$1.00 |
$1.00 |
$0.9300 |
$1.00 |
$0.8000 |
| 69 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 160 | LF |
$30.00 |
$32.13 |
$25.84 |
$29.00 |
$35.00 |
| 70 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 831 | LF |
$35.00 |
$36.27 |
$32.20 |
$35.00 |
$38.00 |
| 71 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 160 | LF |
$12.00 |
$11.00 |
$11.08 |
$28.00 |
$50.00 |
| 72 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 831 | LF |
$14.00 |
$11.00 |
$13.80 |
$28.00 |
$50.00 |
| 73 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 1,020 | TON |
$35.00 |
$37.96 |
$35.13 |
$42.00 |
$50.00 |
| 74 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 270 | TON |
$30.00 |
$30.24 |
$26.98 |
$35.00 |
$50.00 |
| 75 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 52 | LF |
$20.00 |
$42.79 |
$32.50 |
$18.00 |
$20.00 |
| 76 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 150 | LF |
$20.00 |
$8.18 |
$29.00 |
$18.00 |
$20.00 |
| 77 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$10,000.00 |
$6,325.00 |
$5,125.00 |
$25,000.00 |
$25,000.00 |
| 78 | 623(A) 1418 |
BEAM GUARDRAIL W-BEAM SINGLE | 192.5 | LF |
$20.00 |
$13.75 |
$14.66 |
$18.00 |
$15.00 |
| 79 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$2,500.00 |
$1,430.00 |
$1,380.00 |
$1,500.00 |
$1,200.00 |
| 80 | 623(F) 6030 |
GUARDRAIL ANCHOR UNIT (TYPE B) | 3 | EA |
$600.00 |
$445.50 |
$471.50 |
$650.00 |
$900.00 |
| 81 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$20,000.00 |
$10,237.50 |
$11,115.00 |
$25,000.00 |
$22,000.00 |
| 82 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$3,554.25 |
$7,350.00 |
$5,000.00 |
$5,000.00 |
| 83 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$72,000.00 |
$43,582.20 |
$73,550.00 |
$75,000.00 |
$55,586.95 |