Bid tab 100062

Let Mar 18, 2010 · · Leflore Sign up free

‹ Mar 2010 results

BRIDGE AND APPROACHES COUNTY ROAD (EW-172): OVER BEECH CREEK AND A TRIBUTARY TO BEECH CREEK, 0.5 MILE SOUTH AND 8.5 MILES EAST OF OCTAVIA . PROJECT LENGTH = 0.587 MILES

Let date
Thursday, March 18, 2010
Contract
100062
J/P numbers
21249(04)
District
County
Leflore
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (EW-172): OVER BEECH CREEK AND A TRIBUTARY TO BEECH CREEK, 0.5 MILE SOUTH AND 8.5 MILES EAST OF OCTAVIA . PROJECT LENGTH = 0.587 MILES
Project number
BRF-140C(113)CO

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,520,437
1 K & R BUILDERS, INC. Low bidder $1,079,468 -29.0%
2 HUB Construction, Inc. $1,143,732 -24.8% +6.0%
3 C-GAWF CONSTRUCTION, INC. $1,269,342 -16.5% +17.6%
4 WITTWER CONSTRUCTION CO., INC. $1,619,970 +6.5% +50.1%

Bid tab: unit prices 55 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 K & R BUILDERS,…#2 HUB Constructio…#3 C-GAWF CONSTRUC…#4 WITTWER CONSTRU…
1201 0102 CLEARING AND GRUBBING1LSUM $50,000.00 $18,000.00 $30,000.00 $12,500.00 $100,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION33,947CY $10.00 $5.00 $5.25 $7.25 $8.00
3202(C) 0184 UNCLASSIFIED BORROW1,000CY $20.00 $5.00 $5.50 $2.00 $10.00
4210 0121 OBLITERATING ABANDONED ROAD5.7STA $700.00 $410.00 $450.00 $250.00 $1,200.00
5223 2801 TEMPORARY SILT FENCE1,750LF $2.56 $1.15 $3.00 $1.25 $3.00
6227 0100 TEMPORARY SILT DIKE500LF $7.91 $6.65 $6.00 $5.00 $12.00
7230(A) 2806 SOLID SLAB SODDING9,500SY $2.25 $1.40 $2.00 $1.62 $1.35
8232(A) 2813 SEEDING METHOD A2.3AC $500.00 $395.00 $500.00 $496.75 $400.00
9233(A) 2817 VEGETATIVE MULCHING6.6AC $500.00 $449.00 $350.00 $561.25 $450.00
10234(A) 4406 FERTILIZING (0-46-0)0.17TON $1,000.00 $2,000.00 $750.00 $1,000.00 $1,500.00
11234(A) 4407 FERTILIZING (13-13-13)1.3TON $1,000.00 $650.00 $750.00 $812.50 $660.00
12303 0192 AGGREGATE BASE1,750CY $40.00 $42.45 $40.00 $52.00 $45.00
13403(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E500TON $35.00 $23.00 $30.00 $25.62 $42.00
14407 0250 TACK COAT438GAL $3.00 $3.87 $4.00 $4.84 $3.90
15408 5774 PRIME COAT1,440GAL $6.00 $6.00 $7.00 $7.50 $6.10
16411(S3) 5945 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK)1,485TON $95.00 $84.50 $82.00 $95.58 $77.00
17411(S4) 5960 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK)1,040TON $100.00 $89.00 $85.00 $99.64 $80.00
18509(D) 0325 CLASS C CONCRETE10CY $350.00 $250.00 $300.00 $325.00 $300.00
19601(A) 0297 TYPE I PLAIN RIPRAP100TON $40.00 $39.00 $40.00 $43.90 $45.00
20601(E) 6312 FILTER FABRIC (RIPRAP)200SY $5.00 $4.35 $2.00 $1.00 $12.50
21613(D) 0689 18" CORR. GALV. STEEL PIPE214LF $27.00 $15.00 $25.00 $24.00 $25.00
22613(D) 0690 24" CORR. GALV. STEEL PIPE36LF $32.00 $20.00 $30.00 $28.00 $28.00
