Filtered by: County: Lake Clear all
| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jan 18, 2019 | 46481 | LakeDistrict 1 | Removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and placing new raised pavement marker castings within the limits shown. | — | Executed | Superior Road Striping, Inc. $278,325 · | ||
| Jan 18, 2019 | 61F33 | LakeDistrict 1 | Pavement reconstruction, construction of a shared use path, and lighting improvements on 14th Street from Green Bay Road to Sheridan Road in North Chicago. | — | Executed | Berger Excavating Contractors, Inc. $16,525,114 · | ||
| Jan 18, 2019 | 62C77 | LakeDistrict 1 | Resurfacing on US 41 (Skokie Hwy) from 1000 feet north of IL 176 (Rockland Rd) to 100 feet north of IL 120 (Belvidere Rd.). | — | Executed | Peter Baker & Son Co. $6,097,098 · | ||
| Jan 18, 2019 | 62F48 | LakeDistrict 1 | Resurfacing, pedestrian ramp improvement, and culvert repair on US 41 from Park Ave. West to Il 176 (Rockland Rd.); and on IL 22 from Tennyson Lane to US 41. 8.29 miles. | — | Executed | Peter Baker & Son Co. and Plote Construction, Inc JV $13,226,577 · | ||
| Jan 18, 2019 | 62G87 | CookLakeMcHenryDistrict 1 | Cleaning and painting existing steel on structures. IL 137 over US 45, IL 31 over UPRR, and Green Bay Road over North Shore Channel. | — | Executed | Eagle Painting & Maintenance Company, Inc. $302,850 · | ||
| Jan 18, 2019 | 62H31 | CookLakeDistrict 1 | Crack and joint sealing on US 12 (Rand Rd.) from Ela Road to IL 58 (Golf Rd.) | — | Executed | Freehill Asphalt, Inc. $451,265 · | ||
| Mar 8, 2019 | 60R68 | LakeDistrict 1 | Bridge deck scarification and latex concrete overlay, retrofitting bridge parapets, and reconstruction of transverse bridge joints to IL 43 over IL 120. | — | Executed | Areatha Construction Co., Inc. $1,777,994 · | ||
| Mar 8, 2019 | 61F47 | LakeDistrict 1 | Resurfacing Greenwood Avenue from Wilmot Road to Waukegan Road in Deerfield. | — | Executed | A Lamp Concrete Contractors, Inc. $1,668,129 · | ||
| Mar 8, 2019 | 62D38 | LakeDistrict 1 | Remove and replace original section of the culvert (approximately 40 ft) in the center portion of the culvert carrying IL 21 (Milwaukee Ave.) over a ditch in the village of Vernon Hills (SN 049-0599) | — | Executed | Martam Construction Incorporated $377,924 · | ||
| Mar 8, 2019 | 62G58 | LakeDistrict 1 | 2 miles of resurfacing on IL 137 (Amstutz Expressway) from IL 120 (Belvidere Street) to just south of IL 137 (Greenwood Avenue) in the City of Waukegan. | — | Executed | J. A. Johnson Paving Company $2,327,169 · | ||
| Mar 8, 2019 | 62G90 | LakeDistrict 1 | Sheet pile retaining wall and parking improvement at Illinois Beach State Park | — | Executed | Alliance Contractors, Inc. $953,418 · | ||
| Mar 8, 2019 | 62H39 | LakeDistrict 1 | Demolition of a single-family home in Mundelein and an auto repair building in Grayslake. | — | Executed | Lima Contractors $158,946 · | ||
| Apr 26, 2019 | 61E24 | LakeDistrict 1 | Pavement reconstruction, sidewalks, HMA pedestrian path, box culvert, water main relacation, traffic signal and street lighting on Weiland Road from Deerfield Parkway to Lake Cook Road. | — | Executed | Lake County Grading Company, LLC $12,090,770 · | ||
| Apr 26, 2019 | 61F65 | LakeDistrict 1 | Reconstruction of Orchard Lane from Monaville Road to Rollins Road, and resurfacing of Hook Lane from Orchard Lane to Rollins Road in the Village of Round Lake Beach. | — | Executed | Campanella and Sons, Inc. $5,231,811 · | ||
| Apr 26, 2019 | 61F69 | LakeDistrict 1 | Resurfacing Grand Avenue from Nippersink Boulevard to Illinois Route 59 in the Village of Fox Lake. | — | Executed | Peter Baker & Son Co. $1,287,252 · | ||
| Apr 26, 2019 | 61F75 | LakeDistrict 1 | Roadway reconstruction on Rockland Road from IL 21 to the Des Plaines River in Libertyville. | — | Executed | Copenhaver Construction, Inc. $6,139,354 · | ||
| Apr 26, 2019 | 62C01 | LakeDistrict 1 | 1.433 miles of 3P resurfacing and milled rumble strips on US 41 from IL 120 to Dorchester Avenue in Parck City and Gurnee. | — | Executed | Peter Baker & Son Co. $3,628,516 · | ||
| Apr 26, 2019 | 62G96 | LakeDistrict 1 | 0.947 mile of 3P resurfacing and overlaying including pedestrian curb improvements on US 41 from Lake-Cook Road to south of Chantilly Boulevard in Highland Park. | — | Executed | Plote Construction, Inc. $2,694,455 · | ||
| Apr 26, 2019 | 62H28 | LakeDistrict 1 | Routing, cleaning and sealing longitudinal cracks on IL 137 from IL 83 to O'Plaine Road in Libertyville and Green Oaks. | — | Executed | SKC Construction, Inc. $254,148 · | ||
