27-1BR-1
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | The Kilian Corporation Low bidder | $4,946,423 | ||
| 2 | Keeley & Sons, Inc. | $4,992,101 | +0.9% | |
| 3 | Plocher Construction Company, Inc. | $5,654,000 | +14.3% | |
| 4 | St. Louis Bridge Construction Company | $5,970,278 | +20.7% | |
| 5 | Keller Construction, Inc. | $6,629,292 | +34.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 The Kilian Corp… | #2 Keeley & Sons, … | #3 Plocher Constru… | #4 St. Louis Bridg… | #5 Keller Construc… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0100003 | CLEARING & GRUBBING | 3,531 | SQ YD | $3.00 | $2.55 | $2.95 | $2.92 | $3.00 | |
| 2 | X0323992 | HELICAL GROUND ANCHOR | 8 | EACH | $4,000.00 | $4,110.00 | $6,650.00 | $5,000.00 | $4,000.00 | |
| 3 | X0325088 | PLAC OF CEMENT GROUT | 32 | CU FT | $17.00 | $125.00 | $80.00 | $200.00 | $152.50 | |
| 4 | X0325734 | SLOTTED DRAIN REMOVAL | 1,225 | FOOT | $13.00 | $6.75 | $10.20 | $10.20 | $10.38 | |
| 5 | X0326519 | STEEL RAILING REMOVAL | 126 | FOOT | $5.50 | $5.00 | $5.30 | $5.29 | $5.40 | |
| 6 | X0327980 | PAVMT MRKG REM WTR BL | 27,197 | SQ FT | $0.0100 | $1.79 | $1.75 | $1.75 | $0.4000 | |
| 7 | X5091755 | PARAPET RAILING SPL | 115 | FOOT | $113.00 | $137.24 | $111.00 | $111.00 | $113.00 | |
| 8 | X5860110 | GRANULAR BACKFILL STR | 338 | CU YD | $39.00 | $36.90 | $45.00 | $32.00 | $45.94 | |
| 9 | X6430110 | REM IMP ATTEN SALV | 2 | EACH | $605.00 | $1,040.00 | $600.00 | $600.00 | $966.00 | |
| 10 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $100,000.00 | $48,642.00 | $80,000.00 | $81,925.00 | $120,500.00 | |
| 11 | X7030030 | WET REF TEM TAPE T3 4 | 25,319 | FOOT | $0.9000 | $0.9200 | $0.9000 | $0.9000 | $0.9200 | |
| 12 | X7040125 | PIN TEMP CONC BARRIER | 144 | EACH | $21.00 | $23.00 | $17.00 | $17.00 | $17.29 | |
| 13 | X7830070 | GRV RCSD PVT MRKG 5 | 2,324 | FOOT | $1.50 | $1.53 | $1.50 | $1.50 | $1.53 | |
| 14 | Z0000300 | ADJ ROCKER & SOLE PLT | 18 | EACH | $2,265.00 | $1,785.00 | $2,210.00 | $2,400.00 | $2,440.00 | |
| 15 | Z0001899 | JACK & REM EX BEARING | 24 | EACH | $2,650.00 | $2,490.00 | $3,000.00 | $4,000.00 | $2,950.00 | |
| 16 | Z0001903 | STRUCT STEEL REMOV | 25,120 | POUND | $2.70 | $3.45 | $3.00 | $1.30 | $2.52 | |
| 17 | Z0004552 | APPROACH SLAB REM | 427 | SQ YD | $30.00 | $23.00 | $35.00 | $30.00 | $30.30 | |
| 18 | Z0007101 | C&D LEAD PT CL RS N1 | 1 | L SUM | $29,400.00 | $29,454.54 | $31,000.00 | $28,877.00 | $29,500.00 | |
| 19 | Z0007102 | C&D LEAD PT CL RS N2 | 1 | L SUM | $29,400.00 | $29,454.54 | $31,000.00 | $28,877.00 | $29,500.00 | |
