18-00024-00-BT
- Let date
- Friday, November 8, 2019
- Contract
- 61F63 · job page
- District
- District 1
- County
- Lake
- Highway
- Limits
- Construction of HMA path on Riverwoods Road between Daniel Wright School and Whytegate Park and construction of a sidewalk along Westminster Way from the CDW Path west for 0.07 miles, located in the Village of Lincolnshire.
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Chicagoland Paving Contractors, Inc. Low bidder | $270,000 | ||
| 2 | Copenhaver Construction, Inc. | $283,996 | +5.2% | |
| 3 | A Lamp Concrete Contractors, Inc. | $294,659 | +9.1% | |
| 4 | Martam Construction Incorporated | $328,862 | +21.8% | |
| 5 | Landmark Contractors, Inc. | $330,095 | +22.3% | |
| 6 | Alliance Contractors, Inc. | $368,754 | +36.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Chicagoland Pav… | #2 Copenhaver Cons… | #3 A Lamp Concrete… | #4 Martam Construc… | #5 Landmark Contra… | #6 Alliance Contra… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | A2004416 | T-GINKGO BILOBA 2 | 3 | EACH | $1,015.00 | $700.00 | $990.00 | $1,050.00 | $715.00 | $950.00 | |
| 2 | A2005016 | T-GYMNOCLA DIO 2 | 2 | EACH | $450.00 | $700.00 | $935.00 | $500.00 | $535.00 | $425.00 | |
| 3 | A2006516 | T-QUERCUS BICOL 2 | 2 | EACH | $480.00 | $700.00 | $935.00 | $500.00 | $555.00 | $450.00 | |
| 4 | A2007116 | T-QUERCUS RUBRA 2 | 4 | EACH | $480.00 | $700.00 | $935.00 | $500.00 | $555.00 | $450.00 | |
| 5 | X0100003 | CLEARING & GRUBBING | 1,300 | SQ YD | $22.00 | $4.00 | $22.00 | $22.00 | $4.00 | $20.00 | |
| 6 | X4403300 | CONC MEDIAN REMOV | 195 | SQ FT | $5.00 | $8.00 | $4.00 | $8.00 | $8.85 | $10.00 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,500.00 | $16,000.00 | $6,000.00 | $7,000.00 | $5,749.00 | $4,635.00 | |
| 8 | Z0030850 | TEMP INFO SIGNING | 105 | SQ FT | $20.00 | $20.00 | $15.00 | $15.00 | $12.00 | $15.00 | |
| 9 | Z0075500 | TIMBER RETAINING WALL | 750 | SQ FT | $25.00 | $35.00 | $50.00 | $47.00 | $65.05 | $45.00 | |
| 10 | 20100110 | TREE REMOV 6-15 | 92 | UNIT | $42.50 | $30.00 | $44.00 | $45.00 | $30.00 | $40.00 | |
| 11 | 20100210 | TREE REMOV OVER 15 | 26 | UNIT | $72.25 | $40.00 | $75.00 | $75.00 | $40.00 | $68.00 | |
| 12 | 20101100 | TREE TRUNK PROTECTION | 14 | EACH | $100.00 | $60.00 | $75.00 | $220.00 | $200.00 | $150.00 | |
| 13 | 20101200 | TREE ROOT PRUNING | 14 | EACH | $160.00 | $20.00 | $75.00 | $180.00 | $200.00 | $90.00 | |
| 14 | 20200100 | EARTH EXCAVATION | 850 | CU YD | $35.00 | $36.00 | $20.00 | $45.00 | $69.05 | $10.00 | |
| 15 | 20201200 | REM & DISP UNS MATL | 80 | CU YD | $50.00 | $36.00 | $15.00 | $56.00 | $95.00 | $50.00 | |
| 16 | 21101600 | TOPSOIL F & P VAR DP | 1,900 | SQ YD | $5.30 | $4.00 | $2.00 | $6.00 | $6.65 | $5.00 | |
| 17 | 25000210 | SEEDING CL 2A | 0.4 | ACRE | $5,150.00 | $8,000.00 | $3,245.00 | $5,500.00 | $3,000.00 | $4,840.00 | |
| 18 | 25000400 | NITROGEN FERT NUTR | 35 | POUND | $1.10 | $1.00 | $4.40 | $2.00 | $3.00 | $1.00 | |
| 19 | 25000600 | POTASSIUM FERT NUTR | 35 | POUND | $1.10 | $1.00 | $4.40 | $2.00 | $3.00 | $1.00 | |
| 20 | 25100630 | EROSION CONTR BLANKET | 1,900 | SQ YD | $1.06 | $2.00 | $2.75 | $1.20 | $1.25 | $1.00 | |
| 21 | 28000250 | TEMP EROS CONTR SEED | 100 | POUND | $1.00 | $0.0100 | $1.00 | $1.00 | $6.00 | $0.1000 | |
