Bid tab 110379

Let Sep 15, 2011 · Division 4 · Grant Sign up free

‹ Sep 2011 results

BRIDGE AND APPROACHES COUNTY ROAD (EW-12): OVER DEER CREEK, 3.0 MILES WEST OF THE KAY COUNTY LINE. PROJECT LENGTH =0.113 MILES

Let date
Thursday, September 15, 2011
Contract
110379
J/P numbers
25586(04)
District
Division 4
County
Grant
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (EW-12): OVER DEER CREEK, 3.0 MILES WEST OF THE KAY COUNTY LINE. PROJECT LENGTH =0.113 MILES
Project number
BRO-127D(146)CI

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$436,846
1 K & R BUILDERS, INC. Low bidder $418,872 -4.1%
2 BRIDGECO CONTRACTORS, INC. $435,430 -0.3% +4.0%
3 B & B BRIDGE COMPANY, LLC $444,935 +1.9% +6.2%
4 L & M Contractors, Inc. $487,541 +11.6% +16.4%
5 WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES $523,229 +19.8% +24.9%
6 King Construction CO., INC. $595,521 +36.3% +42.2%

Bid tab: unit prices 34 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 K & R BUILDERS,…#2 BRIDGECO CONTRA…#3 B & B BRIDGE CO…#4 L & M Contracto…#5 WILDCAT CONSTRU…#6 King Constructi…
1202(H) 0185 EARTHWORK1LSUM $35,000.00 $22,250.00 $20,470.00 $20,000.00 $31,000.00 $13,000.00 $35,000.00
2221(C) 2801 TEMPORARY SILT FENCE200LF $3.00 $1.65 $3.00 $2.50 $2.50 $1.90 $1.55
3221(F) 0100 TEMPORARY SILT DIKE550LF $8.00 $4.10 $5.00 $5.95 $5.95 $8.40 $7.00
4230(A) 2806 SOLID SLAB SODDING6,805SY $2.25 $1.75 $2.40 $1.85 $1.85 $1.90 $1.55
5233(A) 2817 VEGETATIVE MULCHING1.41AC $600.00 $150.00 $700.00 $495.00 $495.00 $360.00 $300.00
6402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E465TON $32.00 $32.00 $36.50 $30.00 $29.00 $42.00 $15.00
7509(D) 0325 CLASS C CONCRETE10CY $250.00 $212.50 $250.00 $200.00 $200.00 $350.00 $350.00
8613(B) 4528 28" X 20" CORR. GALV. STEEL PIPE ARCH70LF $45.00 $20.50 $24.00 $23.00 $26.00 $54.00 $45.00
9613(M) 7187 TYPE B4 CULVERT END TREATMENT2EA $1,000.00 $900.00 $400.00 $1,000.00 $1,900.00 $1,350.00 $2,200.00
10850(A) 8110 SHEET ALUMINUM SIGNS10.36SF $15.00 $25.00 $39.00 $24.00 $25.00 $29.00 $24.00
11851(A) 3206 4"@13 GALV.STEEL WIDE FLANGE BEAM POST24LF $18.00 $15.00 $25.00 $15.50 $20.00 $19.00 $15.50
12501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON80CY $10.00 $7.50 $10.00 $25.00 $15.00 $11.00 $60.00
13501(D) 6353 UNCLASSIFIED BACKFILL50CY $15.00 $10.00 $12.00 $44.00 $25.00 $27.00 $50.00
14503(A) 1311 PRESTRESSED CONCRETE BEAMS (TYPE II)430.01LF $165.00 $165.00 $160.00 $175.00 $190.00 $255.00 $200.00
15504(D) 6239 CONCRETE RAIL (TR3)277LF $60.00 $60.50 $60.00 $54.00 $60.00 $75.00 $85.00
16506(A) 1322 STRUCTURAL STEEL500LB $3.00 $2.00 $3.13 $3.80 $3.00 $2.00 $3.50
17507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY20EA $700.00 $685.00 $555.00 $785.00 $480.00 $780.00 $650.00
18507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY4EA $700.00 $685.00 $556.00 $785.00 $580.00 $780.00 $650.00
19509(A) 1326 CLASS AA CONCRETE83.4CY $435.00 $450.00 $400.00 $505.00 $590.00 $475.00 $925.00
20509(B) 1328 CLASS A CONCRETE81.88CY $425.00 $472.50 $400.00 $505.00 $590.00 $475.00 $925.00
21511(A) 1332 REINFORCING STEEL31,207LB $0.8500 $0.8600 $1.00 $0.9000 $0.9000 $0.9000 $1.40
22514(A) 6010 PILES, FURNISHED (HP 10X42)468LF $22.00 $25.90 $26.25 $27.75 $33.00 $34.00 $34.00
23514(B) 6292 PILES, DRIVEN (HP 10X42)468LF $10.00 $11.10 $12.00 $12.50 $7.00 $16.00 $12.00
24516(A) 6093 DRILLED SHAFTS 42" DIAMETER90LF $450.00 $511.00 $637.42 $500.00 $670.00 $555.00 $500.00
25601(B) 1353 TYPE I-A PLAIN RIPRAP1,143TON $36.00 $33.66 $39.00 $34.00 $35.50 $46.00 $35.05
26601(C) 1355 TYPE I-A FILTER BLANKET343TON $34.00 $29.00 $33.68 $34.00 $34.00 $46.00 $31.35
27619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $6,500.00 $3,600.00 $6,000.00 $7,500.00 $3,000.00 $13,500.00 $10,000.00
28623(A) 1418 BEAM GUARDRAIL W-BEAM SINGLE102LF $30.00 $25.00 $22.00 $15.50 $17.50 $19.00 $15.50
29623(F) 6030 GUARDRAIL ANCHOR UNIT (TYPE B)2EA $550.00 $1,500.00 $875.00 $775.00 $800.00 $930.00 $775.00
30623(F) 6033 GUARDRAIL ANCHOR UNIT (TYPE II)2EA $2,200.00 $1,950.00 $1,925.00 $1,825.00 $1,850.00 $2,200.00 $1,825.00
31880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $4,000.00 $3,000.00 $2,800.00 $1,750.00 $2,000.00 $2,500.00 $1,750.00
32642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $4,200.00 $5,000.00 $5,600.00 $5,600.00 $5,200.00 $1,100.00 $5,750.00
33220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $3,000.00 $2,475.00 $1,800.00 $2,500.00 $3,000.00 $1,050.00 $4,000.00
34641 1399 MOBILIZATION1LSUM $18,000.00 $16,500.00 $16,862.68 $22,500.00 $26,300.00 $34,500.00 $50,350.00