| Apr 26, 2019 | 62H29 | CookLakeDistrict 1 | A total of 10.2 miles of routing, cleaning, and sealing of longitudinal cracks at 3 locations on IL 21/US 45 in Niles, Glenview, Vernon Hills, Libertyville and Gurnee. | — | Executed | Denler, Inc. $525,544 · | ||
| Apr 26, 2019 | 62H36 | LakeDistrict 1 | 1.9 miles of resurfacing, pedestrian ramp improvements and culvert repairs on US 41 from West Park Avenue to Chantilly Boulevard in the City of Highland Park. | — | Executed | Peter Baker & Son Co. and Plote Construction, Inc JV $5,321,788 · | ||
| Apr 26, 2019 | 62H81 | LakeDistrict 1 | 1.9 miles of ultra thin wearing course and ADA upgrades on US 41 from Ferndale Street to IL 21 in the Village of Gurnee. | — | Rejected | |||
| Jun 14, 2019 | 46507 | LakeWillDistrict 1 | Apply water borne, lead free, white and yellow paint pavement marking lines, 4, 6, and 8 inches in width in Lake and Will counties. | — | Executed | STF, LLC d/b/a Traffic Control Company $593,000 · | ||
| Jun 14, 2019 | 62B75 | LakeDistrict 1 | Intersection reconstruction at IL 131 and Kenosha Road in the Village of Beach Park. | — | Executed | Campanella and Sons, Inc. $3,348,311 · | ||
| Jun 14, 2019 | 62G30 | LakeDistrict 1 | 3.1 miles of resurfacing on IL 22 from N. Quentin Road to IL 83 in the Villages of Kildeer and Long Grove. | — | Executed | Builders Paving, LLC $1,698,888 · | ||
| Jun 14, 2019 | 62G83 | LakeDistrict 1 | 1.9 miles of resurfacing, shoulders, milled rumble strips, ADA ramps and pedestrian traffic signals at 2 locations in Gurnee, Livertyville, Waukegan and Park City: 1) IL 120 from east of I-94 to IL 43; 2)IL 21 at Red Top Drive. | — | Executed | Peter Baker & Son Co. $2,893,697 · | ||
| Jun 14, 2019 | 62H10 | LakeMcHenryDistrict 1 | Guardrail improvements at varous locations in McHenry and Lake Counties. | — | Executed | Kujo, Inc. $655,072 · | ||
| Jun 14, 2019 | 62H18 | LakeDistrict 1 | Culvert wing wall replacement on IL 120 just west of IL 83 in Grayslake. | — | Executed | Meru Corporation $147,965 · | ||
| Jun 14, 2019 | 62H88 | LakeDistrict 1 | Demolition and site clean-up of three single-family residences on IL 22 between Quentin Road and west of IL 83 in Long Grove and Kildeer. | — | Executed | McDonagh Demolition, Inc. $122,288 · | ||
| Jun 14, 2019 | 62J14 | LakeMcHenryDistrict 1 | Intermittent resurfacing on various routes in Lake and McHenry counties. | — | Executed | J. A. Johnson Paving Company $1,964,700 · | ||
| Jul 12, 2019 | 62H92 | LakeDistrict 1 | 1.8 miles of resurfacing and pedestrian ramp improvements along US 45 from Lake Woodlawn Dr. to IL RTE 83 in Mundelein. | — | Executed | Builders Paving, LLC $2,634,888 · | ||
| Jul 12, 2019 | 62H95 | LakeDistrict 1 | 3.56 miles of standard overlay and pedestrian ramp upgrades on IL-176 from Hilltop Terrace to De Webb Blvd. and on IL 60/83 from IL-176 to CN Railroad in Mundelein. | — | Executed | Arrow Road Construction Co. $2,064,157 · | ||
| Jul 12, 2019 | 62J03 | LakeDistrict 1 | 0.98 miles of designed overlay and pedestrian ramp improvements on IL 43 from McGaw Road / Pulaski Road to US 41 in Park City and Waukegan. | — | Executed | Peter Baker & Son Co. $1,997,757 · | ||
| Aug 2, 2019 | 62H91 | LakeDistrict 1 | Drain tile repair project, includes replacement of 18" clay pipe with 24" reinforced concrete pipe in unincorporated Avon Township on IL 120, just east of Wilson Road | — | Executed | Lion Construction 1, LLC $497,411 · | ||
| Sep 20, 2019 | 61D65 | LakeDistrict 1 | Reconstruct the intersection of Hart Road at US Route 14 in the Villages of Barrington and Barrington Hills. | — | Executed | Plote Construction, Inc. $7,965,000 · | ||
| Sep 20, 2019 | 61F25 | LakeDistrict 1 | Pavement reconstruction and the construction of a HMA pedestrian path next to Weiland Road from Aptakisic Road to Deerfield Parkway, and on Aptakistic Road from Joseph Court to Industrial Drive in the villages of Buffalo Grove and Lincolnshire. | — | Executed | Berger Excavating Contractors, Inc. $12,469,513 · | ||
| Sep 20, 2019 | 61G00 | LakeDistrict 1 | Reconstruction and resurfacing Rockland Road from east of the Des Plaines River bridge to St. Mary's Road, located in Libertyville Township, Lake County. | — | Executed | Berger Excavating Contractors, Inc. $1,964,385 · | ||
| Nov 8, 2019 | 61F63 | LakeDistrict 1 | Construction of HMA path on Riverwoods Road between Daniel Wright School and Whytegate Park and construction of a sidewalk along Westminster Way from the CDW Path west for 0.07 miles, located in the Village of Lincolnshire. | — | Executed | Chicagoland Paving Contractors, Inc. $270,000 · |
1–38 of 38
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.