$8.94Avg low bid / SQ YD
$8.36Avg of all bids
—Avg engineer's estimate
21Jobs · 45,557.7 SQ YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 4 | 11,957 | $11.07 | $9.88 |
| 2022 | 4 | 1,262 | $60.53 | $56.88 |
| 2021 | 4 | 9,032 | $7.21 | $6.01 |
| 2020 | 1 | 1,572 | $2.78 | $3.99 |
| 2019 | 4 | 20,813.7 | $4.22 | $5.61 |
| 2018 | 4 | 921 | $44.71 | $57.16 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 22, 2023 | 62D82 | CookDistrict 1 | 100 SQ YD | $25.00 | John Burns Construction Company |
| Mar 10, 2023 | 61H80 | MchenryDistrict 1 | 940 SQ YD | $4.00 | Benchmark Construction Co., Inc. |
| Mar 10, 2023 | 74B71 | EffinghamDistrict 7 | 2,623 SQ YD | $25.00 | Endrizzi Contracting, Inc |
| Jan 20, 2023 | 85700 | LeeDistrict 2 | 8,294 SQ YD | $7.30 | Martin & Company Excavating |
| Nov 18, 2022 | 72D32 | MontgomeryDistrict 6 | 60 SQ YD | $31.35 | Illinois Valley Paving, a div of UCM, Inc. |
| Nov 18, 2022 | 93691 | SangamonDistrict 6 | 1,065 SQ YD | $63.63 | Illinois Valley Paving, a div of UCM, Inc. |
| Sep 23, 2022 | 62N04 | CookDistrict 1 | 115 SQ YD | $37.80 | Meade Inc. |
| Sep 23, 2022 | 70943 | McleanDistrict 5 | 22 SQ YD | $108.65 | Rowe Construction, a div of UCM, Inc. |
| Sep 17, 2021 | 62D79 | Cook, LakeDistrict 1 | 4,185 SQ YD | $4.33 | Meade Inc. |
| Jul 30, 2021 | 62D86 | LakeDistrict 1 | 1,970 SQ YD | $2.50 | Lorig Construction Company |
| Mar 5, 2021 | 85658 | Rock IslandDistrict 2 | 2,000 SQ YD | $7.00 | Miller Trucking & Excavating Company |
| Jan 15, 2021 | 91752 | VermilionDistrict 5 | 877 SQ YD | $32.00 | Cross Construction, Inc. |
| Jun 12, 2020 | 61G55 | DupageDistrict 1 | 1,572 SQ YD | $2.78 | P. T. Ferro Construction Co. |
| Nov 8, 2019 | 62J76 | CookDistrict 1 | 14,694 SQ YD | $2.75 | D. Construction, Inc. |
| Nov 8, 2019 | 61F63 | LakeDistrict 1 | 1,300 SQ YD | $22.00 | Chicagoland Paving Contractors, Inc. |
| Jun 14, 2019 | 85674 | StephensonDistrict 2 | 4,414.7 SQ YD | $1.25 | Fischer Excavating, Inc. |
| Apr 26, 2019 | 60R52 | WillDistrict 1 | 405 SQ YD | $33.00 | D. Construction, Inc. |
| Nov 9, 2018 | 46472 | Dupage, WillDistrict 1 | 106 SQ YD | $125.50 | Aldridge Electric, Inc. |
| Nov 9, 2018 | 46473 | CookDistrict 1 | 50 SQ YD | $250.00 | Kujo, Inc. |
| Aug 3, 2018 | 62F85 | WillDistrict 1 | 405 SQ YD | $8.00 | Clean Cut Tree Service, Inc. |
| Jun 15, 2018 | 60P55 | WillDistrict 1 | 360 SQ YD | $33.70 | Meade Inc. |
| Jan 19, 2018 | 76J11 | St ClairDistrict 8 | 3,531 SQ YD | $3.00 | The Kilian Corporation |