| 20 | Z0012754 | STR REP CON DP = < 5 | 359 | SQ FT | $105.00 | $137.80 | $42.00 | $250.00 | $237.00 | |
| 21 | Z0012755 | STR REP CON DP OVER 5 | 21 | SQ FT | $225.00 | $197.80 | $80.00 | $300.00 | $265.00 | |
| 22 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $16,000.00 | $22,440.00 | $15,000.00 | $5,096.00 | $21,000.00 | |
| 23 | Z0018002 | DRAINAGE SCUPPR DS-11 | 4 | EACH | $985.00 | $1,294.50 | $1,200.00 | $1,000.00 | $1,500.00 | |
| 24 | Z0033700 | LONG JOINT SEALANT | 318 | FOOT | $14.00 | $18.45 | $26.00 | $5.00 | $26.25 | |
| 25 | Z0034806 | MODULAR EXP JT-SW 6 | 338 | FOOT | $2,300.00 | $1,095.00 | $2,250.00 | $3,150.00 | $2,812.00 | |
| 26 | Z0046304 | P UNDR FOR STRUCT 4 | 462 | FOOT | $15.00 | $27.95 | $14.00 | $25.00 | $21.50 | |
| 27 | Z0076600 | TRAINEES | 1,500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 28 | Z0076604 | TRAINEES TPG | 1,500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 29 | 20200100 | EARTH EXCAVATION | 4,586 | CU YD | $0.0100 | $9.80 | $17.00 | $16.98 | $17.27 | |
| 30 | 20700220 | POROUS GRAN EMBANK | 571 | CU YD | $41.50 | $28.90 | $40.00 | $50.00 | $45.74 | |
| 31 | 25000200 | SEEDING CL 2 | 3 | ACRE | $1,225.00 | $1,224.00 | $1,220.00 | $1,217.89 | $1,220.00 | |
| 32 | 25000400 | NITROGEN FERT NUTR | 272 | POUND | $1.25 | $1.23 | $1.70 | $1.70 | $1.22 | |
| 33 | 25000500 | PHOSPHORUS FERT NUTR | 272 | POUND | $1.25 | $1.23 | $1.70 | $1.70 | $1.22 | |
| 34 | 25000600 | POTASSIUM FERT NUTR | 272 | POUND | $1.25 | $1.23 | $1.70 | $1.70 | $1.22 | |
| 35 | 25100630 | EROSION CONTR BLANKET | 14,621 | SQ YD | $1.35 | $1.33 | $1.55 | $1.54 | $1.32 | |
| 36 | 28000250 | TEMP EROS CONTR SEED | 906 | POUND | $3.50 | $6.00 | $2.50 | $2.50 | $2.54 | |
| 37 | 28000305 | TEMP DITCH CHECKS | 276 | FOOT | $13.00 | $6.60 | $15.30 | $15.29 | $15.54 | |
| 38 | 28000400 | PERIMETER EROS BAR | 980 | FOOT | $3.15 | $3.17 | $2.35 | $2.35 | $2.39 | |
| 39 | 28000500 | INLET & PIPE PROTECT | 6 | EACH | $120.00 | $405.00 | $115.00 | $200.00 | $105.00 | |
| 40 | 28100105 | STONE RIPRAP CL A3 | 55 | SQ YD | $25.00 | $59.80 | $32.00 | $30.23 | $30.75 | |
| 41 | 28100109 | STONE RIPRAP CL A5 | 5,105 | SQ YD | $47.50 | $39.80 | $48.00 | $46.55 | $47.35 | |
| 42 | 28200200 | FILTER FABRIC | 5,105 | SQ YD | $2.30 | $3.20 | $2.30 | $2.27 | $2.30 | |
| 43 | 31101200 | SUB GRAN MAT B 4 | 872 | SQ YD | $7.50 | $5.80 | $6.20 | $10.00 | $8.93 | |
| 44 | 35400500 | PCC BASE CSE W 10 | 41 | SQ YD | $140.00 | $137.80 | $210.00 | $180.00 | $210.00 | |
| 45 | 40600275 | BIT MATLS PR CT | 9,043 | POUND | $0.5000 | $0.0200 | $0.0100 | $0.0100 | $0.0100 | |
