2019-007-DM
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | McDonagh Demolition, Inc. Low bidder | $122,288 | ||
| 2 | Scanlon Excavating & Concrete, Inc. | $155,520 | +27.2% | |
| 3 | Martam Construction Incorporated | $165,746 | +35.5% | |
| 4 | Copenhaver Construction, Inc. | $166,790 | +36.4% | |
| 5 | Phoenix Corporation of the Quad Cities | $184,594 | +50.9% | |
| 6 | Lima Contractors | $226,374 | +85.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 McDonagh Demoli… | #2 Scanlon Excavat… | #3 Martam Construc… | #4 Copenhaver Cons… | #5 Phoenix Corpora… | #6 Lima Contractors |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | K1004595 | PRUN SAFETY/EQUIP CLR | 1 | L SUM | $1,500.00 | $2,500.00 | $1,500.00 | $1,000.00 | $2,000.00 | $1,380.00 | |
| 2 | X0326864 | BRICK SIDEWALK REM | 242.2 | SQ FT | $5.00 | $3.00 | $5.00 | $5.00 | $1.50 | $2.36 | |
| 3 | X0488100 | REM EX SEPTIC TANK | 3 | EACH | $1,200.00 | $3,000.00 | $1,500.00 | $2,000.00 | $3,100.00 | $4,105.50 | |
| 4 | X2010400 | STUMP REMOVAL ONLY | 30 | UNIT | $12.00 | $25.00 | $20.00 | $30.00 | $40.00 | $11.50 | |
| 5 | Z0007601 | BLDG REMOV NO 1 | 1 | L SUM | $17,200.00 | $25,000.00 | $32,000.00 | $19,000.00 | $21,985.00 | $37,262.50 | |
| 6 | Z0007602 | BLDG REMOV NO 2 | 1 | L SUM | $16,700.00 | $25,000.00 | $24,000.00 | $24,000.00 | $22,529.00 | $34,962.50 | |
| 7 | Z0007603 | BLDG REMOV NO 3 | 1 | L SUM | $16,200.00 | $28,000.00 | $24,000.00 | $26,000.00 | $24,750.00 | $39,712.50 | |
| 8 | Z0015500 | DEBRIS REMOVAL | 1 | L SUM | $9,800.00 | $3,500.00 | $9,000.00 | $20,000.00 | $10,750.00 | $1,150.00 | |
| 9 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $6.00 | $20.00 | $20.00 | $20.00 | $12.00 | $28.75 | |
| 10 | Z0049901 | R&D NON-FR ASB BLD 1 | 1 | L SUM | $5,000.00 | $3,500.00 | $4,500.00 | $5,000.00 | $3,800.00 | $8,000.00 | |
| 11 | Z0049902 | R&D NON-FR ASB BLD 2 | 1 | L SUM | $100.00 | $500.00 | $1,000.00 | $5,000.00 | $1.00 | $8,000.00 | |
| 12 | Z0049903 | R&D NON-FR ASB BLD 3 | 1 | L SUM | $3,000.00 | $3,500.00 | $3,000.00 | $5,000.00 | $2,500.00 | $8,000.00 | |
| 13 | Z0064800 | SELECTIVE CLEARING | 1.2 | UNIT | $615.00 | $3,000.00 | $400.00 | $1,000.00 | $2,500.00 | $230.00 | |
| 14 | 20100110 | TREE REMOV 6-15 | 115 | UNIT | $20.00 | $30.00 | $22.00 | $20.00 | $50.00 | $21.85 | |
| 15 | 20100210 | TREE REMOV OVER 15 | 148 | UNIT | $25.00 | $30.00 | $25.00 | $30.00 | $52.00 | $26.55 | |
| 16 | 21101625 | TOPSOIL F & P 6 | 737.9 | SQ YD | $9.50 | $8.35 | $0.2000 | $6.00 | $9.50 | $9.01 | |
| 17 | 25000110 | SEEDING CL 1A | 0.14 | ACRE | $5,600.00 | $4,500.00 | $33,000.00 | $6,000.00 | $7,500.00 | $10,580.00 | |
| 18 | 25000400 | NITROGEN FERT NUTR | 12.6 | POUND | $6.00 | $5.00 | $2.00 | $1.00 | $8.00 | $4.60 | |
| 19 | 25000600 | POTASSIUM FERT NUTR | 12.6 | POUND | $6.00 | $5.00 | $2.00 | $1.00 | $8.00 | $4.60 | |
| 20 | 25100105 | MULCH METHOD 1 | 0.14 | ACRE | $4,000.00 | $10,000.00 | $1,000.00 | $10,000.00 | $6,000.00 | $15,486.67 | |
| 21 | 25100630 | EROSION CONTR BLANKET | 737.9 | SQ YD | $2.00 | $3.50 | $4.00 | $3.00 | $4.00 | $3.72 | |
| 22 | 28000400 | PERIMETER EROS BAR | 1,129 | FOOT | $3.00 | $4.00 | $3.00 | $3.00 | $2.50 | $3.45 | |
| 23 | 30300001 | AGG SUBGRADE IMPROVE | 18 | CU YD | $105.00 | $50.00 | $85.00 | $50.00 | $60.00 | $161.92 | |
| 24 | 44000200 | DRIVE PAVEMENT REM | 737.9 | SQ YD | $3.00 | $6.00 | $8.00 | $16.00 | $6.00 | $16.62 | |
| 25 | 44000300 | CURB REM | 128.3 | FOOT | $8.00 | $7.00 | $6.00 | $9.00 | $3.00 | $11.93 | |
| 26 | 44000600 | SIDEWALK REM | 211.4 | SQ FT | $2.00 | $3.00 | $5.00 | $5.00 | $3.00 | $1.89 | |
| 27 | 67000400 | ENGR FIELD OFFICE A | 4.5 | CAL MO | $1,500.00 | $500.00 | $2,800.00 | $1,000.00 | $800.00 | $1,380.00 | |
| 28 | 67100100 | MOBILIZATION | 1 | L SUM | $7,400.00 | $7,500.00 | $9,940.00 | $10,000.00 | $35,010.65 | $16,100.00 | |
| 29 | 67201000 | SEAL ABAN WATER WELLS | 3 | EACH | $2,500.00 | $3,000.00 | $3,200.00 | $1,000.00 | $2,780.00 | $3,335.00 |