Bid tab 62H88

Let Jun 14, 2019 · District 1 · Lake Sign up free

‹ Jun 2019 results

2019-007-DM

Let date
Friday, June 14, 2019
Contract
62H88 · job page
District
District 1
County
Lake
Highway
Limits
Demolition and site clean-up of three single-family residences on IL 22 between Quentin Road and west of IL 83 in Long Grove and Kildeer.

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 McDonagh Demolition, Inc. Low bidder $122,288
2 Scanlon Excavating & Concrete, Inc. $155,520 +27.2%
3 Martam Construction Incorporated $165,746 +35.5%
4 Copenhaver Construction, Inc. $166,790 +36.4%
5 Phoenix Corporation of the Quad Cities $184,594 +50.9%
6 Lima Contractors $226,374 +85.1%

Bid tab: unit prices 29 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 McDonagh Demoli…#2 Scanlon Excavat…#3 Martam Construc…#4 Copenhaver Cons…#5 Phoenix Corpora…#6 Lima Contractors
1K1004595 PRUN SAFETY/EQUIP CLR1L SUM $1,500.00 $2,500.00 $1,500.00 $1,000.00 $2,000.00 $1,380.00
2X0326864 BRICK SIDEWALK REM242.2SQ FT $5.00 $3.00 $5.00 $5.00 $1.50 $2.36
3X0488100 REM EX SEPTIC TANK3EACH $1,200.00 $3,000.00 $1,500.00 $2,000.00 $3,100.00 $4,105.50
4X2010400 STUMP REMOVAL ONLY30UNIT $12.00 $25.00 $20.00 $30.00 $40.00 $11.50
5Z0007601 BLDG REMOV NO 11L SUM $17,200.00 $25,000.00 $32,000.00 $19,000.00 $21,985.00 $37,262.50
6Z0007602 BLDG REMOV NO 21L SUM $16,700.00 $25,000.00 $24,000.00 $24,000.00 $22,529.00 $34,962.50
7Z0007603 BLDG REMOV NO 31L SUM $16,200.00 $28,000.00 $24,000.00 $26,000.00 $24,750.00 $39,712.50
8Z0015500 DEBRIS REMOVAL1L SUM $9,800.00 $3,500.00 $9,000.00 $20,000.00 $10,750.00 $1,150.00
9Z0030850 TEMP INFO SIGNING51.4SQ FT $6.00 $20.00 $20.00 $20.00 $12.00 $28.75
10Z0049901 R&D NON-FR ASB BLD 11L SUM $5,000.00 $3,500.00 $4,500.00 $5,000.00 $3,800.00 $8,000.00
11Z0049902 R&D NON-FR ASB BLD 21L SUM $100.00 $500.00 $1,000.00 $5,000.00 $1.00 $8,000.00
12Z0049903 R&D NON-FR ASB BLD 31L SUM $3,000.00 $3,500.00 $3,000.00 $5,000.00 $2,500.00 $8,000.00
13Z0064800 SELECTIVE CLEARING1.2UNIT $615.00 $3,000.00 $400.00 $1,000.00 $2,500.00 $230.00
1420100110 TREE REMOV 6-15115UNIT $20.00 $30.00 $22.00 $20.00 $50.00 $21.85
1520100210 TREE REMOV OVER 15148UNIT $25.00 $30.00 $25.00 $30.00 $52.00 $26.55
1621101625 TOPSOIL F & P 6737.9SQ YD $9.50 $8.35 $0.2000 $6.00 $9.50 $9.01
1725000110 SEEDING CL 1A0.14ACRE $5,600.00 $4,500.00 $33,000.00 $6,000.00 $7,500.00 $10,580.00
1825000400 NITROGEN FERT NUTR12.6POUND $6.00 $5.00 $2.00 $1.00 $8.00 $4.60
1925000600 POTASSIUM FERT NUTR12.6POUND $6.00 $5.00 $2.00 $1.00 $8.00 $4.60
2025100105 MULCH METHOD 10.14ACRE $4,000.00 $10,000.00 $1,000.00 $10,000.00 $6,000.00 $15,486.67
2125100630 EROSION CONTR BLANKET737.9SQ YD $2.00 $3.50 $4.00 $3.00 $4.00 $3.72
2228000400 PERIMETER EROS BAR1,129FOOT $3.00 $4.00 $3.00 $3.00 $2.50 $3.45
2330300001 AGG SUBGRADE IMPROVE18CU YD $105.00 $50.00 $85.00 $50.00 $60.00 $161.92
2444000200 DRIVE PAVEMENT REM737.9SQ YD $3.00 $6.00 $8.00 $16.00 $6.00 $16.62
2544000300 CURB REM128.3FOOT $8.00 $7.00 $6.00 $9.00 $3.00 $11.93
2644000600 SIDEWALK REM211.4SQ FT $2.00 $3.00 $5.00 $5.00 $3.00 $1.89
2767000400 ENGR FIELD OFFICE A4.5CAL MO $1,500.00 $500.00 $2,800.00 $1,000.00 $800.00 $1,380.00
2867100100 MOBILIZATION1L SUM $7,400.00 $7,500.00 $9,940.00 $10,000.00 $35,010.65 $16,100.00
2967201000 SEAL ABAN WATER WELLS3EACH $2,500.00 $3,000.00 $3,200.00 $1,000.00 $2,780.00 $3,335.00