| 46 | 40600290 | BIT MATLS TACK CT | 1,904 | POUND | $0.4500 | $2.02 | $1.98 | $1.98 | $2.01 | |
| 47 | 40600647 | LB MM IL-9.5FG N90 | 63 | TON | $160.00 | $198.45 | $194.55 | $194.55 | $198.00 | |
| 48 | 40603545 | P HMA SC "D" N90 | 72 | TON | $160.00 | $214.20 | $210.00 | $210.00 | $213.50 | |
| 49 | 42000080 | PVT CON PCC BR APP SL | 872 | SQ YD | $120.00 | $109.45 | $100.00 | $125.00 | $149.00 | |
| 50 | 44000100 | PAVEMENT REM | 9,990 | SQ YD | $5.00 | $8.35 | $5.15 | $5.13 | $5.20 | |
| 51 | 44000155 | HMA SURF REM 1 1/2 | 848 | SQ YD | $12.50 | $8.16 | $8.55 | $8.00 | $8.14 | |
| 52 | 44004250 | PAVED SHLD REMOVAL | 985 | SQ YD | $8.00 | $7.90 | $7.90 | $7.89 | $8.03 | |
| 53 | 44201359 | CL C PATCH T4 10 | 116 | SQ YD | $88.00 | $93.80 | $115.00 | $75.00 | $142.00 | |
| 54 | 48102100 | AGG WEDGE SHLD TYPE B | 133 | TON | $36.00 | $59.51 | $58.40 | $125.00 | $60.00 | |
| 55 | 48203029 | HMA SHOULDERS 8 | 1,241 | SQ YD | $38.00 | $45.71 | $44.82 | $44.81 | $45.50 | |
| 56 | 48203037 | HMA SHOULDERS 10 | 2,636 | SQ YD | $39.00 | $44.21 | $43.35 | $43.34 | $44.08 | |
| 57 | 50102400 | CONC REM | 120.9 | CU YD | $685.00 | $567.80 | $1,165.00 | $1,100.00 | $994.00 | |
| 58 | 50104650 | SLOPE WALL REMOV | 4,345 | SQ YD | $6.75 | $8.90 | $6.80 | $6.76 | $6.87 | |
| 59 | 50104720 | REM EXIST CONC DECK | 2 | EACH | $75,000.00 | $57,890.00 | $68,000.00 | $100,000.00 | $66,810.00 | |
| 60 | 50105220 | PIPE CULVERT REMOV | 781 | FOOT | $4.25 | $8.65 | $5.50 | $5.10 | $10.48 | |
| 61 | 50200100 | STRUCTURE EXCAVATION | 672 | CU YD | $25.00 | $27.80 | $24.50 | $24.38 | $24.79 | |
| 62 | 50300225 | CONC STRUCT | 336.5 | CU YD | $495.00 | $697.80 | $580.00 | $1,000.00 | $978.50 | |
| 63 | 50300255 | CONC SUP-STR | 913.4 | CU YD | $875.00 | $937.80 | $1,100.00 | $1,100.00 | $1,493.50 | |
| 64 | 50300260 | BR DECK GROOVING | 2,968 | SQ YD | $4.75 | $4.14 | $4.25 | $6.00 | $4.85 | |
| 65 | 50300300 | PROTECTIVE COAT | 3,823 | SQ YD | $1.25 | $1.95 | $0.2400 | $6.00 | $1.45 | |
| 66 | 50301350 | CONC SUPSTR APP SLAB | 215.3 | CU YD | $335.00 | $287.90 | $280.00 | $650.00 | $308.00 | |
| 67 | 50500405 | F & E STRUCT STEEL | 54,750 | POUND | $5.65 | $7.80 | $6.00 | $3.25 | $5.98 | |
| 68 | 50500505 | STUD SHEAR CONNECTORS | 7,956 | EACH | $2.40 | $2.65 | $2.70 | $2.25 | $2.38 | |
| 69 | 50606701 | C & P STRUCT STL L1 | 1 | L SUM | $117,000.00 | $117,818.16 | $120,000.00 | $115,508.00 | $120,805.00 | |
| 70 | 50606702 | C & P STRUCT STL L2 | 1 | L SUM | $117,000.00 | $117,818.16 | $120,000.00 | $115,508.00 | $120,805.00 | |