23613(D) 0693 42" CORR. GALV. STEEL PIPE80LF $60.00 $38.00 $50.00 $55.00 $45.00
24613(M) 5726 18" PREFAB. CULVERT END SECTION, ROUND10EA $600.00 $225.00 $250.00 $250.00 $185.00
25613(M) 5730 24" PREFAB. CULVERT END SECTION, ROUND2EA $750.00 $260.00 $275.00 $275.00 $225.00
26850(A) 8110 SHEET ALUMINUM SIGNS10SF $20.00 $15.00 $18.00 $18.75 $15.10
27851(D) 8597 FLANGE CHANNEL POSTS(4 LB/FT)22LF $15.00 $10.00 $15.00 $12.50 $10.10
28854(A) 8800 TRAFFIC STRIPE(PAINT)(4" WIDE)12,800LF $0.3000 $0.1600 $0.3000 $0.1900 $0.1600
29501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON84CY $20.00 $6.00 $15.00 $10.00 $50.00
30501(G) 6309 CLSM BACKFILL82CY $120.00 $130.00 $175.00 $125.00 $300.00
31503(A) 1313 PRESTRESSED CONCRETE BEAMS (TYPE IV)416.67LF $190.00 $172.00 $180.00 $177.00 $285.00
32504(E) 1380 CONCRETE RAIL (TR1)275LF $60.00 $60.00 $65.00 $67.00 $100.00
33506(A) 1322 STRUCTURAL STEEL1,991LB $3.50 $3.00 $2.50 $3.85 $5.00
34509(A) 1326 CLASS AA CONCRETE80.6CY $600.00 $410.00 $600.00 $550.00 $950.00
35509(B) 1328 CLASS A CONCRETE53.8CY $500.00 $417.00 $600.00 $600.00 $925.00
36511(A) 1332 REINFORCING STEEL25,424LB $1.25 $0.7500 $0.6500 $0.9900 $1.25
37514 6260 (PL)PILOT HOLES368LF $100.00 $120.00 $105.00 $35.00 $120.00
38514(A) 6011 PILES, FURNISHED (HP 12X53)444LF $40.00 $31.00 $30.00 $27.13 $30.00
39514(B) 6294 PILES, DRIVEN (HP 12X53)444LF $20.00 $9.00 $12.00 $22.00 $35.00
40601(A-1)1353 TYPE I-A PLAIN RIPRAP702TON $40.00 $37.00 $40.00 $43.90 $45.00
41601(A-2)1355 TYPE I-A FILTER BLANKET144TON $40.00 $37.00 $35.00 $42.50 $43.00
42619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $30,000.00 $6,000.00 $5,000.00 $5,000.00 $50,000.00
43623(F) 6034 GUARD RAIL ANCHOR UNIT (TYPE III)4EA $2,500.00 $1,850.00 $2,500.00 $2,656.25 $2,160.00
44880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $5,500.00 $4,800.00 $6,000.00 $5,000.00 $4,100.00
45202(A) 1301 UNCLASSIFIED EXCAVATION560CY $10.00 $4.70 $6.00 $7.78 $6.00
46501(A) 1306 STRUCTURAL EXCAVATION UNCLASSIFIED71.3CY $20.00 $10.50 $25.00 $20.00 $45.00
47509(B) 1328 CLASS A CONCRETE176CY $500.00 $410.00 $400.00 $380.00 $540.00
48511(A) 1332 REINFORCING STEEL28,876LB $1.25 $0.7500 $0.6500 $0.7000 $1.25
49202(A) 1301 UNCLASSIFIED EXCAVATION600CY $10.00 $4.70 $6.00 $7.78 $6.00
50501(A) 1306 STRUCTURAL EXCAVATION UNCLASSIFIED71.3CY $20.00 $10.50 $25.00 $20.00 $45.00
51509(B) 1328 CLASS A CONCRETE176CY $500.00 $410.00 $400.00 $380.00 $540.00
52511(A) 1332 REINFORCING STEEL28,876LB $1.25 $0.7500 $0.6500 $0.7000 $1.25
53642 0098 STAKING1LSUM $15,000.00 $9,000.00 $10,000.00 $22,500.00 $11,250.00
54220 2800 (SP)SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $5,000.00 $2,500.00 $3,500.00 $7,000.00
55641 1399 MOBILIZATION1LSUM $50,000.00 $27,250.00 $40,000.00 $77,500.00 $59,449.65