| 22 | 28000400 | PERIMETER EROS BAR | 1,200 | FOOT | $3.25 | $2.00 | $3.00 | $3.00 | $3.00 | $3.00 | |
| 23 | 31101200 | SUB GRAN MAT B 4 | 320 | SQ YD | $5.50 | $6.00 | $6.00 | $9.00 | $17.90 | $5.75 | |
| 24 | 31101400 | SUB GRAN MAT B 6 | 1,280 | SQ YD | $11.50 | $12.00 | $12.00 | $10.00 | $20.35 | $8.75 | |
| 25 | 31101600 | SUB GRAN MAT B 8 | 40 | SQ YD | $15.00 | $12.00 | $14.00 | $22.00 | $31.10 | $13.00 | |
| 26 | 40600275 | BIT MATLS PR CT | 350 | POUND | $0.0100 | $1.00 | $1.00 | $3.00 | $2.00 | $2.00 | |
| 27 | 40600290 | BIT MATLS TACK CT | 90 | POUND | $0.0100 | $1.00 | $1.00 | $10.00 | $9.00 | $9.00 | |
| 28 | 40600982 | HMA SURF REM BUTT JT | 105 | SQ YD | $10.00 | $20.00 | $10.00 | $6.00 | $5.00 | $5.00 | |
| 29 | 40603080 | HMA BC IL-19.0 N50 | 10 | TON | $125.00 | $250.00 | $100.00 | $325.00 | $275.00 | $275.00 | |
| 30 | 40604060 | HMA SC IL-9.5 D N50 | 250 | TON | $100.00 | $140.00 | $120.00 | $165.00 | $150.00 | $150.00 | |
| 31 | 40800050 | INCIDENTAL HMA SURF | 15 | TON | $125.00 | $100.00 | $200.00 | $250.00 | $220.00 | $220.00 | |
| 32 | 42001300 | PROTECTIVE COAT | 300 | SQ YD | $10.60 | $2.00 | $1.50 | $2.00 | $2.85 | $0.0100 | |
| 33 | 42400200 | PC CONC SIDEWALK 5 | 2,700 | SQ FT | $12.75 | $7.00 | $7.75 | $7.00 | $8.15 | $7.00 | |
| 34 | 42400800 | DETECTABLE WARNINGS | 150 | SQ FT | $37.25 | $25.00 | $35.00 | $35.00 | $27.50 | $30.00 | |
| 35 | 44000100 | PAVEMENT REM | 25 | SQ YD | $40.00 | $20.00 | $20.00 | $36.00 | $71.20 | $75.00 | |
| 36 | 44000157 | HMA SURF REM 2 | 200 | SQ YD | $7.50 | $10.00 | $30.00 | $55.00 | $50.00 | $50.00 | |
| 37 | 44000500 | COMB CURB GUTTER REM | 190 | FOOT | $7.50 | $7.00 | $5.00 | $8.00 | $18.30 | $20.00 | |
| 38 | 60603800 | COMB CC&G TB6.12 | 145 | FOOT | $53.00 | $28.00 | $30.00 | $45.00 | $44.80 | $75.00 | |
| 39 | 60605000 | COMB CC&G TB6.24 | 50 | FOOT | $69.00 | $31.00 | $40.00 | $56.00 | $51.40 | $100.00 | |
| 40 | 66900200 | NON SPL WASTE DISPOSL | 50 | CU YD | $50.00 | $109.00 | $300.00 | $122.00 | $85.00 | $50.00 | |
| 41 | 66900565 | PNAS SOIL ANALYSIS | 2 | EACH | $1,000.00 | $700.00 | $330.00 | $300.00 | $275.00 | $275.00 | |
| 42 | 66900570 | PNAS GRND WATER ANALY | 2 | EACH | $1,000.00 | $700.00 | $330.00 | $300.00 | $275.00 | $275.00 | |
| 43 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,300.00 | $3,500.00 | $3,300.00 | $2,000.00 | $1,500.00 | $1,500.00 | |
| 44 | 66901002 | ON-SITE MON REG SUB | 1 | CAL DA | $1,675.00 | $800.00 | $750.00 | $1,600.00 | $600.00 | $600.00 | |
| 45 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,350.00 | $900.00 | $1,000.00 | $3,000.00 | $2,000.00 | $2,000.00 | |
| 46 | 67100100 | MOBILIZATION | 1 | L SUM | $23,459.60 | $16,075.00 | $17,000.00 | $18,000.00 | $17,300.00 | $130,000.00 | |
| 47 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $2,500.00 | $39,000.00 | $34,000.00 | $24,000.00 | $4,000.00 | $1.00 | |
| 48 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $100.00 | $4,000.00 | $100.00 | $1.00 | $1.00 | $1.00 | |
| 49 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $100.00 | $1,000.00 | $100.00 | $1.00 | $1.00 | $1,800.00 | |
| 50 | 78000600 | THPL PVT MK LINE 12 | 280 | FOOT | $15.55 | $15.00 | $10.00 | $10.00 | $13.75 | $9.00 |