| 71 | 50800205 | REINF BARS, EPOXY CTD | 375,900 | POUND | $1.05 | $1.20 | $1.10 | $1.00 | $1.08 | |
| 72 | 50800515 | BAR SPLICERS | 371 | EACH | $29.00 | $22.85 | $28.00 | $24.00 | $27.98 | |
| 73 | 51500100 | NAME PLATES | 2 | EACH | $445.00 | $545.00 | $754.48 | $800.00 | $523.00 | |
| 74 | 52100010 | ELAST BEARING ASSY T1 | 24 | EACH | $655.00 | $619.98 | $890.00 | $775.00 | $1,210.00 | |
| 75 | 52100520 | ANCHOR BOLTS 1 | 48 | EACH | $132.00 | $68.87 | $60.00 | $170.00 | $244.00 | |
| 76 | 542C0223 | P CUL CL C 1 18 | 8 | FOOT | $80.00 | $63.00 | $33.00 | $150.00 | $170.00 | |
| 77 | 54213447 | END SECTIONS 12 | 2 | EACH | $360.00 | $265.00 | $105.00 | $400.00 | $667.00 | |
| 78 | 54213453 | END SECTIONS 18 | 1 | EACH | $565.00 | $435.00 | $250.00 | $500.00 | $700.00 | |
| 79 | 550A0050 | STORM SEW CL A 1 12 | 8 | FOOT | $105.00 | $77.00 | $56.00 | $250.00 | $325.00 | |
| 80 | 58700300 | CONCRETE SEALER | 3,253 | SQ FT | $0.7000 | $0.6500 | $1.15 | $3.00 | $1.80 | |
| 81 | 59100100 | GEOCOMPOSITE WALL DR | 346 | SQ YD | $28.00 | $34.80 | $20.00 | $50.00 | $27.35 | |
| 82 | 60100945 | PIPE DRAINS 12 | 63 | FOOT | $34.00 | $29.80 | $31.00 | $40.00 | $70.00 | |
| 83 | 60234200 | INLETS TA T1F OL | 3 | EACH | $990.00 | $1,650.00 | $1,300.00 | $1,300.00 | $1,538.00 | |
| 84 | 60259905 | MAN RECON N MI 604106 | 1 | EACH | $2,225.00 | $2,300.00 | $2,500.00 | $2,800.00 | $4,058.00 | |
| 85 | 61000050 | CONC THRUST BLOCKS | 2 | EACH | $275.00 | $365.00 | $400.00 | $1,200.00 | $1,400.00 | |
| 86 | 61000335 | TY G INLET BOX 610001 | 2 | EACH | $1,400.00 | $2,200.00 | $1,800.00 | $3,200.00 | $3,500.00 | |
| 87 | 61100500 | EXPLOR TRENCH 52 | 100 | FOOT | $5.00 | $15.00 | $35.00 | $30.00 | $37.00 | |
| 88 | 61100605 | MISC CONCRETE | 6 | CU YD | $325.00 | $195.00 | $165.00 | $240.00 | $1,411.00 | |
| 89 | 61133100 | FLD TILE JUN VAULT 2D | 1 | EACH | $1,050.00 | $1,750.00 | $1,800.00 | $2,700.00 | $1,566.00 | |
| 90 | 61133300 | FLD TILE JUN VAULT 4D | 1 | EACH | $1,500.00 | $2,050.00 | $2,200.00 | $3,600.00 | $2,760.00 | |
| 91 | 61140200 | STORM SEWER SPEC 12 | 150 | FOOT | $25.00 | $39.75 | $23.00 | $90.00 | $60.60 | |
| 92 | 63000001 | SPBGR TY A 6FT POSTS | 837.5 | FOOT | $23.25 | $22.39 | $29.10 | $23.00 | $29.64 | |
| 93 | 63100070 | TRAF BAR TERM T5 | 2 | EACH | $915.00 | $1,096.50 | $900.00 | $900.00 | $915.00 | |
| 94 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $3,050.00 | $2,919.50 | $3,000.00 | $3,700.00 | $3,407.00 | |
| 95 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $2,850.00 | $2,590.80 | $2,800.00 | $2,800.00 | $2,847.00 | |
| 96 | 63200310 | GUARDRAIL REMOV | 1,098 | FOOT | $3.10 | $5.00 | $3.00 | $3.00 | $3.05 | |
| 97 | 66201120 | CONC SHLD CURB | 35 | FOOT | $1.50 | $42.50 | $50.00 | $150.00 | $56.00 | |
| 98 | 66900200 | NON SPL WASTE DISPOSL | 1,200 | CU YD | $57.00 | $49.80 | $50.00 | $35.00 | $110.00 | |
| 99 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $4,300.00 | $2,448.00 | $5,000.00 | $4,200.00 | $4,320.00 | |
| 100 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,200.00 | $1,836.00 | $1,000.00 | $2,450.00 | $864.00 | |
| 101 | 67000400 | ENGR FIELD OFFICE A | 18 | CAL MO | $1,300.00 | $1,980.00 | $650.00 | $1,800.00 | $1,420.00 | |
| 102 | 67100100 | MOBILIZATION | 1 | L SUM | $187,750.00 | $240,000.00 | $345,000.00 | $189,000.00 | $397,743.00 | |
| 103 | 70100315 | TRAF CONT-PROT 701422 | 4 | EACH | $0.0100 | $6,780.00 | $6,500.00 | $3,350.00 | $8,430.00 | |
| 104 | 70107006 | PAVT MK BLKOUT TAPE 6 | 23,140 | FOOT | $0.0100 | $1.59 | $1.55 | $1.55 | $1.58 | |
| 105 | 70300100 | SHORT TERM PAVT MKING | 952 | FOOT | $0.5000 | $2.00 | $0.9000 | $2.00 | $1.83 | |
| 106 | 70300150 | SHRT TRM PAVT MK REM | 317 | SQ FT | $6.00 | $4.00 | $1.95 | $2.00 | $3.05 | |
| 107 | 70300220 | TEMP PVT MK LINE 4 | 42,363 | FOOT | $0.1600 | $0.1600 | $0.1500 | $0.1500 | $0.1500 | |
| 108 | 70400100 | TEMP CONC BARRIER | 6,375 | FOOT | $16.25 | $12.90 | $23.00 | $19.35 | $23.75 | |
| 109 | 70400200 | REL TEMP CONC BARRIER | 7,837.5 | FOOT | $5.75 | $6.45 | $7.50 | $7.05 | $7.17 | |
| 110 | 70400600 | REL TEMP CONC BAR SO | 1,812.5 | FOOT | $5.75 | $7.80 | $4.00 | $3.80 | $3.86 | |
| 111 | 70600251 | IMP ATTN TEMP NRN TL3 | 4 | EACH | $2,275.00 | $1,480.00 | $5,325.00 | $5,325.00 | $5,415.00 | |
| 112 | 70600352 | IMP ATTN REL NRN TL3 | 4 | EACH | $775.00 | $740.00 | $450.00 | $450.00 | $457.00 | |
| 113 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $30.50 | $30.60 | $30.00 | $30.00 | $30.50 | |
| 114 | 78003110 | PREF PL PM TB LINE 4 | 2,324 | FOOT | $2.50 | $2.55 | $2.50 | $2.50 | $2.55 | |
| 115 | 78004210 | PREF PL PM TB INL L4 | 14,337 | FOOT | $2.05 | $2.10 | $2.05 | $2.05 | $2.08 | |
| 116 | 78100100 | RAISED REFL PAVT MKR | 93 | EACH | $51.00 | $51.00 | $50.00 | $50.00 | $50.85 | |
| 117 | 78200005 | GRDRAIL REF TYPE A | 20 | EACH | $8.10 | $9.18 | $8.00 | $8.00 | $8.14 | |
| 118 | 78200010 | BARR WALL REF TYPE B | 16 | EACH | $13.00 | $13.01 | $12.75 | $12.75 | $13.00 | |
| 119 | 78200011 | BARR WALL REF TYPE C | 16 | EACH | $13.25 | $13.26 | $13.00 | $13.00 | $13.20 | |
| 120 | 78300200 | RAISED REF PVT MK REM | 93 | EACH | $7.00 | $10.00 | $32.25 | $50.00 | $12.20 |